10784 N OWENS PL 91042
Certificate Information: 10784 N OWENS PL 91042
- Application / Permit
- 19014-10000-04412
- Plan Check / Job No.
- B19LA16988
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF 380 SF TO AN EXISTING SINGLE FAMILY DWELLING, TO EXPAND MASTER BEDROOM AND LIVING ROOM, RELOCATE KITCHEN.
- Permit Issued
- Issued on 9/16/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/7/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/14/2019 | JOHNNY WU |
| Corrections Issued | 8/14/2019 | JOHNNY WU |
| Plan Check Approved | 9/16/2019 | GEORGE ALVAREZ |
| Issued | 9/16/2019 | LADBS |
| CofO in Progress | 10/14/2020 | MATTHEW NELSON |
| No Progress | 12/5/2020 | MICHAEL SMITH |
| CofO in Progress | 12/7/2020 | MICHAEL SMITH |
| Permit Finaled | 12/7/2020 | MICHAEL SMITH |
| CofO Issued | 12/7/2020 | MICHAEL SMITH |
| Permit Finaled | 12/7/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/14/2019 | CELINA MORENO |
| Private street | Cleared | 8/14/2019 | SOPHIE GABEL-SCHEINBAU |
| Roof/Waste drainage to street | Cleared | 8/14/2019 | CELINA MORENO |
| ZA Case | Cleared | 8/14/2019 | SOPHIE GABEL-SCHEINBAU |
| Grading Pre-Inspection | Cleared | 9/16/2019 | JOHNNY WU |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | PO BOX 7112 NORTHRIDGE, CA 91327 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/21/2019 | Approved | MATTHEW NELSON |
| Underground Mechanical | 10/21/2019 | Not Ready for Inspection | MATTHEW NELSON |
| Underground Mechanical | 10/28/2019 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2019 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 11/22/2019 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 1/6/2020 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Rough | 1/6/2020 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2020 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 1/6/2020 | Not Ready for Inspection | MATTHEW NELSON |
| Special/Order Compliance | 1/6/2020 | Approved | PIERRE VEGA |
| BUILDING-Rough-Frame | 2/18/2020 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 2/18/2020 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 2/18/2020 | Approved | MATTHEW NELSON |
| Insulation | 3/10/2020 | Approved | MATTHEW NELSON |
| Drywall Nailing | 3/19/2020 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 3/19/2020 | Approved | MATTHEW NELSON |
| Final | 9/30/2020 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 9/30/2020 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 9/30/2020 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 9/30/2020 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 10/14/2020 | Approved | MATTHEW NELSON |
| Final | 10/14/2020 | OK to Issue CofO | MATTHEW NELSON |
| HVAC-Final | 10/14/2020 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 10/14/2020 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 10/14/2020 | SGSOV Approved | MATTHEW NELSON |