1849 S KELTON AVE 90025
Certificate Information: 1849 S KELTON AVE 90025
- Application / Permit
- 19014-10000-04922
- Plan Check / Job No.
- B19LA18952
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 2-STORY ACCESSORY DWELLING UNIT W ATTACHED GARAGE AND CARPORT, AT REAR OF LOT.
- Permit Issued
- Issued on 6/7/2021
- Issuing Office
- Current Status
- CofO Issued on 8/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2019 | FERNANDO FLORES |
| Corrections Issued | 10/1/2019 | FERNANDO FLORES |
| Quality Review Completed | 10/15/2019 | ARMEN JIVALAGIAN |
| Green Plans Picked Up | 10/27/2020 | APPLICANT |
| Plan Check Approved | 6/2/2021 | FERNANDO FLORES |
| Issued | 6/7/2021 | APPLICANT |
| Building Plans Picked Up | 8/3/2021 | APPLICANT |
| CofO in Progress | 8/21/2023 | SEAN WIRCH |
| CofO Issued | 8/22/2023 | RONALD MYRICK |
| Permit Finaled | 8/22/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 9/11/2020 | KURT CORRAL |
| City Hist. Cultural Monument | Cleared | 10/8/2020 | LAMBERT GIESSINGER |
| Historic monument | Cleared | 10/8/2020 | LAMBERT GIESSINGER |
| ZI | Cleared | 10/8/2020 | LAMBERT GIESSINGER |
| Green Code | Cleared | 10/12/2020 | VIVIAN LAO |
| Address approval | Cleared | 10/22/2020 | ANTHONY MAINEZ |
| Miscellaneous | Cleared | 10/22/2020 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 10/22/2020 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/26/2020 | ANTHONY MAINEZ |
| Tract Map conditions | Cleared | 1/19/2021 | SARAHI ORTEGA |
| Tract Map conditions | Cleared | 1/19/2021 | SARAHI ORTEGA |
| ZA Case | Cleared | 1/19/2021 | SARAHI ORTEGA |
| Low Impact Development | Cleared | 2/16/2021 | ORVAL HERNANDEZ-MARCI |
| Construction near power lines | Cleared | 3/25/2021 | WALTER RAMIREZ |
| Construction within easement | Cleared | 3/25/2021 | WALTER RAMIREZ |
| Specific Plan | Cleared | 5/5/2021 | FREDDY GARCIA |
| Address approval | Cleared | 5/20/2021 | CATHERINE ADROVER |
| Roof/Waste drainage to street | Cleared | 5/25/2021 | CATHERINE ADROVER |
| GPI Written Notices | Cleared | 5/27/2021 | STANLEY RAAP |
| Grading Pre-Inspection | Cleared | 6/1/2021 | FERNANDO FLORES |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
| Engineer | Rowlands,, James; Lic. No.: C21818 | 10954 SANTA MONICA BLVD LOS ANGELES, CA 90025 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/17/2022 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 4/13/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 4/18/2022 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 4/21/2022 | Corrections Issued | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 5/2/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 5/6/2022 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2022 | Corrections Issued | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2022 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2022 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2022 | Corrections Issued | KENNETH NAGLE |
| Footing/Foundation/Slab | 7/28/2022 | Corrections Issued | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 9/6/2022 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 9/9/2022 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 9/23/2022 | Approved | JOHN KIDWELL |
| Sewer | 9/23/2022 | Approved | JOHN KIDWELL |
| Wood Frame | 9/23/2022 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 9/27/2022 | Not Ready for Inspection | CLAYTON GRAHAM |
| Sewer | 9/27/2022 | Not Ready for Inspection | CLAYTON GRAHAM |
| Gas Test | 10/3/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| Rough-Elec/Plmb/HVAC | 10/3/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 10/3/2022 | SGSOV Not Ready | ASHLEY THOMPSON |
| Sewer | 10/3/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| HVAC-Rough | 10/11/2022 | Partial Approval | MICHAEL PELHAM |
| SGSOV-Seismic Gas S/O Valve | 10/11/2022 | SGSOV Approved | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 10/17/2022 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 10/17/2022 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 10/17/2022 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 10/17/2022 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 10/17/2022 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 10/17/2022 | Partial Approval | STEPHANIE SWANSON |
| METHANE-Barrier | 10/17/2022 | Approved | STEPHANIE SWANSON |
| METHANE-Subgrade | 10/17/2022 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 10/21/2022 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 10/21/2022 | Approved | ASHLEY THOMPSON |
| HVAC-Rough | 10/21/2022 | Approved | ASHLEY THOMPSON |
| METHANE-Rough | 10/21/2022 | Approved | ASHLEY THOMPSON |
| PLUMBING-Rough | 10/21/2022 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 10/25/2022 | Conditional Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 10/28/2022 | Approved | ANDREW NAVE |
| Insulation | 10/28/2022 | Approved | ANDREW NAVE |
| Drywall Nailing | 11/7/2022 | No Access for Inspection | ASHLEY THOMPSON |
| Drywall Nailing | 11/9/2022 | Approved | ASHLEY THOMPSON |
| Final | 2/24/2023 | No Access for Inspection | CLAYTON GRAHAM |
| Green Building Final | 2/24/2023 | No Access for Inspection | CLAYTON GRAHAM |
| Smoke Detectors | 2/24/2023 | No Access for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Final | 3/2/2023 | Corrections Issued | CLAYTON GRAHAM |
| Gas Test | 3/2/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Final | 3/2/2023 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Final | 3/2/2023 | Conditional Approval | CLAYTON GRAHAM |
| ELECTRICAL-Final | 3/7/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Gas Test | 3/7/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 3/7/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 3/10/2023 | Approved | CLAYTON GRAHAM |
| PLUMBING-Final | 3/10/2023 | Partial Inspection | CLAYTON GRAHAM |
| Final | 6/22/2023 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 6/22/2023 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 6/22/2023 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 6/22/2023 | Approved | JESUS PINEDA |
| Final | 7/6/2023 | No Access for Inspection | JEREMY TODD |
| ELECTRICAL-Final | 7/11/2023 | Approved | JEREMY TODD |
| Final | 8/22/2023 | OK to Issue CofO | SEAN WIRCH |