4307-4309 S COMPTON AVE 90011
Certificate Information: 4307-4309 S COMPTON AVE 90011
- Application / Permit
- 19014-10000-04114
- Plan Check / Job No.
- B19LA15714
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2 STORY GROUND FLOOR ADDITION TO EXISTING 1 STORY SINGLE FAMILY DWELLING CREATING A DUPLEX
- Permit Issued
- Issued on 11/15/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/24/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2019 | SERGIO GUTIERREZ |
| Green Plans Picked Up | 8/14/2019 | APPLICANT |
| Corrections Issued | 8/16/2019 | SERGIO GUTIERREZ |
| Quality Review Completed | 8/16/2019 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 8/20/2019 | APPLICANT |
| Applicant returned to address corrections | 11/5/2019 | SERGIO GUTIERREZ |
| Plan Check Approved | 11/8/2019 | SERGIO GUTIERREZ |
| Issued | 11/15/2019 | LADBS |
| CofO in Progress | 9/2/2020 | ROBERT MCDOWELL |
| Permit Finaled | 9/24/2020 | DEROLD HAUFF |
| CofO Issued | 9/24/2020 | DEROLD HAUFF |
| Permit Finaled | 9/24/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/18/2019 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 9/18/2019 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 9/18/2019 | ROBERT DUFF |
| Sewer availability | Cleared | 9/18/2019 | ERIK BEASLEY |
| Green Code | Cleared | 10/10/2019 | VIVIAN LAO |
| Community Plan Implem. Overlay | Cleared | 10/18/2019 | ANNA VAN |
| Low Impact Development | Cleared | 10/18/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 10/18/2019 | CELINA MORENO |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/18/2019 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 12/30/2019 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 2/6/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 2/6/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 2/28/2020 | Not Ready for Inspection | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2020 | Not Ready for Inspection | HORACE FULTZ |
| Green Building Rough | 2/28/2020 | Not Ready for Inspection | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| Rough-Elec/Plmb/HVAC | 3/5/2020 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 3/10/2020 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2020 | Approved | JOAQUIN GREENOUGH |
| Insulation | 3/11/2020 | Partial Approval | JOAQUIN GREENOUGH |
| Rough-Elec/Plmb/HVAC | 3/11/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 3/18/2020 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 3/18/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 3/18/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 3/18/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 3/18/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 3/20/2020 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 3/20/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| HVAC-Rough | 3/20/2020 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 3/20/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| Wood Frame | 3/24/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 4/6/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 4/6/2020 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 4/6/2020 | Partial Inspection | CHRIS CHRISTENSEN |
| Insulation | 4/10/2020 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 4/21/2020 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 4/21/2020 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 6/18/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 6/18/2020 | Approved | ROBERT MCDOWELL |
| Final | 6/18/2020 | Conditional Approval | ROBERT MCDOWELL |
| Green Building Final | 6/18/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 6/18/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Final | 6/18/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 6/18/2020 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 6/18/2020 | SGSOV Approved | ROBERT MCDOWELL |
| Smoke Detectors | 6/18/2020 | Approved | ROBERT MCDOWELL |
| Service/Power Release | 8/7/2020 | Approved | ROBERT MCDOWELL |