3632 S WEST BLVD 90016
Certificate Information: 3632 S WEST BLVD 90016
- Application / Permit
- 19014-10000-04799
- Plan Check / Job No.
- B19LA18542
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (E) GARAGE AND REC ROOM CONVERTED TO ACCESSORY DWELLING UNIT WITH 10'x32' IRREGULAR ADDITION. PART OF GARAGE CONVERTED TO STORAGE (195 SF) . WORK PER ENGR DESIGN.
- Permit Issued
- Issued on 10/28/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2019 | GEORGE ALVAREZ |
| Corrections Issued | 9/25/2019 | GEORGE ALVAREZ |
| Quality Review Completed | 9/28/2019 | STANLEY RAAP |
| Building Plans Picked Up | 10/9/2019 | APPLICANT |
| Green Plans Picked Up | 10/10/2019 | APPLICANT |
| Plan Check Approved | 1/28/2020 | GEORGE ALVAREZ |
| Issued | 10/28/2020 | APPLICANT |
| CofO in Progress | 12/3/2021 | AMY COLIN |
| CofO in Progress | 12/8/2021 | AMY COLIN |
| CofO in Progress | 12/8/2021 | AMY COLIN |
| CofO in Progress | 12/8/2021 | JOAQUIN GREENOUGH |
| CofO in Progress | 12/8/2021 | AMY COLIN |
| Permit Finaled | 12/17/2021 | DEROLD HAUFF |
| CofO Issued | 12/17/2021 | DEROLD HAUFF |
| Permit Finaled | 12/17/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 12/14/2019 | RIDWAN HARDY |
| Construction within easement | Cleared | 12/14/2019 | RIDWAN HARDY |
| Address approval | Cleared | 12/31/2019 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 12/31/2019 | CELINA MORENO |
| ZA Case | Cleared | 12/31/2019 | TERRI OSBORNE |
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2020 | CELINA MORENO |
| Green Code | Cleared | 1/14/2020 | KHEDER ALRAZAA |
| Sewer availability | Cleared | 1/14/2020 | CELINA MORENO |
Contact Information
| Contractor | Raw Development Inc; Lic. No.: 989611-B | 4859 W SLAUSON AVENUE #377 LOS ANGELES, CA 90056 |
| Engineer | Stewart,, Carl William; Lic. No.: C86681 | 8811 GENTLE WIND DR CORONA, CA 92883 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/14/2020 | Partial Inspection | SCOTT FINNILA |
| Sewer | 12/14/2020 | Approved | SCOTT FINNILA |
| Underground Mechanical | 12/14/2020 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 12/22/2020 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 2/19/2021 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Rough | 2/19/2021 | Partial Inspection | DAVID FEILER |
| Green Building Rough | 2/19/2021 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 3/22/2021 | Approved | DAVID FEILER |
| HVAC-Rough | 3/22/2021 | Approved | DAVID FEILER |
| PLUMBING-Rough | 3/22/2021 | Approved | DAVID FEILER |
| Wood Frame | 3/22/2021 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 4/15/2021 | Approved | DAVID FEILER |
| Green Building Rough | 4/15/2021 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 4/27/2021 | Corrections Issued | ALAN MORELOS |
| Pre-Inspection | 4/27/2021 | Partial Inspection | DEANDRE HOFFMAN |
| Insulation | 5/5/2021 | Not Ready for Inspection | AMY COLIN |
| Pre-Inspection | 5/5/2021 | Partial Inspection | WILLIAM WREN |
| Insulation | 5/13/2021 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 5/13/2021 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 6/7/2021 | Approved | WILLIAM WREN |
| Final | 9/2/2021 | Corrections Issued | DAVID FEILER |
| Green Building Final | 9/2/2021 | Approved | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 9/2/2021 | SGSOV Not Ready | DAVID FEILER |
| Smoke Detectors | 9/2/2021 | Approved | DAVID FEILER |
| Final | 9/21/2021 | Partial Inspection | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 9/21/2021 | SGSOV Approved | DAVID FEILER |
| Final | 10/25/2021 | Conditional Approval | AMY COLIN |
| ELECTRICAL-Final | 12/2/2021 | Approved | AMY COLIN |
| Final | 12/2/2021 | OK to Issue CofO | AMY COLIN |
| HVAC-Final | 12/2/2021 | Approved | AMY COLIN |
| PLUMBING-Final | 12/2/2021 | Approved | AMY COLIN |
| Service/Power Release | 12/8/2021 | Approved | AMY COLIN |