811 N HAVERFORD AVE 90272
Certificate Information: 811 N HAVERFORD AVE 90272
- Application / Permit
- 19014-10000-04852
- Plan Check / Job No.
- B19LA18736
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW ENCLOSED GLASS STRUCTURE COVERED PATIO OVER AN (E) SECOND FLOOR. SUN ROOM.
- Permit Issued
- Issued on 2/24/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/13/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/5/2019 | APPLICANT |
| Green Plans Picked Up | 9/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2019 | ZAW HAN |
| Corrections Issued | 9/23/2019 | ZAW HAN |
| Quality Review Completed | 9/27/2019 | HERNAN ARREOLA |
| Building Plans Picked Up | 10/1/2019 | APPLICANT |
| Applicant returned to address corrections | 11/7/2019 | ZAW HAN |
| Plan Check Approved | 11/19/2019 | ZAW HAN |
| Issued | 2/24/2020 | LADBS |
| CofO in Progress | 6/22/2020 | ANDREW NAVE |
| CofO Issued | 8/13/2020 | VINCENT COTTON |
| Permit Finaled | 8/13/2020 | VINCENT COTTON |
Permit Application Clearance Information
| "Q" conditions | Cleared | 10/4/2019 | TREVOR MARTIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2019 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 10/7/2019 | ANTHONY MAINEZ |
| Green Code | Cleared | 11/7/2019 | COLIN LOREDO |
| Grading Pre-Inspection | Cleared | 11/19/2019 | ZAW HAN |
Contact Information
| Contractor | I Team Builders And Design Inc; Lic. No.: 1029756-B | 22647 VENTURA BLVD #265 WOODLAND HILLS, CA 91364 |
| Engineer | Choi,, David; Lic. No.: S4784 | 1327 LOMA AVENUE LONG BEACH, CA 90804 |
| Engineer | Nelson,, Mike Jay; Lic. No.: C62770 | 14845 SW MURRAY SCH DR 110 PMB 306 BEAVERTON, OR 97007 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 3/10/2020 | Corrections Issued | ANDREW NAVE |
| Green Building Rough | 3/10/2020 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 3/19/2020 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 5/22/2020 | Approved | ANDREW NAVE |
| Drywall Nailing | 5/27/2020 | Approved | ANDREW NAVE |
| Final | 6/2/2020 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 6/2/2020 | Approved | ANDREW NAVE |
| Green Building Final | 6/2/2020 | Approved | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 6/2/2020 | SGSOV Approved | ANDREW NAVE |
| Smoke Detectors | 6/2/2020 | Approved | ANDREW NAVE |