2201 S HARCOURT AVE 90016

Certificate Information: 2201 S HARCOURT AVE 90016

Application / Permit
19014-10000-04382
Plan Check / Job No.
B19LA16882
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SINGLE STORY BATHROOM ADDITION TO (E) 1-STORY SFD. "COMPLY WITH DEPARTMENT ORDER effective date 12/28/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". All permits shall be for the same time period limitation. CEIS Case Number is 838210.
Permit Issued
Issued on 2/26/2020
Issuing Office
Metro
Current Status
CofO Issued on 7/28/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/13/2019 APPLICANT
Assigned to Plan Check Engineer 8/21/2019 ZAW HAN
Corrections Issued 8/28/2019 ZAW HAN
Green Plans Picked Up 8/29/2019 APPLICANT
Quality Review Completed 9/4/2019 HERNAN ARREOLA
Building Plans Picked Up 9/6/2019 APPLICANT
Plan Check Approved 12/17/2019 ZAW HAN
Issued 2/26/2020 LADBS
CofO in Progress 7/27/2020 DANIEL GONZALEZ
Permit Finaled 7/28/2020 BRUCE TODD
CofO Issued 7/28/2020 BRUCE TODD
Permit Finaled 7/28/2020 BRUCE TODD

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/20/2019 CELINA MORENO
Roof/Waste drainage to street Cleared 9/20/2019 CELINA MORENO
Sewer availability Cleared 9/20/2019 CELINA MORENO
Green Code Cleared 11/8/2019 SEAN DANG

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Hong Kook; Lic. No.: C64529 839 S MUIRFIELD RD      LOS ANGELES, CA 90005

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/14/2020 Corrections Issued WILLIAM MICHALAK
Footing/Foundation/Slab 5/7/2020 Approved WILLIAM MICHALAK
BUILDING-Rough-Frame 5/27/2020 Approved WILLIAM MICHALAK
Drywall Nailing 5/27/2020 Approved WILLIAM MICHALAK
Final 5/27/2020 Corrections Issued WILLIAM MICHALAK
Green Building Final 5/27/2020 Approved WILLIAM MICHALAK
Green Building Rough 5/27/2020 Approved WILLIAM MICHALAK
MERV13>=Final 5/27/2020 Approved WILLIAM MICHALAK
MERV13>=Rough 5/27/2020 Approved WILLIAM MICHALAK
Smoke Detectors 5/27/2020 Corrections Issued WILLIAM MICHALAK
Final 5/29/2020 Corrections Issued WILLIAM MICHALAK
Smoke Detectors 5/29/2020 Approved WILLIAM MICHALAK
ELECTRICAL-Final 7/10/2020 Approved DANIEL GONZALEZ
Final 7/10/2020 Conditional Approval DANIEL GONZALEZ
HVAC-Final 7/10/2020 Approved DANIEL GONZALEZ
PLUMBING-Final 7/10/2020 Approved DANIEL GONZALEZ
Final 7/27/2020 OK to Issue CofO DANIEL GONZALEZ