6903 N NESTLE AVE 91335
Certificate Information: 6903 N NESTLE AVE 91335
- Application / Permit
- 19014-10000-04978
- Plan Check / Job No.
- B19LA19131
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Addition to (E) detached garage and conversion of entire building into an Accessory Dwelling Unit per AB 494 and SB 229.
- Permit Issued
- Issued on 6/17/2020
- Issuing Office
- Current Status
- CofO Issued on 5/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2019 | ARSALAN SHABESTARI |
| Corrections Issued | 9/17/2019 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 2/24/2020 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 3/10/2020 | MONICA RAMIREZ |
| Plan Check Approved | 3/16/2020 | HELEN NGUYEN |
| Issued | 6/17/2020 | APPLICANT |
| Building Plans Picked Up | 6/19/2020 | APPLICANT |
| CofO in Progress | 1/27/2022 | VINCENT HANLEY |
| CofO Issued | 5/21/2022 | MICHAEL SMITH |
| Permit Finaled | 5/21/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Hold | Cleared | 9/17/2019 | CYNTHIA RYAN |
| Construction near power lines | Cleared | 12/26/2019 | OSCAR CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2020 | CELINA MORENO |
| ZI | Cleared | 2/24/2020 | ANNA VIDAL |
| Address approval | Cleared | 2/25/2020 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 3/10/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 3/10/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 3/10/2020 | CECILIO NAVARRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/2/2020 | Partial Approval | VINCENT HANLEY |
| Sewer | 7/2/2020 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 7/27/2020 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 7/27/2020 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 7/27/2020 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 9/30/2020 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 9/30/2020 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2020 | Approved | VINCENT HANLEY |
| Gas Test | 9/30/2020 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 9/30/2020 | Approved | VINCENT HANLEY |
| HVAC-Rough | 9/30/2020 | Approved | VINCENT HANLEY |
| Insulation | 9/30/2020 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 9/30/2020 | Approved | VINCENT HANLEY |
| Rough-Elec/Plmb/HVAC | 9/30/2020 | Approved | VINCENT HANLEY |
| Underground Mechanical | 9/30/2020 | Approved | VINCENT HANLEY |
| Wood Frame | 9/30/2020 | Approved | VINCENT HANLEY |
| Insulation | 10/2/2020 | Approved | VINCENT HANLEY |
| Drywall Nailing | 10/13/2020 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 10/13/2020 | Approved | VINCENT HANLEY |
| Shower Pan | 10/13/2020 | Approved | VINCENT HANLEY |
| Final | 7/14/2021 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 7/14/2021 | Not Ready for Inspection | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 7/14/2021 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 7/14/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 1/26/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 1/26/2022 | Approved | VINCENT HANLEY |
| Final | 1/26/2022 | OK to Issue CofO | VINCENT HANLEY |
| Gas Test | 1/26/2022 | Approved | VINCENT HANLEY |
| Green Building Final | 1/26/2022 | Approved | VINCENT HANLEY |
| HVAC-Final | 1/26/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 1/26/2022 | Approved | VINCENT HANLEY |