15758 W PLUMMER ST 91343
Certificate Information: 15758 W PLUMMER ST 91343
- Application / Permit
- 19014-10000-04434
- Plan Check / Job No.
- B19LA17119
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AT REAR OF (E) 1 STORY SINGLE FAMILY DWELLING ___ X ___ (IRREGULAR) FOR NEW MASTER BEDROOM & BATHROOM, AND TO EXTEND KITCHEN/DINING AREA.
- Permit Issued
- Issued on 10/21/2019
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 10/21/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2019 | JEFFREY MACHADO |
| Corrections Issued | 9/4/2019 | JEFFREY MACHADO |
| Quality Review Completed | 9/7/2019 | STANLEY RAAP |
| Building Plans Picked Up | 9/16/2019 | APPLICANT |
| Green Plans Picked Up | 9/16/2019 | APPLICANT |
| Plan Check Approved | 10/17/2019 | SAMUEL GONZALEZ |
| Issued | 10/21/2019 | LADBS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/26/2019 | CELINA MORENO |
| Sewer availability | Cleared | 9/26/2019 | CELINA MORENO |
| Low Impact Development | Cleared | 10/2/2019 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 10/2/2019 | JEANIE LAM |
| Green Code | Cleared | 10/7/2019 | VIVIAN LAO |
Contact Information
| Contractor | Goliath Construction; Lic. No.: 1056541-B | 6914 RADFORD AVE NORTH HOLLYWOOD, CA 91605 |
| Engineer | Hernandez,, Gerardo; Lic. No.: C78115 | 1426 E STUART AVE WEST COVINA, CA 91791 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/23/2019 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 11/5/2019 | Partial Inspection | JACK KARGODORIAN |
| Underground Mechanical | 11/5/2019 | Partial Inspection | JACK KARGODORIAN |
| Wood Frame | 11/5/2019 | Partial Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2019 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 1/7/2020 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 1/7/2020 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 1/24/2020 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 1/29/2020 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 1/29/2020 | Approved | JENNIFER RABUCHIN |
| Insulation | 1/29/2020 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 1/29/2020 | Partial Approval | JENNIFER RABUCHIN |
| MERV13>=Rough | 1/29/2020 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 2/1/2020 | Approved | ROBERT VORHIS |
| Gas Test | 2/1/2020 | Corrections Issued | ROBERT VORHIS |
| Green Building Rough | 2/1/2020 | Approved | ROBERT VORHIS |
| ELECTRICAL-Final | 3/6/2020 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 3/6/2020 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 3/6/2020 | Approved | JACK KARGODORIAN |
| HVAC-Final | 3/6/2020 | Not Ready for Inspection | JACK KARGODORIAN |
| MERV13>=Final | 3/6/2020 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 3/6/2020 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 3/6/2020 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 3/6/2020 | Approved | JACK KARGODORIAN |
| Final | 3/12/2020 | Conditional Approval | JACK KARGODORIAN |
| Gas Test | 3/12/2020 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 3/12/2020 | Approved | JACK KARGODORIAN |