1965 1/2 E NEW JERSEY ST 90033

Certificate Information: 1965 1/2 E NEW JERSEY ST 90033

Application / Permit
19014-10000-04619
Plan Check / Job No.
B19LA17872
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(35) Condo-Single Family
Work Description
ADDITION TO EXISTING DWELLING UNIT.
Permit Issued
Issued on 6/17/2021
Issuing Office
Current Status
CofO Issued on 4/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/23/2019 APPLICANT
Assigned to Plan Check Engineer 9/12/2019 EVERARDO SANTOS
Green Plans Picked Up 9/24/2019 APPLICANT
Corrections Issued 9/26/2019 EVERARDO SANTOS
Quality Review Completed 10/28/2019 JOSE RODRIGUEZ
Applicant returned to address corrections 3/24/2021 CARLOS MONTES
Plan Check Approved 5/27/2021 CARLOS MONTES
Issued 6/17/2021 APPLICANT
Building Plans Picked Up 6/18/2021 APPLICANT
CofO in Progress 4/20/2024 FREDDIE RIVERA
No Progress 4/22/2024 SCOTT FINNILA
CofO in Progress 4/22/2024 SCOTT FINNILA
CofO in Progress 4/22/2024 SCOTT FINNILA
CofO Issued 4/22/2024 DEROLD HAUFF
Permit Finaled 4/22/2024 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 3/24/2021 CARLOS MONTES
Address approval Cleared 4/20/2021 CELINA MORENO
Roof/Waste drainage to street Cleared 4/20/2021 CELINA MORENO
Sewer availability Cleared 4/20/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 4/22/2021 CELINA MORENO
"Q" conditions Cleared 4/27/2021 MAXFIELD VERMY
Miscellaneous Cleared 4/27/2021 MAXFIELD VERMY
Grading Pre-Inspection Cleared 4/28/2021 BRIAN MILLER
Frnt yard landscape/Water mgmt Cleared 5/13/2021 MAXFIELD VERMY

Contact Information

Contractor Owner-Builder       ,
Engineer Soto,, Miguel Angel; Lic. No.: C87493 3756 MERCURY AVE      LOS ANGELES, CA 90031

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/3/2021 Corrections Issued COREY HUPP
Sewer 8/3/2021 Not Ready for Inspection COREY HUPP
BUILDING-Rough-Frame 10/14/2022 Partial Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 10/14/2022 Corrections Issued FREDDIE RIVERA
Green Building Rough 10/14/2022 Partial Inspection FREDDIE RIVERA
MERV13>=Rough 10/14/2022 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 4/19/2024 Approved FREDDIE RIVERA
Drywall Nailing 4/19/2024 Approved FREDDIE RIVERA
Final 4/19/2024 OK to Issue CofO FREDDIE RIVERA
Footing/Foundation/Slab 4/19/2024 Approved FREDDIE RIVERA
Green Building Final 4/19/2024 Approved FREDDIE RIVERA
Green Building Rough 4/19/2024 Approved FREDDIE RIVERA
MERV13>=Final 4/19/2024 Approved FREDDIE RIVERA
MERV13>=Rough 4/19/2024 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 4/19/2024 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 4/19/2024 Approved FREDDIE RIVERA