1429 S 12TH AVE 90019

Certificate Information: 1429 S 12TH AVE 90019

Application / Permit
19014-10000-04683
Plan Check / Job No.
B19LA18051
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
ADDITION TO EXISTING RECREATION ROOM. LAUNDRY ADDITION. NO INTERIOR ACCESS BETWEEN RECREATION ROOM AND LAUNDRY ROOM.
Permit Issued
Issued on 2/10/2020
Issuing Office
Metro
Current Status
CofO Issued on 2/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/27/2019 APPLICANT
Assigned to Plan Check Engineer 9/5/2019 ALBERT SERVIN
Corrections Issued 9/10/2019 ALBERT SERVIN
Building Plans Picked Up 10/10/2019 APPLICANT
Quality Review Completed 2/3/2020 KEN GILL
Plan Check Approved 2/5/2020 ALBERT SERVIN
Issued 2/10/2020 LADBS
CofO in Progress 11/3/2021 STUART CHAPMAN
No Progress 1/26/2022 STUART CHAPMAN
CofO in Progress 1/31/2022 STUART CHAPMAN
Permit Finaled 2/1/2022 DEROLD HAUFF
CofO Issued 2/1/2022 DEROLD HAUFF
Permit Finaled 2/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/27/2019 EMIL KYUPELYAN
Roof/Waste drainage to street Cleared 11/27/2019 EMIL KYUPELYAN
Sewer availability Cleared 11/27/2019 EMIL KYUPELYAN
Green Code Cleared 12/4/2019 KHEDER ALRAZAA
Community Plan Implem. Overlay Cleared 1/29/2020 KYLE WINSTON

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/19/2020 Partial Inspection ROBERT VORHIS
Footing/Foundation/Slab 3/25/2020 Corrections Issued ALEJANDRO DE ARTOLA
METHANE-Barrier 3/25/2020 Not Ready for Inspection ALEJANDRO DE ARTOLA
METHANE-Subgrade 3/25/2020 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 4/9/2020 Not Ready for Inspection STUART CHAPMAN
METHANE-Barrier 4/9/2020 Not Ready for Inspection STUART CHAPMAN
METHANE-Subgrade 4/9/2020 Not Ready for Inspection STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 4/14/2020 Not Ready for Inspection STUART CHAPMAN
Footing/Foundation/Slab 4/14/2020 Not Ready for Inspection STUART CHAPMAN
METHANE-Barrier 4/14/2020 Not Ready for Inspection STUART CHAPMAN
METHANE-Subgrade 4/14/2020 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 4/16/2020 Not Ready for Inspection STUART CHAPMAN
METHANE-Barrier 4/16/2020 Not Ready for Inspection STUART CHAPMAN
METHANE-Subgrade 4/16/2020 Approved STUART CHAPMAN
Footing/Foundation/Slab 4/22/2020 Approved STUART CHAPMAN
METHANE-Barrier 4/22/2020 Approved STUART CHAPMAN
BUILDING-Rough-Frame 6/17/2020 Not Ready for Inspection STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 6/17/2020 Partial Approval STUART CHAPMAN
Green Building Rough 6/17/2020 Not Ready for Inspection STUART CHAPMAN
METHANE-Rough 6/17/2020 Not Ready for Inspection STUART CHAPMAN
Wood Frame 6/17/2020 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Rough 8/14/2020 Approved STUART CHAPMAN
Wood Frame 8/14/2020 Conditional Approval STUART CHAPMAN
Interior/Exterior Lathing 9/4/2020 Partial Approval STUART CHAPMAN
Insulation 9/16/2020 Approved STUART CHAPMAN
Drywall Nailing 10/8/2020 Approved STUART CHAPMAN
Interior/Exterior Lathing 10/14/2020 Approved STUART CHAPMAN
BUILDING-Rough-Frame 11/23/2020 Approved STUART CHAPMAN
Final 11/23/2020 Conditional Approval STUART CHAPMAN
Green Building Final 11/23/2020 Approved STUART CHAPMAN
Green Building Rough 11/23/2020 Approved STUART CHAPMAN
METHANE-Final 11/23/2020 Approved STUART CHAPMAN
METHANE-Rough 11/23/2020 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 11/23/2020 SGSOV Approved STUART CHAPMAN
Smoke Detectors 11/23/2020 Approved STUART CHAPMAN
Final 1/26/2022 Corrections Issued STUART CHAPMAN
Final 1/31/2022 OK to Issue CofO STUART CHAPMAN