12161 W VALLEYHEART DR 91604

Certificate Information: 12161 W VALLEYHEART DR 91604

Application / Permit
19014-10000-05062
Plan Check / Job No.
B19LA19513
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition to ground floor and new 2nd story addition to existing sfd.
Permit Issued
Issued on 1/8/2020
Issuing Office
Metro
Current Status
CofO Issued on 10/28/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/13/2019 APPLICANT
Assigned to Plan Check Engineer 10/3/2019 SAMUEL GONZALEZ
Corrections Issued 10/9/2019 SAMUEL GONZALEZ
Green Plans Picked Up 10/15/2019 APPLICANT
Quality Review Completed 11/6/2019 QUAN NGHIEM
Building Plans Picked Up 11/13/2019 APPLICANT
Plan Check Approved 1/8/2020 SAMUEL GONZALEZ
Issued 1/8/2020 LADBS
CofO in Progress 9/9/2021 CHRISTOPHER DELLEFIELD
No Progress 9/10/2021 MICHAEL PELHAM
CofO in Progress 10/8/2021 MICHAEL PELHAM
Permit Finaled 10/28/2021 MICHAEL SMITH
CofO Issued 10/28/2021 MICHAEL SMITH
Permit Finaled 10/28/2021 MICHAEL SMITH

Permit Application Clearance Information

ZI Cleared 12/16/2019 DAISY BENICIA
Eng Process Fee Ord 176,300 Cleared 12/17/2019 ERIK BEASLEY
Sewer availability Cleared 12/17/2019 ERIK BEASLEY
Low Impact Development Cleared 12/18/2019 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 12/18/2019 THOMAS LANG
Green Code Cleared 1/6/2020 DONALD CRICHLOW

Contact Information

Contractor Owner-Builder       ,
Engineer Singh,, Jasbir; Lic. No.: C38767 16194 EASTRIDGE CT      CHINO HILLS, CA 91709

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/1/2020 Conditional Approval ARAM AVEDISIAN
Footing/Foundation/Slab 4/10/2020 Approved RAYMOND KEHOE
Deputy Drilled-In Anchors 4/15/2020 Approved TROY SANDERS
BUILDING-Rough-Frame 5/19/2020 Partial Approval ARAM AVEDISIAN
Green Building Rough 5/19/2020 Not Ready for Inspection ARAM AVEDISIAN
Deputy Wood Construction 6/2/2020 Conditional Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 6/8/2020 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 6/8/2020 Partial Approval ARAM AVEDISIAN
Green Building Rough 6/8/2020 Approved ARAM AVEDISIAN
HVAC-Rough 6/8/2020 Approved ARAM AVEDISIAN
PLUMBING-Rough 6/8/2020 Partial Approval ARAM AVEDISIAN
Insulation 6/12/2020 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 6/12/2020 Partial Approval ARAM AVEDISIAN
Drywall Nailing 6/16/2020 Approved ARAM AVEDISIAN
Shower Pan 6/22/2020 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 11/17/2020 Partial Approval ARAM AVEDISIAN
Final 8/17/2021 Corrections Issued ARAM AVEDISIAN
Green Building Final 8/17/2021 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 8/17/2021 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 8/17/2021 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 9/3/2021 SGSOV Not Ready LILIANA PORTILLO
ELECTRICAL-Final 9/9/2021 Approved CHRISTOPHER DELLEFIELD
Final 9/9/2021 OK to Issue CofO CHRISTOPHER DELLEFIELD
HVAC-Final 9/9/2021 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Final 9/9/2021 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 9/9/2021 SGSOV Approved CHRISTOPHER DELLEFIELD
Special/Order Compliance 9/10/2021 Corrections Issued MICHAEL PELHAM