1309 1/2 W HEPNER AVE 90041
Certificate Information: 1309 1/2 W HEPNER AVE 90041
- Application / Permit
- 19014-10000-04148
- Plan Check / Job No.
- B19LA15864
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED ADDITION TO AND CONVERSION OF (E) GARAGE TO ADU PER AB 494 AND SB 229 PER ENGINEER DESIGN.
- Permit Issued
- Issued on 4/15/2022
- Issuing Office
- Current Status
- CofO Issued on 12/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2019 | SINA KHOSRAVI |
| Corrections Issued | 8/5/2019 | SINA KHOSRAVI |
| Plan Check Approved | 12/12/2019 | KEVIN MORALES |
| Issued | 4/15/2022 | APPLICANT |
| Building Plans Picked Up | 4/28/2022 | APPLICANT |
| CofO in Progress | 12/16/2022 | CRAIG VAUGHAN |
| CofO in Progress | 12/16/2022 | CRAIG VAUGHAN |
| CofO Issued | 12/21/2022 | DEROLD HAUFF |
| Permit Finaled | 12/21/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/5/2019 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 8/5/2019 | SINA KHOSRAVI |
| Eng Process Fee Ord 176,300 | Cleared | 8/20/2019 | JEANIE LAM |
| Sewer availability | Cleared | 8/20/2019 | JEANIE LAM |
| Low Impact Development | Cleared | 9/9/2019 | ORVAL HERNANDEZ-MARCI |
| Construction near power lines | Cleared | 12/12/2019 | OSCAR CASTRO |
| Roof/Waste drainage to street | Cleared | 12/12/2019 | CELINA MORENO |
Contact Information
| Contractor | Golden West Heating And Cooling; Lic. No.: 1046260-B | 1933 JEFFERSON DRIVE PASADENA, CA 91104 |
| Engineer | Singh,, Jasbir; Lic. No.: C38767 | 16194 EASTRIDGE CT CHINO HILLS, CA 91709 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/6/2022 | Conditional Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 5/12/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 5/13/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 5/31/2022 | Partial Approval | CRAIG VAUGHAN |
| HVAC-Rough | 6/30/2022 | Not Ready for Inspection | AMY COLIN |
| Sewer | 6/30/2022 | Approved | AMY COLIN |
| Underground Mechanical | 6/30/2022 | Approved | AMY COLIN |
| BUILDING-Rough-Frame | 7/11/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 7/11/2022 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 7/11/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 7/11/2022 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 7/11/2022 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 7/11/2022 | Approved | CRAIG VAUGHAN |
| Wood Frame | 7/15/2022 | Corrections Issued | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2022 | Corrections Issued | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2022 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 8/31/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 9/6/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 10/24/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 10/24/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 10/24/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Service/Power Release | 10/24/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Service/Power Release | 11/3/2022 | Corrections Issued | CRAIG VAUGHAN |
| Service/Power Release | 11/30/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 12/1/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 12/1/2022 | Corrections Issued | CRAIG VAUGHAN |
| Final | 12/1/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Final | 12/1/2022 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 12/1/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 12/1/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 12/1/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 12/1/2022 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 12/1/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 12/13/2022 | Approved | CRAIG VAUGHAN |
| Final | 12/13/2022 | OK to Issue CofO | CRAIG VAUGHAN |
| Service/Power Release | 12/13/2022 | Approved | CRAIG VAUGHAN |