1506 W VERNON AVE 90062

Certificate Information: 1506 W VERNON AVE 90062

Application / Permit
19014-10000-04618
Plan Check / Job No.
B19LA17870
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
PROPOSED CHANGE OF USE FROM SINGLE FAMILY DWELLING TO 3-UNIT APARTMENT. SCOPE WILL ALSO INCLUDE GROUND FLOOR ADDITION AND SECOND STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING TO CREATE COVERED PORCH AT FIRST FLOOR AND TWO ADDITIONAL 2 BEDROOM/1 BATHROOM UNITS ON SECOND FLOOR. ***SHALL BE SPRINKLERED PER NFPA 13 R***
Permit Issued
Issued on 4/14/2022
Issuing Office
Current Status
CofO Issued on 8/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/26/2019 APPLICANT
Assigned to Plan Check Engineer 9/12/2019 MICHAEL LOPEZ
Corrections Issued 9/17/2019 MICHAEL LOPEZ
Quality Review Completed 9/28/2019 STANLEY RAAP
Applicant returned to address corrections 2/2/2021 MICHAEL LOPEZ
Green Plans Picked Up 5/14/2021 APPLICANT
Applicant returned to address corrections 6/10/2021 MICHAEL LOPEZ
Applicant returned to address corrections 10/28/2021 MICHAEL LOPEZ
Applicant returned to address corrections 1/25/2022 MICHAEL LOPEZ
Plan Check Approved 3/3/2022 MICHAEL LOPEZ
Issued 4/14/2022 APPLICANT
Building Plans Picked Up 4/15/2022 APPLICANT
CofO in Progress 8/29/2023 ALAN MORELOS
CofO Issued 8/30/2023 ERNESTO CORRAL
Permit Finaled 8/30/2023 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 1/9/2020 ERIK BEASLEY
Green Code Cleared 1/9/2020 SARAH ABOULHOSN
Eng Process Fee Ord 176,300 Cleared 1/17/2020 JAMES MORALEZ
Sewer availability Cleared 1/17/2020 JAMES MORALEZ
Hydrant and Access approval Cleared 2/10/2020 JOHN CONNEALLY
Low Impact Development Cleared 3/10/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 3/10/2020 THOMAS LANG
CPC Cleared 11/12/2020 TERRI OSBORNE
Highway dedication Cleared 3/31/2021 CELINA MORENO
Frnt yard landscape/Water mgmt Cleared 4/8/2021 TERRI OSBORNE
Prkng lot landscape/Water mgmt Cleared 4/8/2021 TERRI OSBORNE

Contact Information

Contractor A T S Design And Construction; Lic. No.: 971152-B 18432 AMIE AVENUE      TORRANCE, CA 90504
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 26851 GRAYSLAKE ROAD      RANCHO PALOS VERDES, CA 90275

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/10/2022 Conditional Approval DARRYL ARNOLD
Deputy Drilled-In Anchors 6/16/2022 Conditional Approval DARRYL ARNOLD
Green Building Rough 7/8/2022 Partial Inspection RUSSELL BONVOULOIR
Wood Frame 7/8/2022 Partial Approval RUSSELL BONVOULOIR
Floor/Roof Diaphrgm/Shear Wall 8/2/2022 Approved RUSSELL BONVOULOIR
Deputy Wood Construction 9/12/2022 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 9/14/2022 Partial Inspection RUSSELL BONVOULOIR
Wood Frame 9/14/2022 Partial Inspection RUSSELL BONVOULOIR
Insulation 9/29/2022 Approved RUSSELL BONVOULOIR
Drywall Nailing 10/6/2022 Approved GREGORY POMISH
Final 8/15/2023 Not Ready for Inspection ALAN MORELOS
Footing/Foundation/Slab 8/15/2023 Approved ALAN MORELOS
Green Building Final 8/15/2023 Approved ALAN MORELOS
Green Building Rough 8/15/2023 Approved ALAN MORELOS
SGSOV-Seismic Gas S/O Valve 8/15/2023 SGSOV Not Ready ALAN MORELOS
Smoke Detectors 8/15/2023 Approved ALAN MORELOS
Wood Frame 8/15/2023 Approved ALAN MORELOS
Final 8/29/2023 OK to Issue CofO ALAN MORELOS
SGSOV-Seismic Gas S/O Valve 8/29/2023 SGSOV Approved ALAN MORELOS