2236 S SYCAMORE AVE 90016

Certificate Information: 2236 S SYCAMORE AVE 90016

Application / Permit
19014-10000-04480
Plan Check / Job No.
B19LA17347
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 1-STORY ADDITION TO REAR OF SINGLE FAMILY DWELLING
Permit Issued
Issued on 3/13/2020
Issuing Office
Metro
Current Status
CofO Issued on 3/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/19/2019 APPLICANT
Assigned to Plan Check Engineer 8/22/2019 SINA KHOSRAVI
Corrections Issued 8/22/2019 SINA KHOSRAVI
Plan Check Approved 11/25/2019 MONICA RAMIREZ
Issued 3/13/2020 LADBS
Building Plans Picked Up 6/12/2020 APPLICANT
CofO in Progress 2/24/2022 STUART CHAPMAN
Permit Finaled 3/5/2022 DEROLD HAUFF
CofO Issued 3/5/2022 DEROLD HAUFF
Permit Finaled 3/5/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/22/2019 JEANIE LAM
Roof/Waste drainage to street Cleared 11/22/2019 JEANIE LAM
Sewer availability Cleared 11/22/2019 JEANIE LAM
Low Impact Development Cleared 11/25/2019 ANDRES COVARRUBIAS

Contact Information

Contractor Owner-Builder       ,
Engineer Tagudar,, Fred; Lic. No.: C33612 850 E OCEAN BLVD 706      LONG BEACH, CA 90802

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/17/2020 Corrections Issued STUART CHAPMAN
PLUMBING-Rough 4/17/2020 Partial Approval STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 4/21/2020 Conditional Approval STUART CHAPMAN
PLUMBING-Rough 4/21/2020 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 4/29/2020 Conditional Approval STUART CHAPMAN
Insulation 5/4/2020 Conditional Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 5/7/2020 Partial Approval STUART CHAPMAN
Green Building Rough 5/7/2020 Not Ready for Inspection STUART CHAPMAN
MERV13>=Rough 5/7/2020 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 6/25/2020 Corrections Issued DAVID CHAN
ELECTRICAL-Rough 6/25/2020 Approved DAVID CHAN
HVAC-Rough 6/25/2020 Approved DAVID CHAN
PLUMBING-Rough 6/25/2020 Not Ready for Inspection DAVID CHAN
BUILDING-Rough-Frame 6/29/2020 Partial Approval STUART CHAPMAN
Green Building Rough 6/29/2020 Not Ready for Inspection STUART CHAPMAN
MERV13>=Rough 6/29/2020 Approved STUART CHAPMAN
PLUMBING-Rough 6/29/2020 Approved STUART CHAPMAN
Green Building Rough 7/2/2020 Approved STUART CHAPMAN
Shower Pan 7/2/2020 Approved STUART CHAPMAN
Insulation 7/7/2020 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 7/7/2020 Corrections Issued THOMAS LOGRASSO
Drywall Nailing 7/14/2020 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 9/28/2020 Approved STUART CHAPMAN
Final 9/28/2020 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 9/28/2020 Approved STUART CHAPMAN
Green Building Final 9/28/2020 Not Ready for Inspection STUART CHAPMAN
MERV13>=Final 9/28/2020 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 9/28/2020 SGSOV Approved STUART CHAPMAN
Smoke Detectors 9/28/2020 Approved STUART CHAPMAN
Final 10/28/2020 Conditional Approval STUART CHAPMAN
Green Building Final 10/28/2020 Approved STUART CHAPMAN
Final 2/16/2022 Corrections Issued STUART CHAPMAN
ELECTRICAL-Final 2/24/2022 Approved STUART CHAPMAN
Final 2/24/2022 OK to Issue CofO STUART CHAPMAN
HVAC-Final 2/24/2022 Approved STUART CHAPMAN
PLUMBING-Final 2/24/2022 Approved STUART CHAPMAN