921 S HUDSON AVE 90019

Certificate Information: 921 S HUDSON AVE 90019

Application / Permit
19014-10000-04389
Plan Check / Job No.
B19LA16889
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
FOR 2ND STORY ADDITION TO (E) 1-STORY GARAGE & CONVERT TO ACCESSORY DWELLING UNIT PER AB494 AND SB229. (N) SPIRAL STAIRS PER STANDARD PLAN #111
Permit Issued
Issued on 1/23/2020
Issuing Office
Metro
Current Status
CofO Issued on 1/11/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/13/2019 APPLICANT
Green Plans Picked Up 8/28/2019 APPLICANT
Assigned to Plan Check Engineer 8/29/2019 VU NGUYEN
Corrections Issued 9/4/2019 VU NGUYEN
Quality Review Completed 9/16/2019 JOSE RODRIGUEZ
Building Plans Picked Up 9/26/2019 APPLICANT
Plan Check Approved 10/28/2019 VU NGUYEN
Issued 1/23/2020 LADBS
CofO in Progress 1/4/2021 JOSEPH MCGARRY
Permit Finaled 1/11/2021 DEROLD HAUFF
CofO Issued 1/11/2021 DEROLD HAUFF
Permit Finaled 1/11/2021 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 10/4/2019 ANNA VAN
CPC Cleared 10/4/2019 ANNA VAN
Address approval Cleared 10/15/2019 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 10/15/2019 EMIL KYUPELYAN
Roof/Waste drainage to street Cleared 10/15/2019 EMIL KYUPELYAN
Sewer availability Cleared 10/15/2019 EMIL KYUPELYAN
Green Code Cleared 10/21/2019 VU NGUYEN

Contact Information

Architect Cooke,, Barrett H; Lic. No.: C37365 5239 WINDERMERE AVE      LOS ANGELES, CA 90041
Contractor Williams Christopher; Lic. No.: 711380-B P O BOX 8652      LA CRESCENTA, CA 91224
Engineer Farish,, William Crawford; Lic. No.: C30123 19432 CASTLEWOOD CR      HUNTINGTON BEACH, CA 92648
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/3/2020 Corrections Issued ARTHUR SARGSYAN
METHANE-Barrier 3/3/2020 Not Ready for Inspection ARTHUR SARGSYAN
METHANE-Subgrade 3/3/2020 Not Ready for Inspection ARTHUR SARGSYAN
Underground Mechanical 3/3/2020 Not Ready for Inspection ARTHUR SARGSYAN
Footing/Foundation/Slab 3/9/2020 Not Ready for Inspection ARTHUR SARGSYAN
METHANE-Barrier 3/9/2020 Approved ARTHUR SARGSYAN
METHANE-Subgrade 3/9/2020 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 4/3/2020 Partial Approval ARTHUR SARGSYAN
Underground Mechanical 4/7/2020 Not Ready for Inspection ARTHUR SARGSYAN
PLUMBING-Rough 5/1/2020 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 5/20/2020 Partial Approval ARTHUR SARGSYAN
BUILDING-Rough-Frame 6/10/2020 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 6/10/2020 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 6/10/2020 Approved ARTHUR SARGSYAN
Green Building Rough 6/10/2020 Approved ARTHUR SARGSYAN
HVAC-Rough 6/10/2020 Approved ARTHUR SARGSYAN
METHANE-Rough 6/10/2020 Approved ARTHUR SARGSYAN
PLUMBING-Rough 6/10/2020 Approved ARTHUR SARGSYAN
Insulation 6/22/2020 Approved ARTHUR SARGSYAN
Drywall Nailing 6/29/2020 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 6/29/2020 Approved THOMAS LOGRASSO
Drywall Nailing 7/7/2020 No Access for Inspection THOMAS LOGRASSO
Shower Pan 7/7/2020 No Access for Inspection THOMAS LOGRASSO
Interior/Exterior Lathing 7/15/2020 Approved ARTHUR SARGSYAN
Shower Pan 7/15/2020 Approved ARTHUR SARGSYAN
Final 11/24/2020 No Access for Inspection CHRIS CHRISTENSEN
Footing/Foundation/Slab 11/24/2020 No Access for Inspection CHRIS CHRISTENSEN
Green Building Final 11/24/2020 No Access for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 11/24/2020 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 11/24/2020 No Access for Inspection CHRIS CHRISTENSEN
Final 12/4/2020 Corrections Issued JOSEPH MCGARRY
Footing/Foundation/Slab 12/4/2020 Corrections Issued JOSEPH MCGARRY
Green Building Final 12/4/2020 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 12/4/2020 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 12/4/2020 Approved JOSEPH MCGARRY
Final 12/11/2020 Partial Inspection JOSEPH MCGARRY
Footing/Foundation/Slab 12/11/2020 Approved JOSEPH MCGARRY
Gas Test 12/11/2020 Approved JOSEPH MCGARRY
Final 12/31/2020 OK to Issue CofO JOSEPH MCGARRY