1117 S WILTON PL 90019

Certificate Information: 1117 S WILTON PL 90019

Application / Permit
19014-10000-04833
Plan Check / Job No.
B19LA18671
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
FOR SINGLE STORY ADDITION WITH ROOF DECK TO SFD
Permit Issued
Issued on 2/24/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/27/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/4/2019 APPLICANT
Assigned to Plan Check Engineer 9/12/2019 ARSALAN SHABESTARI
Corrections Issued 9/12/2019 ARSALAN SHABESTARI
Plan Check Approved 2/4/2020 ADAM HEGAZI
Issued 2/24/2020 LADBS
CofO in Progress 12/3/2020 KATHRYN BUTTERWORTH
Permit Finaled 10/27/2021 DEROLD HAUFF
CofO Issued 10/27/2021 DEROLD HAUFF
Permit Finaled 10/27/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/12/2019 JEANETTE VONG
HPOZ Cleared 9/12/2019 BRADLEY FURUYA
Miscellaneous Cleared 9/12/2019 BRADLEY FURUYA
Miscellaneous Cleared 9/12/2019 RICHARD REASER
Roof/Waste drainage to street Cleared 9/12/2019 JEANETTE VONG
Flood clearance Cleared 1/9/2020 BRYAN GATHUKA

Contact Information

Engineer Cook,, Aaron William; Lic. No.: C80362 45609 JAGUAR WAY      TEMECULA, CA 92592
Engineer Kim,, Jin; Lic. No.: C64433 5 MONTELENA      IRVINE, CA 92602

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/4/2020 Approved HORACE FULTZ
Excavation/Setback/Form/Re-Bar 3/4/2020 Corrections Issued HORACE FULTZ
Excavation/Setback/Form/Re-Bar 3/17/2020 Approved SCOTT FINNILA
Wood Frame 3/24/2020 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 3/27/2020 Partial Approval KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 4/23/2020 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Rough 4/23/2020 Approved KATHRYN BUTTERWORTH
FLOOD-Proofing Certificate 4/23/2020 Approved KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 4/23/2020 Partial Approval KATHRYN BUTTERWORTH
METHANE-Rough 4/23/2020 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 7/23/2020 Partial Approval KATHRYN BUTTERWORTH
Insulation 7/23/2020 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 7/23/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Wood Frame 7/23/2020 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 10/2/2020 Approved KATHRYN BUTTERWORTH
Drywall Nailing 10/2/2020 Approved KATHRYN BUTTERWORTH
FLOOD-Elevation Certificate 11/16/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 11/16/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Footing/Foundation/Slab 11/16/2020 Partial Approval KATHRYN BUTTERWORTH
METHANE-Barrier 11/16/2020 Approved KATHRYN BUTTERWORTH
METHANE-Subgrade 11/16/2020 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 11/16/2020 SGSOV Approved KATHRYN BUTTERWORTH
Smoke Detectors 11/16/2020 Approved KATHRYN BUTTERWORTH
FLOOD-Elevation Certificate 12/3/2020 Approved KATHRYN BUTTERWORTH
Final 12/3/2020 OK to Issue CofO KATHRYN BUTTERWORTH
Footing/Foundation/Slab 12/3/2020 Approved KATHRYN BUTTERWORTH