1849 S KELTON AVE 90025

Certificate Information: 1849 S KELTON AVE 90025

Application / Permit
19014-10000-04922
Plan Check / Job No.
B19LA18952
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2-STORY ACCESSORY DWELLING UNIT W ATTACHED GARAGE AND CARPORT, AT REAR OF LOT.
Permit Issued
Issued on 6/7/2021
Issuing Office
Current Status
CofO Issued on 8/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2019 APPLICANT
Assigned to Plan Check Engineer 9/26/2019 FERNANDO FLORES
Corrections Issued 10/1/2019 FERNANDO FLORES
Quality Review Completed 10/15/2019 ARMEN JIVALAGIAN
Green Plans Picked Up 10/27/2020 APPLICANT
Plan Check Approved 6/2/2021 FERNANDO FLORES
Issued 6/7/2021 APPLICANT
Building Plans Picked Up 8/3/2021 APPLICANT
CofO in Progress 8/21/2023 SEAN WIRCH
CofO Issued 8/22/2023 RONALD MYRICK
Permit Finaled 8/22/2023 RONALD MYRICK

Permit Application Clearance Information

Hydrant and Access approval Cleared 9/11/2020 KURT CORRAL
City Hist. Cultural Monument Cleared 10/8/2020 LAMBERT GIESSINGER
Historic monument Cleared 10/8/2020 LAMBERT GIESSINGER
ZI Cleared 10/8/2020 LAMBERT GIESSINGER
Green Code Cleared 10/12/2020 VIVIAN LAO
Address approval Cleared 10/22/2020 ANTHONY MAINEZ
Miscellaneous Cleared 10/22/2020 ANTHONY MAINEZ
Sewer availability Cleared 10/22/2020 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 10/26/2020 ANTHONY MAINEZ
Tract Map conditions Cleared 1/19/2021 SARAHI ORTEGA
Tract Map conditions Cleared 1/19/2021 SARAHI ORTEGA
ZA Case Cleared 1/19/2021 SARAHI ORTEGA
Low Impact Development Cleared 2/16/2021 ORVAL HERNANDEZ-MARCI
Construction near power lines Cleared 3/25/2021 WALTER RAMIREZ
Construction within easement Cleared 3/25/2021 WALTER RAMIREZ
Specific Plan Cleared 5/5/2021 FREDDY GARCIA
Address approval Cleared 5/20/2021 CATHERINE ADROVER
Roof/Waste drainage to street Cleared 5/25/2021 CATHERINE ADROVER
GPI Written Notices Cleared 5/27/2021 STANLEY RAAP
Grading Pre-Inspection Cleared 6/1/2021 FERNANDO FLORES

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,
Engineer Rowlands,, James; Lic. No.: C21818 10954 SANTA MONICA BLVD      LOS ANGELES, CA 90025

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/17/2022 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 4/13/2022 Corrections Issued OGANES TARAKHCHYAN
PLUMBING-Rough 4/18/2022 Partial Approval KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 4/21/2022 Corrections Issued KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 5/2/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 5/6/2022 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 5/19/2022 Corrections Issued BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 5/23/2022 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 6/8/2022 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 6/13/2022 Corrections Issued KENNETH NAGLE
Footing/Foundation/Slab 7/28/2022 Corrections Issued MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 9/6/2022 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 9/9/2022 Partial Approval JOHN KIDWELL
PLUMBING-Rough 9/23/2022 Approved JOHN KIDWELL
Sewer 9/23/2022 Approved JOHN KIDWELL
Wood Frame 9/23/2022 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 9/27/2022 Not Ready for Inspection CLAYTON GRAHAM
Sewer 9/27/2022 Not Ready for Inspection CLAYTON GRAHAM
Gas Test 10/3/2022 Not Ready for Inspection ASHLEY THOMPSON
Rough-Elec/Plmb/HVAC 10/3/2022 Not Ready for Inspection ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 10/3/2022 SGSOV Not Ready ASHLEY THOMPSON
Sewer 10/3/2022 Not Ready for Inspection ASHLEY THOMPSON
HVAC-Rough 10/11/2022 Partial Approval MICHAEL PELHAM
SGSOV-Seismic Gas S/O Valve 10/11/2022 SGSOV Approved MICHAEL PELHAM
BUILDING-Rough-Frame 10/17/2022 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 10/17/2022 Approved STEPHANIE SWANSON
Footing/Foundation/Slab 10/17/2022 Approved STEPHANIE SWANSON
HVAC-Rough 10/17/2022 Corrections Issued STEPHANIE SWANSON
Insulation 10/17/2022 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 10/17/2022 Partial Approval STEPHANIE SWANSON
METHANE-Barrier 10/17/2022 Approved STEPHANIE SWANSON
METHANE-Subgrade 10/17/2022 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 10/21/2022 Corrections Issued ASHLEY THOMPSON
Green Building Rough 10/21/2022 Approved ASHLEY THOMPSON
HVAC-Rough 10/21/2022 Approved ASHLEY THOMPSON
METHANE-Rough 10/21/2022 Approved ASHLEY THOMPSON
PLUMBING-Rough 10/21/2022 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 10/25/2022 Conditional Approval ANDREW NAVE
BUILDING-Rough-Frame 10/28/2022 Approved ANDREW NAVE
Insulation 10/28/2022 Approved ANDREW NAVE
Drywall Nailing 11/7/2022 No Access for Inspection ASHLEY THOMPSON
Drywall Nailing 11/9/2022 Approved ASHLEY THOMPSON
Final 2/24/2023 No Access for Inspection CLAYTON GRAHAM
Green Building Final 2/24/2023 No Access for Inspection CLAYTON GRAHAM
Smoke Detectors 2/24/2023 No Access for Inspection CLAYTON GRAHAM
ELECTRICAL-Final 3/2/2023 Corrections Issued CLAYTON GRAHAM
Gas Test 3/2/2023 Corrections Issued CLAYTON GRAHAM
HVAC-Final 3/2/2023 Corrections Issued CLAYTON GRAHAM
PLUMBING-Final 3/2/2023 Conditional Approval CLAYTON GRAHAM
ELECTRICAL-Final 3/7/2023 Conditional Approval JESUS RODRIGUEZ
Gas Test 3/7/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 3/7/2023 Approved JESUS RODRIGUEZ
HVAC-Final 3/10/2023 Approved CLAYTON GRAHAM
PLUMBING-Final 3/10/2023 Partial Inspection CLAYTON GRAHAM
Final 6/22/2023 Corrections Issued JESUS PINEDA
Green Building Final 6/22/2023 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 6/22/2023 SGSOV Approved JESUS PINEDA
Smoke Detectors 6/22/2023 Approved JESUS PINEDA
Final 7/6/2023 No Access for Inspection JEREMY TODD
ELECTRICAL-Final 7/11/2023 Approved JEREMY TODD
Final 8/22/2023 OK to Issue CofO SEAN WIRCH