3120 E CHAUCER ST 90065

Certificate Information: 3120 E CHAUCER ST 90065

Application / Permit
19014-10000-04533
Plan Check / Job No.
B19LA17567
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) SINGLE FAMILY DWELLING. EXTERIOR / INTERIOR REMODELING PER ENGINEER DESIGN.
Permit Issued
Issued on 4/29/2021
Issuing Office
Valley
Current Status
CofO Issued on 5/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/21/2019 APPLICANT
Assigned to Plan Check Engineer 8/26/2019 KEVIN MORALES
Corrections Issued 8/26/2019 KEVIN MORALES
Applicant returned to address corrections 6/1/2020 JESSE JIMENEZ
Applicant returned to address corrections 10/23/2020 LUKE GONZALES
Applicant returned to address corrections 2/17/2021 ADAM HEGAZI
Plan Check Approved 4/7/2021 ADAM HEGAZI
Building Plans Picked Up 4/8/2021 APPLICANT
Issued 4/29/2021 APPLICANT
CofO in Progress 5/16/2023 OSVALDO PARAMO
CofO in Progress 5/16/2023 OSVALDO PARAMO
Permit Finaled 5/25/2023 DEROLD HAUFF
Permit Finaled 5/25/2023 DEROLD HAUFF
CofO Issued 5/25/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/26/2019 JEANIE LAM
Grading Pre-Inspection Cleared 8/26/2019 PATRICK MISCHLICH
Low Impact Development Cleared 3/16/2020 ORVAL HERNANDEZ-MARCI
Supp. Use District POD/CDO/TDO Cleared 3/25/2020 ADRINEH MELKONIAN
GPI Written Notices Cleared 3/26/2020 KEVIN MORALES
Roof/Waste drainage to street Cleared 5/26/2020 RENZ SORIANO

Contact Information

Contractor Owner-Builder       ,
Engineer Truong,, Phong Lap; Lic. No.: C70784 20754 TIMBERLINE LN      WALNUT, CA 91789

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/15/2021 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 1/11/2022 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 1/11/2022 Not Ready for Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 1/20/2022 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 1/20/2022 Partial Approval OSVALDO PARAMO
Deputy Wood Construction 3/3/2022 Conditional Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 3/17/2022 Partial Approval OSVALDO PARAMO
BUILDING-Rough-Frame 4/25/2022 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Rough 4/25/2022 Approved OSVALDO PARAMO
Green Building Rough 4/25/2022 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 4/25/2022 Corrections Issued OSVALDO PARAMO
BUILDING-Rough-Frame 5/17/2022 Approved OSVALDO PARAMO
Green Building Rough 5/17/2022 Approved OSVALDO PARAMO
HVAC-Rough 5/17/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 5/17/2022 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 5/17/2022 Approved OSVALDO PARAMO
Insulation 5/27/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 5/27/2022 Approved OSVALDO PARAMO
Drywall Nailing 6/2/2022 Approved OSVALDO PARAMO
Final 7/27/2022 Corrections Issued OSVALDO PARAMO
Green Building Final 7/27/2022 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 7/27/2022 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 7/27/2022 Not Ready for Inspection OSVALDO PARAMO
Final 8/5/2022 Corrections Issued OSVALDO PARAMO
Smoke Detectors 8/5/2022 Approved OSVALDO PARAMO
Final 8/10/2022 Conditional Approval OSVALDO PARAMO
Final 5/15/2023 OK to Issue CofO OSVALDO PARAMO