210 N HOOVER ST 90004
Certificate Information: 210 N HOOVER ST 90004
- Application / Permit
- 19014-10000-05006
- Plan Check / Job No.
- B19LA19241
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED GROUND FLOOR ADDITION (23'-3" X32') TO CREATE A STORAGE ROOM. SCOPE WILL ALSO INCLUDE A SECOND STORY ADDITION (13'-6" X 32') TO CREATE NEW DINING ROOM AND FAMILY ROOM, AND A THIRD STORY ADDITION (26' X 32') TO CREATE 1 NEW BATHROOM, 1 NEW BEDROOM, AND A IRREGULAR (5 X 32) COVERED DECK ON THE THIRD FLOOR.
- Permit Issued
- Issued on 9/10/2020
- Issuing Office
- Current Status
- CofO Issued on 1/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2019 | MICHAEL LOPEZ |
| Corrections Issued | 10/2/2019 | MICHAEL LOPEZ |
| Quality Review Completed | 10/5/2019 | STANLEY RAAP |
| Building Plans Picked Up | 10/21/2019 | APPLICANT |
| Applicant returned to address corrections | 4/8/2020 | MICHAEL LOPEZ |
| Green Plans Picked Up | 4/10/2020 | APPLICANT |
| Applicant returned to address corrections | 6/29/2020 | MICHAEL LOPEZ |
| Plan Check Approved | 9/10/2020 | MICHAEL LOPEZ |
| Issued | 9/10/2020 | APPLICANT |
| CofO in Progress | 12/5/2023 | FREDDIE RIVERA |
| CofO Issued | 1/10/2024 | DEROLD HAUFF |
| Permit Finaled | 1/10/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/29/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2020 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 1/29/2020 | GEORGE SUCHAND |
| Sewer availability | Cleared | 1/29/2020 | JEANIE LAM |
| GPI Written Notices | Cleared | 4/8/2020 | MICHAEL LOPEZ |
| Grading Pre-Inspection | Cleared | 4/8/2020 | MICHAEL LOPEZ |
| Green Code | Cleared | 6/19/2020 | VIVIAN LAO |
| Low Impact Development | Cleared | 7/21/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 8/3/2020 | JEANIE LAM |
Contact Information
| Architect | Grist,, John Kenneth; Lic. No.: C4295 | 91 EAST GRAND VIEW AVENUE SIERRA MADRE, CA 91024 |
| Contractor | Owner-Builder | , |
| Engineer | Haro,, Ruben; Lic. No.: C72213 | 1554 CIPRES CT CAMARILLO, CA 93010 |
| Geologist | Bovenizer,, Ernest; Lic. No.: EG2515 | 7622 GODDARD AVENUE LOS ANGELES, CA 90045 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/9/2020 | Partial Approval | DAVID CHAN |
| Footing/Foundation/Slab | 10/9/2020 | Partial Approval | DAVID CHAN |
| Piling/Pier/Caisson | 10/9/2020 | Partial Approval | DAVID CHAN |
| Deputy Reinf. Concrete | 10/15/2020 | No Access for Inspection | ELMER BLAND |
| Excavation/Setback/Form/Re-Bar | 12/7/2020 | Partial Approval | ROBERT VORHIS |
| Footing/Foundation/Slab | 12/7/2020 | Not Ready for Inspection | ROBERT VORHIS |
| METHANE-Barrier | 12/7/2020 | Approved | ROBERT VORHIS |
| METHANE-Subgrade | 12/7/2020 | Approved | ROBERT VORHIS |
| Deputy Reinf. Concrete | 12/10/2020 | No Access for Inspection | ELMER BLAND |
| Deputy Drilled-In Anchors | 12/18/2020 | No Access for Inspection | ELMER BLAND |
| Footing/Foundation/Slab | 12/29/2020 | Approved | ROBERT VORHIS |
| Footing/Foundation/Slab | 2/16/2021 | Partial Approval | ROBERT VORHIS |
| PLUMBING-Rough | 2/16/2021 | Partial Approval | ROBERT VORHIS |
| Deputy Wood Construction | 2/25/2021 | No Access for Inspection | ELMER BLAND |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2021 | Partial Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2021 | Corrections Issued | ROBERT VORHIS |
| Deputy Wood Construction | 7/22/2021 | No Access for Inspection | ELMER BLAND |
| BUILDING-Rough-Frame | 7/30/2021 | Not Ready for Inspection | ROBERT VORHIS |
| ELECTRICAL-Rough | 7/30/2021 | Approved | ROBERT VORHIS |
| HVAC-Rough | 7/30/2021 | Not Ready for Inspection | ROBERT VORHIS |
| MERV13>=Rough | 7/30/2021 | Approved | ROBERT VORHIS |
| METHANE-Rough | 7/30/2021 | Approved | ROBERT VORHIS |
| PLUMBING-Rough | 7/30/2021 | Approved | ROBERT VORHIS |
| BUILDING-Rough-Frame | 12/2/2021 | Approved | HORACE FULTZ |
| Green Building Rough | 12/2/2021 | Approved | HORACE FULTZ |
| Interior/Exterior Lathing | 12/22/2021 | Partial Approval | ALIZAH MAYAGOITIA |
| Drywall Nailing | 1/14/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 1/14/2022 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 1/14/2022 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 12/15/2022 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 12/15/2022 | Partial Approval | RICHARD DOCKUS |
| Shower Pan | 12/21/2022 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 6/22/2023 | Partial Approval | FREDDIE RIVERA |
| Green Building Final | 8/10/2023 | Partial Inspection | FREDDIE RIVERA |
| MERV13>=Final | 8/10/2023 | Corrections Issued | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 8/10/2023 | Partial Inspection | FREDDIE RIVERA |
| Final | 10/30/2023 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 10/30/2023 | Approved | FREDDIE RIVERA |
| Green Building Final | 10/30/2023 | Approved | FREDDIE RIVERA |
| MERV13>=Final | 10/30/2023 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 10/30/2023 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 10/30/2023 | Approved | FREDDIE RIVERA |
| Final | 11/8/2023 | Corrections Issued | FREDDIE RIVERA |
| MERV13>=Final | 11/8/2023 | Conditional Approval | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 11/8/2023 | SGSOV Not Ready | FREDDIE RIVERA |
| Final | 11/15/2023 | OK to Issue CofO | FREDDIE RIVERA |
| MERV13>=Final | 11/15/2023 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 11/15/2023 | SGSOV Approved | FREDDIE RIVERA |