1520-1522 S BURNSIDE AVE 90019
Certificate Information: 1520-1522 S BURNSIDE AVE 90019
- Application / Permit
- 19014-10000-04668
- Plan Check / Job No.
- B19LA18002
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- INTERIOR REMODEL FOR EXISTING 2 STORY 2 UNIT DWELLING PROPOSED ADDITION OF 59.45 SQFT FOR EACH FLOOR PROPOSED DECK AND BALCONY OF 80SQFT NEW STEEL STAIRS AT REAR
- Permit Issued
- Issued on 10/29/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2019 | JOHNNY WU |
| Green Plans Picked Up | 9/10/2019 | APPLICANT |
| Corrections Issued | 9/16/2019 | JOHNNY WU |
| Quality Review Completed | 10/1/2019 | JOSE RODRIGUEZ |
| Plan Check Approved | 1/30/2020 | JOHNNY WU |
| Issued | 10/29/2020 | APPLICANT |
| Building Plans Picked Up | 10/30/2020 | APPLICANT |
| CofO in Progress | 8/8/2022 | JOSE AVILA |
| No Progress | 9/29/2022 | JOSE AVILA |
| CofO in Progress | 11/10/2022 | JOSE AVILA |
| Permit Finaled | 11/12/2022 | DEROLD HAUFF |
| CofO Issued | 11/12/2022 | DEROLD HAUFF |
| Permit Finaled | 11/12/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Abandoned oil well | Cleared | 12/3/2019 | JEREMY CARTER |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2019 | THOMAS LANG |
| Highway dedication | Cleared | 12/3/2019 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 12/3/2019 | THOMAS LANG |
| Sewer availability | Cleared | 12/3/2019 | THOMAS LANG |
| Housing rent stabilization | Cleared | 12/9/2019 | ISMAEL HERNANDEZ |
| Green Code | Cleared | 12/16/2019 | KHEDER ALRAZAA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/9/2020 | Partial Inspection | DAVID CHAN |
| Deputy Drilled-In Anchors | 5/21/2021 | Partial Approval | RUBEN SALAS |
| PLUMBING-Rough | 6/18/2021 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 6/30/2021 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Rough | 6/30/2021 | Approved | STUART CHAPMAN |
| Green Building Rough | 6/30/2021 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 6/30/2021 | Approved | STUART CHAPMAN |
| METHANE-Rough | 6/30/2021 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 7/8/2021 | Conditional Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 7/8/2021 | Approved | STUART CHAPMAN |
| Green Building Rough | 7/8/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Insulation | 7/14/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Insulation | 7/19/2021 | Corrections Issued | JESUS PINEDA |
| Insulation | 7/26/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Insulation | 8/19/2021 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 8/30/2021 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 8/30/2021 | Approved | JESUS PINEDA |
| Deck | 10/1/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Pre-Inspection | 10/1/2021 | Approved | STUART CHAPMAN |
| Deputy Steel/Welding | 11/2/2021 | Conditional Approval | JUSTIN HAWLEY |
| Structural Steel Frame | 1/27/2022 | Corrections Issued | JOSE AVILA |
| Structural Steel Frame | 2/1/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 2/2/2022 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 2/2/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 2/2/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 2/7/2022 | Approved | JOSE AVILA |
| HVAC-Final | 2/7/2022 | Approved | JOSE AVILA |
| PLUMBING-Final | 2/7/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 3/11/2022 | Approved | JOSE AVILA |
| Final | 3/11/2022 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 3/11/2022 | Conditional Approval | JOSE AVILA |
| Green Building Final | 3/11/2022 | Corrections Issued | JOSE AVILA |
| Green Building Rough | 3/11/2022 | Approved | JOSE AVILA |
| METHANE-Barrier | 3/11/2022 | Approved | JOSE AVILA |
| METHANE-Subgrade | 3/11/2022 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 3/11/2022 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 3/11/2022 | Approved | JOSE AVILA |
| Final | 3/17/2022 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 3/17/2022 | Approved | JOSE AVILA |
| Green Building Final | 3/17/2022 | Approved | JOSE AVILA |
| Final | 3/22/2022 | Corrections Issued | JOSE AVILA |
| Final | 3/25/2022 | Corrections Issued | JOSE AVILA |
| Final | 7/19/2022 | Corrections Issued | JOSE AVILA |
| Final | 8/5/2022 | OK to Issue CofO | JOSE AVILA |