6022 S HARCOURT AVE 90043
Certificate Information: 6022 S HARCOURT AVE 90043
- Application / Permit
- 19014-10000-04235
- Plan Check / Job No.
- B19LA16173
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition at 1st and new 2nd story and remodel to existing 1-story single family dwelling. Add family room, 1/2 bathroom, master bedroom and bathroom, enclose existing front porch (7' x 15') to enlarge existing bedroom, uncovered deck at 2nd floor, and covered patio at 1st floor.
- Permit Issued
- Issued on 3/23/2021
- Issuing Office
- Current Status
- CofO Issued on 6/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2019 | MICHAEL LOPEZ |
| Corrections Issued | 9/4/2019 | JEFFREY MACHADO |
| Quality Review Completed | 9/7/2019 | STANLEY RAAP |
| Building Plans Picked Up | 9/17/2019 | APPLICANT |
| Green Plans Picked Up | 9/17/2019 | APPLICANT |
| Applicant returned to address corrections | 2/13/2020 | MICHAEL LOPEZ |
| Plan Check Approved | 3/4/2020 | MICHAEL LOPEZ |
| Issued | 3/23/2021 | APPLICANT |
| CofO in Progress | 5/30/2023 | ENRIQUE MIRELES |
| CofO in Progress | 5/30/2023 | ENRIQUE MIRELES |
| Permit Finaled | 6/1/2023 | DEROLD HAUFF |
| CofO Issued | 6/1/2023 | DEROLD HAUFF |
| Permit Finaled | 6/1/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/17/2020 | THOMAS LANG |
| Sewer availability | Cleared | 1/17/2020 | THOMAS LANG |
| Green Code | Cleared | 1/28/2020 | COLIN LOREDO |
| Low Impact Development | Cleared | 2/13/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 2/13/2020 | EMIL KYUPELYAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Li,, Dacheng David; Lic. No.: C58075 | 3129 S HACIENDA BL STE 524 HACIENDA HEIGHTS, CA 91745 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/16/2021 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 4/27/2021 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2021 | Partial Inspection | SABAS ALONSO |
| Insulation | 5/11/2021 | Partial Approval | SABAS ALONSO |
| Drywall Nailing | 7/19/2021 | Not Ready for Inspection | HORACE FULTZ |
| PLUMBING-Rough | 7/19/2021 | Partial Approval | HORACE FULTZ |
| Wood Frame | 7/19/2021 | Corrections Issued | HORACE FULTZ |
| BUILDING-Rough-Frame | 7/21/2021 | Not Ready for Inspection | DAVID FEILER |
| Green Building Rough | 7/21/2021 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 7/21/2021 | Approved | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2021 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 7/27/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 7/27/2021 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 8/23/2021 | Corrections Issued | FREDDIE RIVERA |
| Interior/Exterior Lathing | 8/23/2021 | Partial Approval | FREDDIE RIVERA |
| Pre-Inspection | 8/23/2021 | Partial Inspection | JESUS PINEDA |
| ELECTRICAL-Rough | 8/31/2021 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 8/31/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 12/7/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Rough | 12/7/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Wood Frame | 12/7/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 12/16/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 12/16/2021 | Approved | FREDDIE RIVERA |
| Insulation | 12/21/2021 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 1/12/2022 | Approved | FREDDIE RIVERA |
| Shower Pan | 1/12/2022 | Corrections Issued | FREDDIE RIVERA |
| Shower Pan | 3/1/2022 | Approved | FREDDIE RIVERA |
| Service/Power Release | 6/27/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 8/30/2022 | Corrections Issued | ENRIQUE MIRELES |
| Service/Power Release | 9/19/2022 | Partial Approval | ENRIQUE MIRELES |
| ELECTRICAL-Final | 9/23/2022 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Final | 9/23/2022 | Approved | ENRIQUE MIRELES |
| Final | 12/1/2022 | Corrections Issued | ENRIQUE MIRELES |
| Final | 2/10/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 2/10/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 2/10/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 2/10/2023 | Approved | ENRIQUE MIRELES |
| Final | 2/21/2023 | Corrections Issued | ENRIQUE MIRELES |
| Final | 5/3/2023 | Corrections Issued | ENRIQUE MIRELES |
| Final | 5/26/2023 | OK to Issue CofO | ENRIQUE MIRELES |