5247 N SALOMA AVE 91411

Certificate Information: 5247 N SALOMA AVE 91411

Application / Permit
19014-10000-04409
Plan Check / Job No.
B19LA16975
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-STORY, TYPE VB ADDITION TO EXISTING 1-STORY SINGLE FAMILY DWELLING/ATTACHED GARAGE
Permit Issued
Issued on 7/17/2020
Issuing Office
Current Status
CofO Issued on 2/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/14/2019 APPLICANT
Assigned to Plan Check Engineer 8/16/2019 FARSHAD ALIMOHAMADI
Corrections Issued 8/16/2019 FARSHAD ALIMOHAMADI
Plan Check Approved 9/5/2019 VU NGUYEN
Issued 7/17/2020 APPLICANT
CofO in Progress 1/18/2022 JACK KARGODORIAN
CofO Issued 2/5/2022 MICHAEL SMITH
Permit Finaled 2/5/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/5/2019 JEANIE LAM
Low Impact Development Cleared 9/5/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 9/5/2019 JEANIE LAM
Sewer availability Cleared 9/5/2019 JEANIE LAM

Contact Information

Contractor Loch Ness Construction; Lic. No.: 990574-B P O BOX 260      SOMIS, CA 93066

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/15/2020 Conditional Approval CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 9/22/2020 Corrections Issued MICHAEL TEMPLE
PLUMBING-Rough 11/16/2020 Partial Approval DANIEL ORRANTE
Wood Frame 11/16/2020 Corrections Issued DANIEL ORRANTE
Floor/Roof Diaphrgm/Shear Wall 11/18/2020 Approved DANIEL ORRANTE
Green Building Rough 11/18/2020 Not Ready for Inspection DANIEL ORRANTE
BUILDING-Rough-Frame 12/2/2020 Partial Inspection MARK JOHNSON
ELECTRICAL-Rough 12/2/2020 Corrections Issued MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 12/18/2020 Not Ready for Inspection BRENDAN LOONEY
Wood Frame 12/18/2020 Not Ready for Inspection BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 12/22/2020 Partial Approval CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 12/30/2020 Approved ARTHUR SARGSYAN
Deputy Wood Construction 1/11/2021 Conditional Approval CHRISTOPHE COCHRAN
Wood Frame 1/13/2021 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 2/16/2021 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 2/16/2021 Corrections Issued JENNIFER RABUCHIN
Gas Test 2/16/2021 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 2/16/2021 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 2/16/2021 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 2/18/2021 Not Ready for Inspection ARTHUR SARGSYAN
HVAC-Rough 2/18/2021 Not Ready for Inspection ARTHUR SARGSYAN
PLUMBING-Rough 2/18/2021 Not Ready for Inspection ARTHUR SARGSYAN
BUILDING-Rough-Frame 2/22/2021 Partial Approval ARTHUR SARGSYAN
ELECTRICAL-Rough 2/22/2021 Approved ARTHUR SARGSYAN
HVAC-Rough 2/22/2021 Approved ARTHUR SARGSYAN
PLUMBING-Rough 2/22/2021 Approved ARTHUR SARGSYAN
Insulation 2/26/2021 Approved ARTHUR SARGSYAN
Drywall Nailing 3/3/2021 Corrections Issued CHARLES POWELL
Pre-Inspection 3/4/2021 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 4/1/2021 Approved ARTHUR SARGSYAN
Shower Pan 4/1/2021 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 4/9/2021 Approved ARTHUR SARGSYAN
Pre-Inspection 5/13/2021 Partial Inspection MARK JOHNSON
Pre-Inspection 6/18/2021 Partial Approval CHARLES POWELL
BUILDING-Rough-Frame 11/29/2021 Approved JACK KARGODORIAN
Final 11/29/2021 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 11/29/2021 Approved JACK KARGODORIAN
Green Building Final 11/29/2021 Approved JACK KARGODORIAN
Green Building Rough 11/29/2021 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 11/29/2021 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 11/29/2021 Approved JACK KARGODORIAN
Final 1/18/2022 OK to Issue CofO JACK KARGODORIAN