185 1/2 W VERNON AVE 90037

Certificate Information: 185 1/2 W VERNON AVE 90037

Application / Permit
19014-10000-04763
Plan Check / Job No.
B19LA18404
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 15'6" X 20'-2" TO FIRST STORY & 30' X 20'2" IRREGULAR SHAPED 2ND STORY ADDITON TO THE EXISTING 20' X 20' GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) WORK PER ENGINEERING
Permit Issued
Issued on 2/18/2021
Issuing Office
Current Status
CofO Issued on 5/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/30/2019 APPLICANT
Assigned to Plan Check Engineer 9/10/2019 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 9/10/2019 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 9/13/2019 JASON HEALEY
Building Plans Picked Up 9/19/2019 APPLICANT
Green Plans Picked Up 10/10/2019 APPLICANT
Plan Check Approved 2/18/2021 SEWADA ZADOORAN MILAGARDI
Issued 2/18/2021 APPLICANT
CofO in Progress 5/19/2022 JOAQUIN GREENOUGH
CofO in Progress 5/19/2022 JOAQUIN GREENOUGH
Permit Finaled 5/21/2022 DEROLD HAUFF
CofO Issued 5/21/2022 DEROLD HAUFF
Permit Finaled 5/21/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/26/2019 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 9/26/2019 JEANIE LAM
Miscellaneous Cleared 9/26/2019 ANNA VIDAL
Hydrant and Access approval Cleared 12/6/2019 JOHN CONNEALLY
Low Impact Development Cleared 12/17/2019 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 12/19/2019 THOMAS LANG
Sewer availability Cleared 12/19/2019 THOMAS LANG
Green Code Cleared 12/30/2019 KHEDER ALRAZAA
Project located in CRA area Cleared 12/30/2019 GRACIELA ACOSTA
Construction near power lines Cleared 1/5/2021 RIDWAN HARDY
Hold Cleared 3/2/2021 JASON SHEETS

Contact Information

Contractor Owner-Builder       ,
Engineer Segovia,, Felipe; Lic. No.: C41102 2622 DORSET DR      TORRANCE, CA 90503

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/11/2021 Partial Approval SCOTT FINNILA
Underground Mechanical 3/11/2021 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 3/17/2021 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 4/13/2021 Partial Approval FREDDIE RIVERA
ELECTRICAL-Rough 5/7/2021 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 5/7/2021 Approved ROBERT MCDOWELL
PLUMBING-Rough 5/7/2021 Approved ROBERT MCDOWELL
Shower Pan 5/7/2021 Approved ROBERT MCDOWELL
Underground Mechanical 5/7/2021 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 6/22/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Rough 6/22/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Rough-Elec/Plmb/HVAC 6/22/2021 Corrections Issued KATHRYN BUTTERWORTH
Shower Pan 6/22/2021 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Rough 6/24/2021 Partial Inspection DAVID FEILER
HVAC-Rough 6/24/2021 Not Ready for Inspection DAVID FEILER
Insulation 6/24/2021 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 6/24/2021 Partial Inspection DAVID FEILER
Rough-Elec/Plmb/HVAC 6/24/2021 Corrections Issued DAVID FEILER
Shower Pan 6/24/2021 Partial Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 7/21/2021 Partial Approval ELMER BLAND
BUILDING-Rough-Frame 8/27/2021 Approved HORACE FULTZ
Green Building Rough 8/27/2021 Approved HORACE FULTZ
HVAC-Rough 8/27/2021 Approved HORACE FULTZ
Insulation 9/2/2021 Approved ALAN MORELOS
Interior/Exterior Lathing 9/8/2021 Partial Approval ASHLEY THOMPSON
Drywall Nailing 9/10/2021 Approved ALAN MORELOS
ELECTRICAL-Final 1/12/2022 Approved JOAQUIN GREENOUGH
Final 1/12/2022 Corrections Issued JOAQUIN GREENOUGH
Green Building Final 1/12/2022 Approved JOAQUIN GREENOUGH
HVAC-Final 1/12/2022 Approved JOAQUIN GREENOUGH
PLUMBING-Final 1/12/2022 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 1/12/2022 SGSOV Not Ready JOAQUIN GREENOUGH
Service/Power Release 1/12/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Smoke Detectors 1/12/2022 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Final 2/11/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Final 2/11/2022 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Final 2/11/2022 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Final 2/11/2022 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 2/11/2022 SGSOV Not Ready JOAQUIN GREENOUGH
Service/Power Release 2/11/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Smoke Detectors 2/11/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Final 4/19/2022 Corrections Issued JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 4/19/2022 SGSOV Not Ready JOAQUIN GREENOUGH
Smoke Detectors 4/19/2022 Corrections Issued JOAQUIN GREENOUGH
Final 4/25/2022 Corrections Issued JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 4/25/2022 SGSOV Not Ready JOAQUIN GREENOUGH
Smoke Detectors 4/25/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Final 5/18/2022 OK to Issue CofO JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 5/18/2022 SGSOV Approved JOAQUIN GREENOUGH
Smoke Detectors 5/18/2022 Approved JOAQUIN GREENOUGH
Final 5/19/2022 OK to Issue CofO JOAQUIN GREENOUGH
Service/Power Release 5/19/2022 Approved JOAQUIN GREENOUGH