4495 N LIBBIT AVE 91436
Certificate Information: 4495 N LIBBIT AVE 91436
- Application / Permit
- 19014-10000-04278
- Plan Check / Job No.
- B19LA16416
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED ADDITION AND REMODEL TO SINGLE FAMILY; WORK TO INCLUDE INTERIOR REMODEL, ADDITION OF ONE BAHROOM, ONE POWDER ROOM, ENCLOSING (E) COVERED PORCH AND REMODELING KITCHEN
- Permit Issued
- Issued on 1/13/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/7/2019 | MINA HABIB |
| Corrections Issued | 8/7/2019 | MINA HABIB |
| Applicant returned to address corrections | 12/23/2019 | SINA KHOSRAVI |
| Plan Check Approved | 1/7/2020 | MONICA RAMIREZ |
| Issued | 1/13/2020 | LADBS |
| CofO in Progress | 2/2/2021 | RONALD COWAN |
| CofO Issued | 2/17/2021 | DONALD SUNSERI |
| Permit Finaled | 2/17/2021 | DONALD SUNSERI |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/16/2019 | ERIK BEASLEY |
| Grading Pre-Inspection | Cleared | 12/16/2019 | KIRK LINKLATER |
| Roof/Waste drainage to street | Cleared | 12/16/2019 | ERIK BEASLEY |
Contact Information
| Contractor | Gross David W; Lic. No.: 845720-B | 4808 BREWSTER DRIVE TARZANA, CA 91356 |
| Engineer | Motavvef,, Nasser; Lic. No.: C40977 | 15335 MORRISON ST 370 SHERMAN OAKS, CA 91403 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/6/2020 | Corrections Issued | RONALD COWAN |
| Footing/Foundation/Slab | 2/13/2020 | Approved | RONALD COWAN |
| BUILDING-Rough-Frame | 5/6/2020 | Not Ready for Inspection | RONALD COWAN |
| ELECTRICAL-Rough | 5/6/2020 | Not Ready for Inspection | RONALD COWAN |
| PLUMBING-Rough | 5/6/2020 | Not Ready for Inspection | RONALD COWAN |
| BUILDING-Rough-Frame | 5/18/2020 | Approved | RONALD COWAN |
| ELECTRICAL-Rough | 5/18/2020 | Approved | RONALD COWAN |
| PLUMBING-Rough | 5/18/2020 | Approved | RONALD COWAN |
| Insulation | 5/26/2020 | Approved | RONALD COWAN |
| Interior/Exterior Lathing | 5/26/2020 | Partial Approval | RONALD COWAN |
| Shower Pan | 5/26/2020 | Approved | RONALD COWAN |
| Interior/Exterior Lathing | 6/9/2020 | Approved | RONALD COWAN |
| Drywall Nailing | 6/10/2020 | Approved | RONALD COWAN |
| Final | 10/6/2020 | Corrections Issued | RONALD COWAN |
| SGSOV-Seismic Gas S/O Valve | 10/6/2020 | SGSOV Not Ready | RONALD COWAN |
| Smoke Detectors | 10/6/2020 | Approved | RONALD COWAN |
| Final | 12/9/2020 | Corrections Issued | RONALD COWAN |
| SGSOV-Seismic Gas S/O Valve | 12/9/2020 | SGSOV Not Ready | RONALD COWAN |
| Final | 1/6/2021 | Corrections Issued | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 1/6/2021 | SGSOV Approved | DAVID SANDOVAL |
| Final | 1/21/2021 | Not Ready for Inspection | RONALD COWAN |
| Final | 1/28/2021 | OK to Issue CofO | RONALD COWAN |