9532 N AQUEDUCT AVE 91343

Certificate Information: 9532 N AQUEDUCT AVE 91343

Application / Permit
19014-10000-05055
Plan Check / Job No.
B19LA19478
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING GARAGE TO ADU AND ADDITION PER AB494 AND SB229
Permit Issued
Issued on 10/15/2019
Issuing Office
Valley
Current Status
CofO Issued on 11/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/13/2019 APPLICANT
Assigned to Plan Check Engineer 9/23/2019 ARSALAN SHABESTARI
Corrections Issued 9/23/2019 ARSALAN SHABESTARI
Plan Check Approved 9/25/2019 SERGIO GUTIERREZ
Issued 10/15/2019 LADBS
CofO in Progress 5/4/2021 MICHAEL TEMPLE
Permit Finaled 11/29/2021 MICHAEL SMITH
CofO Issued 11/29/2021 MICHAEL SMITH
Permit Finaled 11/29/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/23/2019 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 9/23/2019 EMIL KYUPELYAN
Roof/Waste drainage to street Cleared 9/23/2019 EMIL KYUPELYAN
Sewer availability Cleared 9/23/2019 EMIL KYUPELYAN
ZI Cleared 9/23/2019 DIANA JIMENEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/6/2019 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 11/14/2019 Approved JACK KARGODORIAN
HVAC-Rough 1/14/2020 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Rough 1/14/2020 Not Ready for Inspection JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 1/28/2020 Approved JACK KARGODORIAN
PLUMBING-Rough 1/28/2020 Approved JACK KARGODORIAN
Wood Frame 1/28/2020 Approved JACK KARGODORIAN
Insulation 2/11/2020 Not Ready for Inspection JACK KARGODORIAN
Insulation 3/9/2020 Approved JACK KARGODORIAN
Drywall Nailing 3/17/2020 Approved CHRISTOPHE COCHRAN
Drywall Nailing 3/20/2020 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 3/20/2020 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/20/2020 Approved DANIEL ORRANTE
Final 10/20/2020 Corrections Issued DANIEL ORRANTE
Green Building Final 10/20/2020 Approved DANIEL ORRANTE
Green Building Rough 10/20/2020 Approved DANIEL ORRANTE
MERV13>=Final 10/20/2020 Approved DANIEL ORRANTE
MERV13>=Rough 10/20/2020 Approved DANIEL ORRANTE
SGSOV-Seismic Gas S/O Valve 10/20/2020 SGSOV Approved DANIEL ORRANTE
Smoke Detectors 10/20/2020 Approved DANIEL ORRANTE
Final 12/14/2020 Not Ready for Inspection ARTHUR SARGSYAN
Pre-Inspection 3/15/2021 Partial Inspection MICHAEL TEMPLE
Sewer 4/5/2021 Approved MICHAEL TEMPLE
Final 4/13/2021 Corrections Issued ARTHUR SARGSYAN
Final 4/20/2021 Corrections Issued ARTHUR SARGSYAN
Final 4/27/2021 Corrections Issued MICHAEL TEMPLE
Final 5/4/2021 OK to Issue CofO MICHAEL TEMPLE