9715 S HOLMES AVE 90002

Certificate Information: 9715 S HOLMES AVE 90002

Application / Permit
19014-10000-05102
Plan Check / Job No.
B19LA19679
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF GARAGE TO ACCESSORY DWELLING UNIT AND ADDITION PER AB 494 AND SB 229
Permit Issued
Issued on 9/8/2020
Issuing Office
Current Status
CofO Issued on 6/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/17/2019 APPLICANT
Assigned to Plan Check Engineer 9/24/2019 ARSALAN SHABESTARI
Corrections Issued 9/24/2019 ARSALAN SHABESTARI
Applicant returned to address corrections 2/6/2020 CRISTINA SALAZAR
Plan Check Approved 2/12/2020 FARSHAD ALIMOHAMADI
Issued 9/8/2020 APPLICANT
CofO in Progress 6/16/2022 JOHN KLARIN
Permit Finaled 6/22/2022 DEROLD HAUFF
CofO Issued 6/22/2022 DEROLD HAUFF
Permit Finaled 6/22/2022 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 1/10/2020 RIDWAN HARDY
Construction within easement Cleared 1/10/2020 RIDWAN HARDY
Address approval Cleared 1/30/2020 CELINA MORENO
Community Plan Implem. Overlay Cleared 1/30/2020 JOE LUCKEY
Low Impact Development Cleared 1/30/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 1/30/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 2/10/2020 JUAN ASHTON
Sewer availability Cleared 2/12/2020 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/30/2021 Not Ready for Inspection EUGENE CASSIDY
Underground Mechanical 3/11/2022 Not Ready for Inspection JOHN KLARIN
Excavation/Setback/Form/Re-Bar 3/15/2022 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 3/31/2022 Partial Approval ANSON MAGLASANG
ELECTRICAL-Rough 4/4/2022 Approved ALIZAH MAYAGOITIA
HVAC-Rough 4/4/2022 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 4/4/2022 Corrections Issued ALIZAH MAYAGOITIA
HVAC-Rough 4/7/2022 Approved JOHN KLARIN
PLUMBING-Rough 4/7/2022 Approved JOHN KLARIN
Insulation 4/11/2022 Approved ANSON MAGLASANG
Drywall Nailing 4/13/2022 Approved JOHN KLARIN
Interior/Exterior Lathing 4/13/2022 Approved JOHN KLARIN
Shower Pan 5/10/2022 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 5/19/2022 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 6/2/2022 Approved JOHN KLARIN
Final 6/2/2022 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 6/2/2022 Approved JOHN KLARIN
Green Building Final 6/2/2022 Corrections Issued JOHN KLARIN
Green Building Rough 6/2/2022 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 6/2/2022 SGSOV Approved JOHN KLARIN
Smoke Detectors 6/2/2022 Approved JOHN KLARIN
Pre-Inspection 6/7/2022 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Final 6/15/2022 Approved JOHN KLARIN
Final 6/15/2022 OK to Issue CofO JOHN KLARIN
Green Building Final 6/15/2022 Approved JOHN KLARIN
HVAC-Final 6/15/2022 Approved JOHN KLARIN
PLUMBING-Final 6/15/2022 Approved JOHN KLARIN