6821 S VICTORIA AVE 90043

Certificate Information: 6821 S VICTORIA AVE 90043

Application / Permit
19014-10000-04374
Plan Check / Job No.
B19LA16874
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
CHANGE OF USE FROM MANUFACTURING TO OFFICE (CORPORATE HEADQUARTER OFFICE) ADD TENANT IMPROVEMENT; SECOND FLOOR ADDITION ( 18'-6" X 23'-9") INSIDE THE BUILDING. INTERIOR REMODELING CREATING OFFICES.
Permit Issued
Issued on 2/25/2020
Issuing Office
West Los Angeles
Current Status
CofO Corrected on 4/27/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/13/2019 APPLICANT
Green Plans Picked Up 8/21/2019 APPLICANT
Assigned to Plan Check Engineer 8/23/2019 FARSHAD ALIMOHAMADI
Disabled Access Plans Picked Up 8/26/2019 APPLICANT
Corrections Issued 8/28/2019 FARSHAD ALIMOHAMADI
Quality Review Completed 9/1/2019 YOUNG KIM
Building Plans Picked Up 9/11/2019 APPLICANT
Applicant returned to address corrections 11/15/2019 FARSHAD ALIMOHAMADI
Plan Check Approved 11/15/2019 FARSHAD ALIMOHAMADI
Issued 2/25/2020 LADBS
CofO in Progress 4/16/2021 TIMOTHY BUXTON
CofO Issued-Status Void 4/23/2021 ERNESTO CORRAL
Permit Finaled-Status Void 4/23/2021 ERNESTO CORRAL
Re-Activate Permit 4/27/2021 ERNESTO CORRAL
Permit Finaled 4/27/2021 ERNESTO CORRAL
CofO Corrected 4/27/2021 ERNESTO CORRAL
Permit Finaled 4/27/2021 ERNESTO CORRAL

Permit Application Clearance Information

Green Code Cleared 9/9/2019 SARAH ABOULHOSN
DAS Clearance Cleared 9/13/2019 WAI LAU
Low Impact Development Cleared 10/28/2019 ORVAL HERNANDEZ-MARCIAL
Permit Cleared 10/28/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 11/6/2019 PAMELA TENEZA
Roof/Waste drainage to street Cleared 11/6/2019 ERIK BEASLEY
Sewer availability Cleared 11/6/2019 PAMELA TENEZA
Trees in Parkway Cleared 11/8/2019 JOHN KIM
DAS Clearance Cleared 11/15/2019 FARSHAD ALIMOHAMADI
"D" conditions Cleared 11/18/2019 KYLE WINSTON
Community Plan Implem. Overlay Cleared 11/18/2019 KYLE WINSTON
Project located in CRA area Cleared 11/18/2019 KYLE WINSTON

Contact Information

Contractor Owner-Builder       ,
Engineer Gorgy,, Moheb Shohdy; Lic. No.: C53260 1545 VICTORY BLVD STE 102      GLENDALE, CA 91201

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 3/4/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Footing/Foundation/Slab 3/10/2020 Approved TIMOTHY BUXTON
Wood Frame 7/14/2020 Not Ready for Inspection LANNY MERRICK
Wood Frame 7/20/2020 Partial Approval LANNY MERRICK
Wood Frame 7/21/2020 Partial Approval LANNY MERRICK
Footing/Foundation/Slab 8/4/2020 Approved LANNY MERRICK
Drywall Nailing 8/6/2020 Approved TIMOTHY BUXTON
SGSOV-Seismic Gas S/O Valve 9/30/2020 SGSOV Not Ready LEOPOLDO MENDOZA
Final 10/9/2020 Corrections Issued LEOPOLDO MENDOZA
SGSOV-Seismic Gas S/O Valve 10/23/2020 SGSOV Not Ready LEOPOLDO MENDOZA
Pre-Inspection 10/29/2020 Corrections Issued LEOPOLDO MENDOZA
Deputy Drilled-In Anchors 11/2/2020 Conditional Approval RUSSELL BONVOULOIR
Deputy Steel/Welding 11/2/2020 Conditional Approval RUSSELL BONVOULOIR
Final 1/11/2021 Not Ready for Inspection LEOPOLDO MENDOZA
Green Building Final 1/11/2021 Approved LEOPOLDO MENDOZA
Green Building Rough 1/11/2021 Approved LEOPOLDO MENDOZA
Reinforced Masonry Frame 1/11/2021 Approved LEOPOLDO MENDOZA
SGSOV-Seismic Gas S/O Valve 1/11/2021 SGSOV No Gas LEOPOLDO MENDOZA
Smoke Detectors 1/11/2021 Approved LEOPOLDO MENDOZA
Final 4/8/2021 Conditional Approval TIMOTHY BUXTON