254 W 118TH PL 90061

Certificate Information: 254 W 118TH PL 90061

Application / Permit
19014-10000-04599
Plan Check / Job No.
B19LA17822
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE & STORAGE INTO AN ACCESSORY DWELLING UNIT AND ADD 6 SF PER AB494 AND SB229.
Permit Issued
Issued on 9/30/2019
Issuing Office
San Pedro
Current Status
CofO Issued on 12/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/23/2019 APPLICANT
Assigned to Plan Check Engineer 8/23/2019 KEVIN MORALES
Corrections Issued 8/23/2019 KEVIN MORALES
Plan Check Approved 9/26/2019 ADAM HEGAZI
Issued 9/30/2019 LADBS
CofO in Progress 10/1/2021 EUGENE CASSIDY
Permit Finaled 12/4/2021 DEROLD HAUFF
CofO Issued 12/4/2021 DEROLD HAUFF
Permit Finaled 12/4/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/26/2019 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 9/26/2019 EMIL KYUPELYAN
Sewer availability Cleared 9/26/2019 EMIL KYUPELYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Hale,, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/3/2019 Corrections Issued WILLIAM ROSE
BUILDING-Rough-Frame 1/21/2021 Approved EUGENE CASSIDY
ELECTRICAL-Rough 1/21/2021 Approved EUGENE CASSIDY
Gas Test 1/21/2021 Approved EUGENE CASSIDY
HVAC-Rough 1/21/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 1/21/2021 Approved EUGENE CASSIDY
MERV13>=Rough 1/21/2021 Approved EUGENE CASSIDY
METHANE-Rough 1/21/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 1/21/2021 Approved EUGENE CASSIDY
Shower Pan 1/21/2021 Approved EUGENE CASSIDY
Wood Frame 1/21/2021 Approved EUGENE CASSIDY
Insulation 1/28/2021 Approved EUGENE CASSIDY
Drywall Nailing 2/24/2021 Approved EUGENE CASSIDY
Final 7/19/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 7/19/2021 Approved EUGENE CASSIDY
MERV13>=Final 7/19/2021 Approved EUGENE CASSIDY
METHANE-Barrier 7/19/2021 Approved EUGENE CASSIDY
METHANE-Subgrade 7/19/2021 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 7/19/2021 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 7/19/2021 Approved EUGENE CASSIDY
Final 7/23/2021 Not Ready for Inspection JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 7/23/2021 SGSOV Approved JOHN KLARIN
ELECTRICAL-Final 9/30/2021 Approved EUGENE CASSIDY
Final 9/30/2021 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 9/30/2021 Approved EUGENE CASSIDY
PLUMBING-Final 9/30/2021 Approved EUGENE CASSIDY
Service/Power Release 9/30/2021 Approved EUGENE CASSIDY