1922-1924 W BAXTER ST 90039

Certificate Information: 1922-1924 W BAXTER ST 90039

Application / Permit
19014-10000-04201
Plan Check / Job No.
B19LA16085
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2 STORY ADDITION IN BACK OF HOUSE AND ATTACHED IRR. SHAPE 25'6"X40'10" ADU PER AB 494 AND SB 229 ON 2ND STORY.
Permit Issued
Issued on 1/3/2020
Issuing Office
Metro
Current Status
CofO Issued on 11/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/2/2019 APPLICANT
Assigned to Plan Check Engineer 8/29/2019 SERGIO GUTIERREZ
Corrections Issued 9/4/2019 SERGIO GUTIERREZ
Green Plans Picked Up 9/4/2019 APPLICANT
Quality Review Completed 9/12/2019 KESETE HAREGOT
Building Plans Picked Up 9/17/2019 APPLICANT
Applicant returned to address corrections 12/17/2019 SERGIO GUTIERREZ
Plan Check Approved 12/31/2019 SERGIO GUTIERREZ
Issued 1/3/2020 LADBS
CofO in Progress 11/9/2021 THOMAS LOGRASSO
Permit Finaled 11/19/2021 DEROLD HAUFF
CofO Issued 11/19/2021 DEROLD HAUFF
Permit Finaled 11/19/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/26/2019 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 9/26/2019 THOMAS LANG
BHO/Hillside ordinance Cleared 9/27/2019 THOMAS LANG
BHO/Hillside ordinance Cleared 9/27/2019 THOMAS LANG
BHO/Hillside ordinance Cleared 9/27/2019 THOMAS LANG
Green Code Cleared 11/18/2019 VIVIAN LAO
Sewer availability Cleared 11/22/2019 ELAINE LEI
Low Impact Development Cleared 11/26/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 11/26/2019 THOMAS LANG
Stormwater Pollution Mitigatn Cleared 11/26/2019 JORGE MEJIA LEMUS
GPI Written Notices Cleared 12/20/2019 SERGIO GUTIERREZ
Grading Pre-Inspection Cleared 12/20/2019 SERGIO GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 5525 CANOGA AVE APT 208      WOODLAND HILLS, CA 91367

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/17/2020 Corrections Issued MICHAEL FAUNCE
Excavation/Setback/Form/Re-Bar 3/27/2020 Partial Approval KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 4/1/2020 Partial Approval ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 4/7/2020 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 4/17/2020 Partial Inspection ROBERT VORHIS
Footing/Foundation/Slab 4/23/2020 Approved SCOTT FINNILA
Wood Frame 5/5/2020 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 5/11/2020 Partial Approval MATTHEW NUCKOLLS
Floor/Roof Diaphrgm/Shear Wall 6/4/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Rough 6/16/2020 Corrections Issued DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 6/16/2020 Not Ready for Inspection DAVID CHAN
Special/Order Compliance 6/16/2020 Approved DAVID CHAN
ELECTRICAL-Rough 6/30/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 6/30/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 7/7/2020 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 7/7/2020 Partial Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/7/2020 Partial Approval SCOTT FINNILA
Green Building Rough 7/7/2020 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 7/7/2020 Partial Approval SCOTT FINNILA
Verify Sprinkler Sign Off 7/7/2020 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 7/17/2020 Not Ready for Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 7/17/2020 Corrections Issued JOSEPH MCGARRY
Green Building Rough 7/17/2020 Not Ready for Inspection JOSEPH MCGARRY
HVAC-Rough 7/17/2020 Corrections Issued JOSEPH MCGARRY
PLUMBING-Rough 7/17/2020 Partial Approval JOSEPH MCGARRY
Verify Sprinkler Sign Off 7/17/2020 Not Ready for Inspection JOSEPH MCGARRY
BUILDING-Rough-Frame 7/30/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Rough 7/30/2020 Approved KATHRYN BUTTERWORTH
Green Building Rough 7/30/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Rough 7/30/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 7/30/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 7/30/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 8/10/2020 Corrections Issued STUART CHAPMAN
Green Building Rough 8/10/2020 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 8/10/2020 Approved STUART CHAPMAN
BUILDING-Rough-Frame 8/17/2020 Partial Approval JOSEPH MCGARRY
HVAC-Rough 8/17/2020 Approved JOSEPH MCGARRY
PLUMBING-Rough 8/17/2020 Approved JOSEPH MCGARRY
Insulation 8/27/2020 Corrections Issued RUBEN SALAS
Interior/Exterior Lathing 8/27/2020 Partial Approval RUBEN SALAS
Insulation 8/31/2020 Corrections Issued STUART CHAPMAN
Drywall Nailing 9/8/2020 Approved OSVALDO PARAMO
Insulation 9/8/2020 Approved OSVALDO PARAMO
Interior/Exterior Lathing 9/28/2020 Partial Approval HAMIK HARTOUNIAN
Shower Pan 9/28/2020 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 1/7/2021 Approved RUBEN SALAS
Final 1/7/2021 Corrections Issued RUBEN SALAS
Green Building Final 1/7/2021 Not Ready for Inspection RUBEN SALAS
SGSOV-Seismic Gas S/O Valve 1/7/2021 SGSOV Not Ready RUBEN SALAS
Smoke Detectors 1/7/2021 Not Ready for Inspection RUBEN SALAS
ELECTRICAL-Final 2/5/2021 Corrections Issued SCOTT FINNILA
PLUMBING-Final 2/5/2021 Corrections Issued SCOTT FINNILA
ELECTRICAL-Final 2/12/2021 Not Ready for Inspection COREY HUPP
PLUMBING-Final 2/12/2021 Not Ready for Inspection COREY HUPP
ELECTRICAL-Final 5/14/2021 Corrections Issued ROBERT VORHIS
Final 5/14/2021 Not Ready for Inspection ROBERT VORHIS
Green Building Final 5/14/2021 Approved ROBERT VORHIS
HVAC-Final 5/14/2021 Approved ROBERT VORHIS
PLUMBING-Final 5/14/2021 Approved ROBERT VORHIS
SGSOV-Seismic Gas S/O Valve 5/14/2021 SGSOV Not Ready ROBERT VORHIS
Smoke Detectors 5/14/2021 Approved ROBERT VORHIS
Final 6/11/2021 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 6/11/2021 SGSOV Approved HAMIK HARTOUNIAN
Final 6/21/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 8/17/2021 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Final 8/31/2021 No Access for Inspection SABAS ALONSO
Final 8/31/2021 No Access for Inspection SABAS ALONSO
ELECTRICAL-Final 9/8/2021 Not Ready for Inspection THOMAS LOGRASSO
Final 9/8/2021 Not Ready for Inspection THOMAS LOGRASSO
Final 10/27/2021 Corrections Issued THOMAS LOGRASSO
Final 11/9/2021 OK to Issue CofO THOMAS LOGRASSO
Service/Power Release 11/9/2021 Approved THOMAS LOGRASSO