2921 S OCEAN AVE 90291

Certificate Information: 2921 S OCEAN AVE 90291

Application / Permit
19014-10000-04956
Plan Check / Job No.
B19LA19057
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO (E) GARAGE TO CREATE ACCESORY DWELLING UNIT PER AB 494 AND SB 229 WITH ATTACHED GARAGE.
Permit Issued
Issued on 1/8/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/10/2019 APPLICANT
Assigned to Plan Check Engineer 9/26/2019 EVERARDO SANTOS
Corrections Issued 10/8/2019 EVERARDO SANTOS
Green Plans Picked Up 10/18/2019 APPLICANT
Quality Review Completed 10/28/2019 JOSE RODRIGUEZ
Building Plans Picked Up 10/29/2019 APPLICANT
Plan Check Approved 12/13/2019 EVERARDO SANTOS
Issued 1/8/2020 LADBS
CofO in Progress 10/21/2020 DAVID HEINE
Permit Finaled 2/23/2021 RONALD MYRICK
CofO Issued 2/23/2021 RONALD MYRICK
Permit Finaled 2/23/2021 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 11/5/2019 CELINA MORENO
Specific Plan Cleared 11/7/2019 JEFF KHAU
Green Code Cleared 11/15/2019 EVERARDO SANTOS
Eng Process Fee Ord 176,300 Cleared 11/26/2019 THOMAS LANG
Low Impact Development Cleared 11/26/2019 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 11/26/2019 THOMAS LANG
Sewer availability Cleared 11/27/2019 THOMAS LANG
Coastal Zone Cleared 12/13/2019 JOE LUCKEY
Hydrant and Access approval Cleared 12/13/2019 JEREMY CARTER

Contact Information

Contractor H A S Construction Inc; Lic. No.: 538538-B 11272 WASHINGTON PL      CULVER CITY, CA 90230
Engineer Galbreath,, Sean Martin; Lic. No.: S5653 1386 EAST WALNUT STREET SUITE 202      PASADENA, CA 91106

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/7/2020 Partial Approval DAVID HEINE
ELECTRICAL-Rough 2/14/2020 Partial Approval DAVID HEINE
Footing/Foundation/Slab 2/14/2020 Approved DAVID HEINE
METHANE-Barrier 2/14/2020 Approved DAVID HEINE
METHANE-Subgrade 2/14/2020 Approved DAVID HEINE
Sewer 3/11/2020 Approved DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 3/12/2020 Partial Approval DAVID HEINE
ELECTRICAL-Rough 3/26/2020 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 4/16/2020 Partial Approval DAVID HEINE
PLUMBING-Rough 4/16/2020 Approved DAVID HEINE
ELECTRICAL-Rough 4/30/2020 Approved DAVID HEINE
HVAC-Rough 5/1/2020 Approved DAVID HEINE
Deputy Wood Construction 5/13/2020 Partial Approval DAVID HEINE
BUILDING-Rough-Frame 5/14/2020 Approved DAVID HEINE
Green Building Rough 5/14/2020 Approved DAVID HEINE
METHANE-Rough 5/14/2020 Approved DAVID HEINE
Interior/Exterior Lathing 5/28/2020 Partial Approval DAVID HEINE
Insulation 6/8/2020 Approved DAVID HEINE
Drywall Nailing 6/15/2020 Approved DAVID HEINE
Shower Pan 7/10/2020 Approved DAVID HEINE
Interior/Exterior Lathing 7/20/2020 Approved DAVID HEINE
Excavation/Setback/Form/Re-Bar 8/20/2020 Partial Approval DAVID HEINE
Masonry Wall/Backfill 9/8/2020 Partial Approval DAVID HEINE
Masonry Wall/Backfill 9/11/2020 Partial Approval DAVID HEINE
ELECTRICAL-Final 9/14/2020 Approved DAVID HEINE
HVAC-Final 9/17/2020 Approved DAVID HEINE
PLUMBING-Final 9/17/2020 Approved DAVID HEINE
Final 10/15/2020 Conditional Approval DAVID HEINE
Green Building Final 10/15/2020 Approved DAVID HEINE
SGSOV-Seismic Gas S/O Valve 10/15/2020 SGSOV Approved DAVID HEINE
Smoke Detectors 10/15/2020 Approved DAVID HEINE
Final 10/21/2020 OK to Issue CofO DAVID HEINE
Service/Power Release 11/18/2020 Approved JUAN VALENZUELA
Service/Power Release 12/4/2020 Approved DAVID HEINE
Service/Power Release 12/9/2020 Partial Inspection JUAN VALENZUELA