1520-1522 S BURNSIDE AVE 90019

Certificate Information: 1520-1522 S BURNSIDE AVE 90019

Application / Permit
19014-10000-04668
Plan Check / Job No.
B19LA18002
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
INTERIOR REMODEL FOR EXISTING 2 STORY 2 UNIT DWELLING PROPOSED ADDITION OF 59.45 SQFT FOR EACH FLOOR PROPOSED DECK AND BALCONY OF 80SQFT NEW STEEL STAIRS AT REAR
Permit Issued
Issued on 10/29/2020
Issuing Office
Metro
Current Status
CofO Issued on 11/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/27/2019 APPLICANT
Assigned to Plan Check Engineer 9/5/2019 JOHNNY WU
Green Plans Picked Up 9/10/2019 APPLICANT
Corrections Issued 9/16/2019 JOHNNY WU
Quality Review Completed 10/1/2019 JOSE RODRIGUEZ
Plan Check Approved 1/30/2020 JOHNNY WU
Issued 10/29/2020 APPLICANT
Building Plans Picked Up 10/30/2020 APPLICANT
CofO in Progress 8/8/2022 JOSE AVILA
No Progress 9/29/2022 JOSE AVILA
CofO in Progress 11/10/2022 JOSE AVILA
Permit Finaled 11/12/2022 DEROLD HAUFF
CofO Issued 11/12/2022 DEROLD HAUFF
Permit Finaled 11/12/2022 DEROLD HAUFF

Permit Application Clearance Information

Abandoned oil well Cleared 12/3/2019 JEREMY CARTER
Eng Process Fee Ord 176,300 Cleared 12/3/2019 THOMAS LANG
Highway dedication Cleared 12/3/2019 THOMAS LANG
Roof/Waste drainage to street Cleared 12/3/2019 THOMAS LANG
Sewer availability Cleared 12/3/2019 THOMAS LANG
Housing rent stabilization Cleared 12/9/2019 ISMAEL HERNANDEZ
Green Code Cleared 12/16/2019 KHEDER ALRAZAA

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/9/2020 Partial Inspection DAVID CHAN
Deputy Drilled-In Anchors 5/21/2021 Partial Approval RUBEN SALAS
PLUMBING-Rough 6/18/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 6/30/2021 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 6/30/2021 Approved STUART CHAPMAN
Green Building Rough 6/30/2021 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 6/30/2021 Approved STUART CHAPMAN
METHANE-Rough 6/30/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 7/8/2021 Conditional Approval STUART CHAPMAN
ELECTRICAL-Rough 7/8/2021 Approved STUART CHAPMAN
Green Building Rough 7/8/2021 Not Ready for Inspection STUART CHAPMAN
Insulation 7/14/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Insulation 7/19/2021 Corrections Issued JESUS PINEDA
Insulation 7/26/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Insulation 8/19/2021 Approved KATHRYN BUTTERWORTH
Drywall Nailing 8/30/2021 Approved JESUS PINEDA
Interior/Exterior Lathing 8/30/2021 Approved JESUS PINEDA
Deck 10/1/2021 Not Ready for Inspection STUART CHAPMAN
Pre-Inspection 10/1/2021 Approved STUART CHAPMAN
Deputy Steel/Welding 11/2/2021 Conditional Approval JUSTIN HAWLEY
Structural Steel Frame 1/27/2022 Corrections Issued JOSE AVILA
Structural Steel Frame 2/1/2022 Approved JOSE AVILA
ELECTRICAL-Final 2/2/2022 Corrections Issued JOSE AVILA
HVAC-Final 2/2/2022 Corrections Issued JOSE AVILA
PLUMBING-Final 2/2/2022 Approved JOSE AVILA
ELECTRICAL-Final 2/7/2022 Approved JOSE AVILA
HVAC-Final 2/7/2022 Approved JOSE AVILA
PLUMBING-Final 2/7/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 3/11/2022 Approved JOSE AVILA
Final 3/11/2022 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 3/11/2022 Conditional Approval JOSE AVILA
Green Building Final 3/11/2022 Corrections Issued JOSE AVILA
Green Building Rough 3/11/2022 Approved JOSE AVILA
METHANE-Barrier 3/11/2022 Approved JOSE AVILA
METHANE-Subgrade 3/11/2022 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 3/11/2022 SGSOV Approved JOSE AVILA
Smoke Detectors 3/11/2022 Approved JOSE AVILA
Final 3/17/2022 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 3/17/2022 Approved JOSE AVILA
Green Building Final 3/17/2022 Approved JOSE AVILA
Final 3/22/2022 Corrections Issued JOSE AVILA
Final 3/25/2022 Corrections Issued JOSE AVILA
Final 7/19/2022 Corrections Issued JOSE AVILA
Final 8/5/2022 OK to Issue CofO JOSE AVILA