2348 E EADS ST 90031

Certificate Information: 2348 E EADS ST 90031

Application / Permit
19014-10000-04753
Plan Check / Job No.
B19LA18362
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SECOND STORY ADDITION OF 761 SQ/FT TO EXISTING SFD "COMPLY WITH DEPARTMENT ORDER effective date 09/21/2009. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 10/28/2021
Issuing Office
Current Status
CofO Issued on 3/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/30/2019 APPLICANT
Assigned to Plan Check Engineer 9/12/2019 ADAM HEGAZI
Green Plans Picked Up 9/13/2019 APPLICANT
Corrections Issued 9/18/2019 ADAM HEGAZI
Quality Review Completed 9/22/2019 YOUNG KIM
Plan Check Approved 3/6/2020 ADAM HEGAZI
Issued 10/28/2021 APPLICANT
Building Plans Picked Up 10/29/2021 APPLICANT
CofO in Progress 3/1/2023 COREY HUPP
CofO Issued 3/21/2023 DANIEL SANCHEZ
Permit Finaled 3/21/2023 DANIEL SANCHEZ

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/7/2020 THOMAS LANG
ZI Cleared 2/7/2020 JOE LUCKEY
Green Code Cleared 3/5/2020 ADAM HEGAZI
Low Impact Development Cleared 3/5/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 3/5/2020 THOMAS LANG

Contact Information

Contractor D C L A Design Build Inc; Lic. No.: 1060451-B 2241 FERNLEAF      LOS ANGELES, CA 90031
Engineer Garcia,, Ricardo Ray; Lic. No.: C66957 27702 QUINCY ST      CASTAIC, CA 91384
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

RUBEN PEREZ, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT NILES, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
MARK BEVELAQUA, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL SANCHEZ, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
COREY HUPP, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
EMIL OPFFER, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 1/14/2022 No Access for Inspection ALFREDO BALANDRA
Excavation/Setback/Form/Re-Bar 1/18/2022 Corrections Issued TIMOTHY MCCURDY
Footing/Foundation/Slab 1/18/2022 Partial Approval TIMOTHY MCCURDY
BUILDING-Rough-Frame 2/1/2022 Partial Inspection ALFREDO BALANDRA
PLUMBING-Rough 2/1/2022 Corrections Issued ALFREDO BALANDRA
PLUMBING-Rough 2/4/2022 Partial Inspection ROBERT MINASSIANS
Special/Order Compliance 2/4/2022 Partial Inspection PIERRE VEGA
BUILDING-Rough-Frame 2/8/2022 Corrections Issued TIMOTHY MCCURDY
PLUMBING-Rough 2/8/2022 Partial Approval TIMOTHY MCCURDY
BUILDING-Rough-Frame 2/24/2022 Partial Approval TIMOTHY MCCURDY
Pre-Inspection 2/24/2022 Approved TIMOTHY MCCURDY
Floor/Roof Diaphrgm/Shear Wall 3/4/2022 Partial Inspection ROBERT MINASSIANS
Insulation 3/4/2022 Conditional Approval ROBERT MINASSIANS
Floor/Roof Diaphrgm/Shear Wall 3/14/2022 Partial Approval TIMOTHY MCCURDY
ELECTRICAL-Rough 5/6/2022 Corrections Issued COREY HUPP
HVAC-Rough 5/6/2022 Corrections Issued COREY HUPP
PLUMBING-Rough 5/6/2022 Corrections Issued COREY HUPP
BUILDING-Rough-Frame 5/20/2022 Not Ready for Inspection COREY HUPP
ELECTRICAL-Rough 5/20/2022 Approved COREY HUPP
Green Building Rough 5/20/2022 Not Ready for Inspection COREY HUPP
PLUMBING-Rough 5/20/2022 Approved COREY HUPP
BUILDING-Rough-Frame 7/5/2022 Corrections Issued ALFREDO BALANDRA
Green Building Rough 7/5/2022 Approved ALFREDO BALANDRA
HVAC-Rough 7/5/2022 Partial Approval ALFREDO BALANDRA
MERV13>=Rough 7/5/2022 Approved ALFREDO BALANDRA
BUILDING-Rough-Frame 7/11/2022 Corrections Issued ROBERT MINASSIANS
Deputy Wood Construction 7/11/2022 Approved ROBERT MINASSIANS
HVAC-Rough 7/11/2022 Approved ROBERT MINASSIANS
Insulation 7/15/2022 Not Ready for Inspection COREY HUPP
BUILDING-Rough-Frame 8/2/2022 Approved COREY HUPP
Insulation 8/2/2022 Approved COREY HUPP
Drywall Nailing 8/9/2022 Approved COREY HUPP
Interior/Exterior Lathing 8/9/2022 Partial Approval COREY HUPP
Interior/Exterior Lathing 8/23/2022 Not Ready for Inspection COREY HUPP
Shower Pan 8/23/2022 Approved COREY HUPP
Interior/Exterior Lathing 8/26/2022 Approved COREY HUPP
Final 12/5/2022 Partial Inspection COREY HUPP
Footing/Foundation/Slab 12/5/2022 Approved COREY HUPP
Green Building Final 12/5/2022 Not Ready for Inspection COREY HUPP
MERV13>=Final 12/5/2022 Not Ready for Inspection COREY HUPP
SGSOV-Seismic Gas S/O Valve 12/5/2022 SGSOV Approved COREY HUPP
Smoke Detectors 12/5/2022 Corrections Issued COREY HUPP
Final 1/18/2023 Conditional Approval COREY HUPP
Green Building Final 1/18/2023 Approved COREY HUPP
MERV13>=Final 1/18/2023 Approved COREY HUPP
Smoke Detectors 1/18/2023 Approved COREY HUPP