11475 W HAMLIN ST 91606

Certificate Information: 11475 W HAMLIN ST 91606

Application / Permit
19014-10000-04917
Plan Check / Job No.
B19LA18919
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE TO ACCESSORY DWELLING UNIT WITH ADDITION (20'-4" X 49'-3") PER AB 494 AND SB 229.
Permit Issued
Issued on 4/29/2021
Issuing Office
Current Status
Issued on 4/29/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/6/2019 APPLICANT
Assigned to Plan Check Engineer 9/16/2019 FARSHAD ALIMOHAMADI
Corrections Issued 9/16/2019 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 11/8/2019 CRISTINA SALAZAR
Plan Check Approved 11/12/2019 KEVIN MORALES
Issued 4/29/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/16/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 9/16/2019 ERIK BEASLEY
Permit Cleared 9/16/2019 ERIK BEASLEY
Sewer availability Cleared 9/16/2019 ERIK BEASLEY
ZA Case Cleared 9/16/2019 JOE LUCKEY
Construction near power lines Cleared 11/5/2019 OSCAR CASTRO
Low Impact Development Cleared 11/5/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 11/5/2019 THOMAS LANG
Trees in Parkway Cleared 11/8/2019 ADRIAN SANCHEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/26/2022 Conditional Approval CALEB MEISTER
Excavation/Setback/Form/Re-Bar 5/2/2022 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 5/2/2022 Not Ready for Inspection JENNIFER RABUCHIN
METHANE-Barrier 5/2/2022 Approved JENNIFER RABUCHIN
METHANE-Subgrade 5/2/2022 Approved JENNIFER RABUCHIN