5247 N SALOMA AVE 91411
Certificate Information: 5247 N SALOMA AVE 91411
- Application / Permit
- 19014-10000-04409
- Plan Check / Job No.
- B19LA16975
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-STORY, TYPE VB ADDITION TO EXISTING 1-STORY SINGLE FAMILY DWELLING/ATTACHED GARAGE
- Permit Issued
- Issued on 7/17/2020
- Issuing Office
- Current Status
- CofO Issued on 2/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2019 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 8/16/2019 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 9/5/2019 | VU NGUYEN |
| Issued | 7/17/2020 | APPLICANT |
| CofO in Progress | 1/18/2022 | JACK KARGODORIAN |
| CofO Issued | 2/5/2022 | MICHAEL SMITH |
| Permit Finaled | 2/5/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/5/2019 | JEANIE LAM |
| Low Impact Development | Cleared | 9/5/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 9/5/2019 | JEANIE LAM |
| Sewer availability | Cleared | 9/5/2019 | JEANIE LAM |
Contact Information
| Contractor | Loch Ness Construction; Lic. No.: 990574-B | P O BOX 260 SOMIS, CA 93066 |
Inspector Information
| DAVID ANDERSON, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/15/2020 | Conditional Approval | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 9/22/2020 | Corrections Issued | MICHAEL TEMPLE |
| PLUMBING-Rough | 11/16/2020 | Partial Approval | DANIEL ORRANTE |
| Wood Frame | 11/16/2020 | Corrections Issued | DANIEL ORRANTE |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2020 | Approved | DANIEL ORRANTE |
| Green Building Rough | 11/18/2020 | Not Ready for Inspection | DANIEL ORRANTE |
| BUILDING-Rough-Frame | 12/2/2020 | Partial Inspection | MARK JOHNSON |
| ELECTRICAL-Rough | 12/2/2020 | Corrections Issued | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Wood Frame | 12/18/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2020 | Partial Approval | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2020 | Approved | ARTHUR SARGSYAN |
| Deputy Wood Construction | 1/11/2021 | Conditional Approval | CHRISTOPHE COCHRAN |
| Wood Frame | 1/13/2021 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/16/2021 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/16/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 2/16/2021 | Partial Approval | JENNIFER RABUCHIN |
| HVAC-Rough | 2/16/2021 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/16/2021 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/18/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| HVAC-Rough | 2/18/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| PLUMBING-Rough | 2/18/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 2/22/2021 | Partial Approval | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 2/22/2021 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 2/22/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 2/22/2021 | Approved | ARTHUR SARGSYAN |
| Insulation | 2/26/2021 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 3/3/2021 | Corrections Issued | CHARLES POWELL |
| Pre-Inspection | 3/4/2021 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 4/1/2021 | Approved | ARTHUR SARGSYAN |
| Shower Pan | 4/1/2021 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 4/9/2021 | Approved | ARTHUR SARGSYAN |
| Pre-Inspection | 5/13/2021 | Partial Inspection | MARK JOHNSON |
| Pre-Inspection | 6/18/2021 | Partial Approval | CHARLES POWELL |
| BUILDING-Rough-Frame | 11/29/2021 | Approved | JACK KARGODORIAN |
| Final | 11/29/2021 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 11/29/2021 | Approved | JACK KARGODORIAN |
| Green Building Final | 11/29/2021 | Approved | JACK KARGODORIAN |
| Green Building Rough | 11/29/2021 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 11/29/2021 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 11/29/2021 | Approved | JACK KARGODORIAN |
| Final | 1/18/2022 | OK to Issue CofO | JACK KARGODORIAN |