2408 N MCPHERSON PL 90032
Certificate Information: 2408 N MCPHERSON PL 90032
- Application / Permit
- 19014-10000-04418
- Plan Check / Job No.
- B19LA17021
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (E) GARAGE TO BE CONVERTED TO ACCESSORY DWELLING UNIT WITHADDITION (11'-5" x 18'-2") PER ORDINANCE. ALL WORK PER WFPP.
- Permit Issued
- Issued on 12/9/2020
- Issuing Office
- Current Status
- CofO Issued on 6/24/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2019 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 8/16/2019 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 7/7/2020 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 8/17/2020 | CRISTINA SALAZAR |
| Building Plans Picked Up | 9/2/2020 | APPLICANT |
| Applicant returned to address corrections | 11/13/2020 | SHANGQIN XIE |
| Applicant returned to address corrections | 11/24/2020 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 12/8/2020 | FARSHAD ALIMOHAMADI |
| Issued | 12/9/2020 | APPLICANT |
| CofO in Progress | 6/14/2021 | COREY HUPP |
| CofO in Progress | 6/14/2021 | COREY HUPP |
| Permit Finaled | 6/24/2021 | DEROLD HAUFF |
| CofO Issued | 6/24/2021 | DEROLD HAUFF |
| Permit Finaled | 6/24/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/25/2019 | ELAINE LEI |
| Permit | Cleared | 10/25/2019 | ELAINE LEI |
| Roof/Waste drainage to street | Cleared | 10/25/2019 | ELAINE LEI |
| Construction near power lines | Cleared | 1/15/2020 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 9/30/2020 | RENZ SORIANO |
| Trees in Parkway | Cleared | 10/1/2020 | JOHN KIM |
| Sewer availability | Cleared | 10/5/2020 | RENZ SORIANO |
| Grading Pre-Inspection | Cleared | 10/6/2020 | PATRICK MISCHLICH |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/29/2021 | No Access for Inspection | ELMER BLAND |
| Footing/Foundation/Slab | 2/1/2021 | Approved | COREY HUPP |
| Underground Mechanical | 2/1/2021 | Partial Approval | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2021 | Approved | COREY HUPP |
| Interior/Exterior Lathing | 2/17/2021 | Partial Approval | COREY HUPP |
| Rough-Elec/Plmb/HVAC | 2/17/2021 | Partial Approval | COREY HUPP |
| Insulation | 2/23/2021 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 3/3/2021 | Approved | COREY HUPP |
| Drywall Nailing | 3/8/2021 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 3/12/2021 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 5/5/2021 | Approved | OSVALDO PARAMO |
| Final | 5/5/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Gas Test | 5/5/2021 | Approved | OSVALDO PARAMO |
| Green Building Final | 5/5/2021 | Approved | OSVALDO PARAMO |
| Green Building Rough | 5/5/2021 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 5/5/2021 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 5/5/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 6/2/2021 | Corrections Issued | CRAIG VAUGHAN |
| Smoke Detectors | 6/2/2021 | Corrections Issued | CRAIG VAUGHAN |
| Final | 6/14/2021 | OK to Issue CofO | COREY HUPP |
| Smoke Detectors | 6/14/2021 | Approved | COREY HUPP |