2080 N BARNETT ROAD 90032
Certificate Information: 2080 N BARNETT ROAD 90032
- Application / Permit
- 19014-10000-04488
- Plan Check / Job No.
- B19LA17389
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR ALTERATION AND ADDITION TO EXISTING SFD TO CREATE (2) NEW BEDROOMS, KITCHEN, FAMILY ROOM AND DECK.
- Permit Issued
- Issued on 10/1/2020
- Issuing Office
- Current Status
- CofO Issued on 10/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2019 | JOHNNY WU |
| Corrections Issued | 9/5/2019 | JOHNNY WU |
| Quality Review Completed | 9/16/2019 | JOSE RODRIGUEZ |
| Building Plans Picked Up | 9/23/2019 | APPLICANT |
| Applicant returned to address corrections | 2/6/2020 | JOHNNY WU |
| Green Plans Picked Up | 7/7/2020 | APPLICANT |
| Applicant returned to address corrections | 9/9/2020 | JOHNNY WU |
| Plan Check Approved | 9/30/2020 | JOHNNY WU |
| Issued | 10/1/2020 | APPLICANT |
| CofO in Progress | 10/4/2022 | AMY COLIN |
| Permit Finaled | 10/6/2022 | DEROLD HAUFF |
| CofO Issued | 10/6/2022 | DEROLD HAUFF |
| Permit Finaled | 10/6/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/6/2020 | JOHNNY WU |
| BHO/Hillside ordinance | Cleared | 2/11/2020 | JEANETTE VONG |
| BHO/Hillside ordinance | Cleared | 2/11/2020 | JEANETTE VONG |
| Sewer availability | Cleared | 2/11/2020 | JEANETTE VONG |
| Green Code | Cleared | 7/2/2020 | VIVIAN LAO |
| "D" conditions | Cleared | 7/8/2020 | JOE LUCKEY |
| "Q" conditions | Cleared | 7/8/2020 | JOE LUCKEY |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2020 | CELINA MORENO |
| Low Impact Development | Cleared | 8/3/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 8/6/2020 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 8/25/2020 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Amador,, Carlos; Lic. No.: L9365 | 5445 DEL AMO BLVD #202 LAKEWOOD, CA 90712 |
| Engineer | O'Brien,, Kathleen Anne; Lic. No.: C49498 | 1058 PACIFIC AVE SIMI VALLEY, CA 93065 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/22/2020 | Approved | COREY HUPP |
| Footing/Foundation/Slab | 1/28/2021 | Not Ready for Inspection | COREY HUPP |
| Footing/Foundation/Slab | 2/2/2021 | Approved | COREY HUPP |
| Reinforced Concrete Frame | 2/18/2021 | Partial Approval | COREY HUPP |
| Deputy Drilled-In Anchors | 2/26/2021 | Conditional Approval | THOMAS LOGRASSO |
| Pre-Inspection | 3/3/2021 | Not Ready for Inspection | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 3/9/2021 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2021 | Partial Approval | COREY HUPP |
| ELECTRICAL-Rough | 6/15/2021 | Corrections Issued | COREY HUPP |
| Wood Frame | 6/15/2021 | Corrections Issued | COREY HUPP |
| ELECTRICAL-Rough | 7/9/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Wood Frame | 7/9/2021 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 7/14/2021 | Partial Approval | COREY HUPP |
| HVAC-Rough | 7/14/2021 | Partial Approval | COREY HUPP |
| PLUMBING-Rough | 7/14/2021 | Partial Approval | COREY HUPP |
| Wood Frame | 7/14/2021 | Partial Approval | COREY HUPP |
| Interior/Exterior Lathing | 7/23/2021 | Approved | JUSTIN HAWLEY |
| Insulation | 7/29/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 7/30/2021 | Approved | COREY HUPP |
| Drywall Nailing | 8/9/2021 | Partial Approval | RUBEN SALAS |
| ELECTRICAL-Rough | 12/8/2021 | Approved | COREY HUPP |
| HVAC-Rough | 12/8/2021 | Approved | COREY HUPP |
| PLUMBING-Rough | 12/8/2021 | Approved | COREY HUPP |
| Wood Frame | 12/8/2021 | Approved | COREY HUPP |
| Drywall Nailing | 12/30/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 12/30/2021 | Approved | CRAIG VAUGHAN |
| Enclosure/Fence | 4/5/2022 | Partial Inspection | AMY COLIN |
| HVAC-Final | 6/10/2022 | Corrections Issued | AMY COLIN |
| ELECTRICAL-Final | 6/29/2022 | Corrections Issued | AMY COLIN |
| Final | 6/29/2022 | Corrections Issued | AMY COLIN |
| HVAC-Final | 6/29/2022 | Approved | AMY COLIN |
| PLUMBING-Final | 6/29/2022 | Approved | AMY COLIN |
| BUILDING-Rough-Frame | 8/31/2022 | Approved | AMY COLIN |
| ELECTRICAL-Final | 8/31/2022 | Approved | AMY COLIN |
| Final | 8/31/2022 | Corrections Issued | AMY COLIN |
| Green Building Final | 8/31/2022 | Approved | AMY COLIN |
| Green Building Rough | 8/31/2022 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 8/31/2022 | SGSOV Approved | AMY COLIN |
| Smoke Detectors | 8/31/2022 | Approved | AMY COLIN |
| Final | 10/4/2022 | OK to Issue CofO | AMY COLIN |