1142 1/2 E CENTURY BLVD 90002

Certificate Information: 1142 1/2 E CENTURY BLVD 90002

Application / Permit
19014-10000-04347
Plan Check / Job No.
B19LA16774
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO AND CONVERT THE EXISTING GARAGE INTO AN ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
Permit Issued
Issued on 1/29/2020
Issuing Office
Metro
Current Status
CofO Issued on 4/8/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/12/2019 APPLICANT
Assigned to Plan Check Engineer 9/5/2019 JOHNNY WU
Green Plans Picked Up 9/6/2019 APPLICANT
Corrections Issued 9/13/2019 JOHNNY WU
Quality Review Completed 10/1/2019 JOSE RODRIGUEZ
Building Plans Picked Up 10/15/2019 APPLICANT
Applicant returned to address corrections 12/13/2019 JOHNNY WU
Plan Check Approved 12/13/2019 JOHNNY WU
Issued 1/29/2020 LADBS
CofO in Progress 2/8/2021 EUGENE CASSIDY
Permit Finaled 4/8/2021 DEROLD HAUFF
CofO Issued 4/8/2021 DEROLD HAUFF
Permit Finaled 4/8/2021 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 12/4/2019 SARAH ABOULHOSN
Low Impact Development Cleared 12/5/2019 MITESH PATEL
Address approval Cleared 12/6/2019 JAMES MORALEZ
Eng Process Fee Ord 176,300 Cleared 12/6/2019 JAMES MORALEZ
Roof/Waste drainage to street Cleared 12/6/2019 JAMES MORALEZ
Sewer availability Cleared 12/6/2019 JAMES MORALEZ
Hydrant and Access approval Cleared 12/13/2019 JOHN CONNEALLY
ZI Cleared 12/13/2019 RICHARD REASER

Contact Information

Contractor Silva Israel Electric & Plumbing; Lic. No.: 524577-B 10977 DUNCAN AVE      LYNWOOD, CA 90262
Engineer Vega,, Cayetano Gonzalez; Lic. No.: C43117 9234 STAMPS AVE      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/12/2020 Corrections Issued WILLIAM ROSE
Underground Mechanical 2/19/2020 Not Ready for Inspection WILLIAM ROSE
Underground Mechanical 2/21/2020 Partial Approval WILLIAM ROSE
Footing/Foundation/Slab 3/17/2020 Approved WILLIAM ROSE
Underground Mechanical 3/31/2020 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 4/9/2020 No Access for Inspection BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 4/13/2020 Partial Approval BRIAN CHRISTIAN
ELECTRICAL-Rough 4/28/2020 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 4/28/2020 Corrections Issued EUGENE CASSIDY
Special/Order Compliance 4/28/2020 Approved EUGENE CASSIDY
ELECTRICAL-Rough 4/30/2020 Conditional Approval BRIAN CHRISTIAN
PLUMBING-Rough 4/30/2020 Approved BRIAN CHRISTIAN
BUILDING-Rough-Frame 5/19/2020 Not Ready for Inspection BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 5/19/2020 Corrections Issued BRIAN CHRISTIAN
Green Building Rough 5/19/2020 Not Ready for Inspection BRIAN CHRISTIAN
BUILDING-Rough-Frame 5/27/2020 Approved BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 5/27/2020 Approved BRIAN CHRISTIAN
Green Building Rough 5/27/2020 Approved BRIAN CHRISTIAN
HVAC-Rough 5/29/2020 Approved BRIAN CHRISTIAN
Rough-Elec/Plmb/HVAC 5/29/2020 Approved BRIAN CHRISTIAN
HVAC-Rough 6/3/2020 Corrections Issued BRIAN CHRISTIAN
Insulation 6/3/2020 Corrections Issued BRIAN CHRISTIAN
HVAC-Rough 6/4/2020 Approved BRIAN CHRISTIAN
Insulation 6/4/2020 Partial Approval BRIAN CHRISTIAN
Interior/Exterior Lathing 6/4/2020 Corrections Issued BRIAN CHRISTIAN
Insulation 6/9/2020 Approved BRIAN CHRISTIAN
Drywall Nailing 6/19/2020 Approved EUGENE CASSIDY
Interior/Exterior Lathing 6/19/2020 Approved EUGENE CASSIDY
Shower Pan 6/24/2020 Approved BRIAN CHRISTIAN
Excavation/Setback/Form/Re-Bar 8/31/2020 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 9/21/2020 Approved EUGENE CASSIDY
Final 10/8/2020 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 10/8/2020 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 10/8/2020 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 10/8/2020 Not Ready for Inspection EUGENE CASSIDY
Wood Frame 10/22/2020 Approved EUGENE CASSIDY
Final 11/2/2020 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 11/2/2020 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 11/2/2020 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 11/2/2020 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 11/12/2020 Not Ready for Inspection EUGENE CASSIDY
Final 12/7/2020 Corrections Issued EUGENE CASSIDY
Green Building Final 12/7/2020 Approved EUGENE CASSIDY
Smoke Detectors 12/7/2020 Approved EUGENE CASSIDY
Final 12/24/2020 Corrections Issued EUGENE CASSIDY
Final 1/5/2021 Corrections Issued EUGENE CASSIDY
Final 1/26/2021 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Final 2/8/2021 Approved EUGENE CASSIDY
Final 2/8/2021 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 2/8/2021 Approved EUGENE CASSIDY
PLUMBING-Final 2/8/2021 Approved EUGENE CASSIDY