2201 1/2 S HARCOURT AVE 90016

Certificate Information: 2201 1/2 S HARCOURT AVE 90016

Application / Permit
19014-10000-04383
Plan Check / Job No.
B19LA16882
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION & CONVERT A PORTION OF GARAGE/REC ROOM TO NEW ADU PER AB 494 AND SB 229. "COMPLY WITH DEPARTMENT ORDER effective date 12/28/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". All permits shall be for the same time period limitation. CEIS Case Number is 838210.
Permit Issued
Issued on 2/26/2020
Issuing Office
Metro
Current Status
CofO in Progress on 7/27/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/13/2019 APPLICANT
Assigned to Plan Check Engineer 8/21/2019 ZAW HAN
Corrections Issued 8/28/2019 ZAW HAN
Green Plans Picked Up 8/29/2019 APPLICANT
Quality Review Completed 9/4/2019 HERNAN ARREOLA
Building Plans Picked Up 9/6/2019 APPLICANT
Plan Check Approved 12/17/2019 ZAW HAN
Issued 2/26/2020 LADBS
CofO in Progress 7/27/2020 DANIEL GONZALEZ

Permit Application Clearance Information

Abandoned oil well Cleared 9/20/2019 GEORGE SUCHAND
Address approval Cleared 9/20/2019 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 9/20/2019 CELINA MORENO
Sewer availability Cleared 9/20/2019 CELINA MORENO
Construction near power lines Cleared 9/24/2019 OSCAR CASTRO
Green Code Cleared 11/8/2019 SEAN DANG
Low Impact Development Cleared 11/8/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 11/13/2019 EMIL KYUPELYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Hong Kook; Lic. No.: C64529 839 S MUIRFIELD RD      LOS ANGELES, CA 90005

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/1/2020 Approved WILLIAM MICHALAK
Underground Mechanical 4/1/2020 Approved WILLIAM MICHALAK
Footing/Foundation/Slab 4/14/2020 Approved WILLIAM MICHALAK
Floor/Roof Diaphrgm/Shear Wall 5/7/2020 Approved WILLIAM MICHALAK
ELECTRICAL-Rough 5/12/2020 Partial Approval WILLIAM MICHALAK
HVAC-Rough 5/12/2020 Corrections Issued WILLIAM MICHALAK
Interior/Exterior Lathing 5/12/2020 Partial Approval WILLIAM MICHALAK
PLUMBING-Rough 5/12/2020 Partial Approval WILLIAM MICHALAK
ELECTRICAL-Rough 5/13/2020 Approved WILLIAM MICHALAK
HVAC-Rough 5/13/2020 Approved WILLIAM MICHALAK
Insulation 5/13/2020 Approved WILLIAM MICHALAK
Interior/Exterior Lathing 5/13/2020 Partial Approval WILLIAM MICHALAK
PLUMBING-Rough 5/13/2020 Approved WILLIAM MICHALAK
Drywall Nailing 5/19/2020 Approved WILLIAM MICHALAK
Green Building Rough 5/19/2020 Approved WILLIAM MICHALAK
Underground Mechanical 6/10/2020 Approved WILLIAM MICHALAK
ELECTRICAL-Final 6/25/2020 Approved DANIEL GONZALEZ
HVAC-Final 6/25/2020 Corrections Issued DANIEL GONZALEZ
PLUMBING-Final 6/25/2020 Approved DANIEL GONZALEZ
BUILDING-Rough-Frame 7/2/2020 Approved DANIEL GONZALEZ
Final 7/2/2020 Corrections Issued DANIEL GONZALEZ
Green Building Final 7/2/2020 Approved DANIEL GONZALEZ
HVAC-Final 7/2/2020 Approved DANIEL GONZALEZ
SGSOV-Seismic Gas S/O Valve 7/2/2020 SGSOV Approved DANIEL GONZALEZ
Smoke Detectors 7/2/2020 Approved DANIEL GONZALEZ
Final 7/8/2020 Conditional Approval DANIEL GONZALEZ
Final 7/10/2020 OK to Issue CofO DANIEL GONZALEZ
HVAC-Final 7/10/2020 Approved DANIEL GONZALEZ
Service/Power Release 7/10/2020 Approved DANIEL GONZALEZ