6421 E CRESCENT ST 90042
Certificate Information: 6421 E CRESCENT ST 90042
- Application / Permit
- 19014-10000-04856
- Plan Check / Job No.
- B19LA18738
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1ST AND 2ND FLOOR ADDITIONS TO A SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 1/28/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2019 | JOHNNY WU |
| Corrections Issued | 9/24/2019 | JOHNNY WU |
| Green Plans Picked Up | 9/30/2019 | APPLICANT |
| Quality Review Completed | 10/3/2019 | JOSE RODRIGUEZ |
| Plan Check Approved | 12/20/2019 | JOHNNY WU |
| Issued | 1/28/2020 | LADBS |
| CofO in Progress | 1/16/2021 | CRAIG VAUGHAN |
| Permit Finaled | 1/23/2021 | DEROLD HAUFF |
| CofO Issued | 1/23/2021 | DEROLD HAUFF |
| Permit Finaled | 1/23/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/24/2019 | JOHNNY WU |
| Eng Process Fee Ord 176,300 | Cleared | 11/19/2019 | CELINA MORENO |
| Sewer availability | Cleared | 11/19/2019 | CELINA MORENO |
| HPOZ | Cleared | 12/10/2019 | LAMBERT GIESSINGER |
| ZI | Cleared | 12/10/2019 | LAMBERT GIESSINGER |
| Green Code | Cleared | 12/16/2019 | VIVIAN LAO |
| Low Impact Development | Cleared | 12/16/2019 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 12/16/2019 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Galbreath,, Sean Martin; Lic. No.: S5653 | 1386 EAST WALNUT STREET SUITE 202 PASADENA, CA 91106 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/21/2020 | Not Ready for Inspection | COREY HUPP |
| Footing/Foundation/Slab | 4/23/2020 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 5/15/2020 | Partial Approval | CRAIG VAUGHAN |
| Underground Mechanical | 5/15/2020 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 7/17/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Green Building Rough | 7/17/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 7/17/2020 | Approved | OSVALDO PARAMO |
| Deputy Wood Construction | 7/21/2020 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2020 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 7/28/2020 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 7/28/2020 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 7/28/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/3/2020 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 8/3/2020 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/3/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Wood Frame | 8/3/2020 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/5/2020 | Partial Approval | THOMAS LOGRASSO |
| Insulation | 8/17/2020 | Corrections Issued | THOMAS LOGRASSO |
| Drywall Nailing | 8/24/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 8/24/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 9/15/2020 | Approved | CRAIG VAUGHAN |
| Service/Power Release | 10/20/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 10/26/2020 | Not Ready for Inspection | COREY HUPP |
| HVAC-Final | 11/20/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Final | 11/20/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Final | 11/24/2020 | Corrections Issued | COREY HUPP |
| HVAC-Final | 12/1/2020 | Approved | CRAIG VAUGHAN |
| Final | 1/11/2021 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 1/11/2021 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 1/11/2021 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 1/11/2021 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 1/15/2021 | Approved | CRAIG VAUGHAN |
| Final | 1/15/2021 | OK to Issue CofO | CRAIG VAUGHAN |
| Gas Test | 1/15/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 1/15/2021 | Approved | CRAIG VAUGHAN |