2149 N AVON ST 90026
Certificate Information: 2149 N AVON ST 90026
- Application / Permit
- 19014-10000-04498
- Plan Check / Job No.
- B19LA17414
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF (E) GARAGE TO (N) ACCESSORY DWELLING UNIT PER AB 494 & SB 229, SECOND STORY REC ROOM ADDITION ABOVE
- Permit Issued
- Issued on 2/4/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/3/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2019 | LAMAR DAVIS |
| Corrections Issued | 9/4/2019 | LAMAR DAVIS |
| Quality Review Completed | 9/4/2019 | PETER KIM |
| Green Plans Picked Up | 9/4/2019 | APPLICANT |
| Building Plans Picked Up | 9/18/2019 | APPLICANT |
| Applicant returned to address corrections | 1/9/2020 | LAMAR DAVIS |
| Applicant returned to address corrections | 1/22/2020 | LAMAR DAVIS |
| Plan Check Approved | 2/4/2020 | LAMAR DAVIS |
| Issued | 2/4/2020 | LADBS |
| CofO in Progress | 8/25/2020 | HAMIK HARTOUNIAN |
| Permit Finaled | 9/3/2020 | DEROLD HAUFF |
| CofO Issued | 9/3/2020 | DEROLD HAUFF |
| Permit Finaled | 9/3/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/8/2019 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/8/2019 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 10/8/2019 | EMIL KYUPELYAN |
| Grading Pre-Inspection | Cleared | 10/21/2019 | KIRK LINKLATER |
| Low Impact Development | Cleared | 11/4/2019 | JORGE MEJIA LEMUS |
| Green Code | Cleared | 12/11/2019 | KHEDER ALRAZAA |
| Hydrant and Access approval | Cleared | 12/11/2019 | ROBERT DUFF |
| Roof/Waste drainage to street | Cleared | 12/19/2019 | VICTOR MENDOZA |
| GPI Written Notices | Cleared | 2/4/2020 | LAMAR DAVIS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2020 | Approved | AJA COLLAY |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2020 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 5/1/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 5/1/2020 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 5/1/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 5/1/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 5/11/2020 | Corrections Issued | MATTHEW NUCKOLLS |
| ELECTRICAL-Rough | 5/11/2020 | Not Ready for Inspection | MATTHEW NUCKOLLS |
| Green Building Rough | 5/11/2020 | Not Ready for Inspection | MATTHEW NUCKOLLS |
| HVAC-Rough | 5/11/2020 | Not Ready for Inspection | MATTHEW NUCKOLLS |
| PLUMBING-Rough | 5/11/2020 | Not Ready for Inspection | MATTHEW NUCKOLLS |
| HVAC-Rough | 5/13/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 5/13/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 5/15/2020 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 5/15/2020 | Approved | STUART CHAPMAN |
| Green Building Rough | 5/15/2020 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 5/15/2020 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 5/15/2020 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 5/22/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Rough | 5/22/2020 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 6/4/2020 | Approved | ROBERT VORHIS |
| Drywall Nailing | 6/8/2020 | Partial Approval | THOMAS LOGRASSO |
| Shower Pan | 6/8/2020 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 6/11/2020 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 7/27/2020 | SGSOV Not Ready | STUART CHAPMAN |
| Final | 8/4/2020 | Not Ready for Inspection | DAVID CHAN |
| SGSOV-Seismic Gas S/O Valve | 8/4/2020 | SGSOV Approved | DAVID CHAN |
| BUILDING-Rough-Frame | 8/19/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Drywall Nailing | 8/19/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Final | 8/19/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 8/19/2020 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 8/19/2020 | Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 8/19/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/24/2020 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 8/24/2020 | Approved | HAMIK HARTOUNIAN |
| Final | 8/24/2020 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Smoke Detectors | 8/24/2020 | Approved | HAMIK HARTOUNIAN |