226 N WINDSOR BLVD 90004

Certificate Information: 226 N WINDSOR BLVD 90004

Application / Permit
19014-10000-04106
Plan Check / Job No.
B19LA15686
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL AND ADDITION TO (E) SFD. FIRSTFLOOR ADDITION OF 333 SF AND NEW SECOND FLOOR ADDITION (33' X 34').
Permit Issued
Issued on 10/24/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2019 APPLICANT
Assigned to Plan Check Engineer 8/15/2019 CRISTINA SALAZAR
Green Plans Picked Up 8/16/2019 APPLICANT
Corrections Issued 8/19/2019 CRISTINA SALAZAR
Quality Review Completed 8/24/2019 STANLEY RAAP
Building Plans Picked Up 8/30/2019 APPLICANT
Applicant returned to address corrections 9/12/2019 CRISTINA SALAZAR
Applicant returned to address corrections 9/30/2019 CRISTINA SALAZAR
Plan Check Approved 10/9/2019 CRISTINA SALAZAR
Issued 10/24/2019 LADBS
CofO in Progress 3/10/2021 CHRIS CHRISTENSEN
Permit Finaled 3/20/2021 DEROLD HAUFF
CofO Issued 3/20/2021 DEROLD HAUFF
Permit Finaled 3/20/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/30/2019 ELAINE LEI
Green Code Cleared 8/30/2019 NEGAR NEJAD
Sewer availability Cleared 8/30/2019 ELAINE LEI
City Hist. Cultural Monument Cleared 9/30/2019 MAX LODER
HPOZ Cleared 9/30/2019 MAX LODER
Low Impact Development Cleared 10/2/2019 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 10/9/2019 THOMAS LANG

Contact Information

Contractor Giagni D J Inc; Lic. No.: 683169-B 1108 1/2 PALMS BLVD      VENICE, CA 90291
Engineer Ekmekji,, Steve Eli; Lic. No.: C66727 19281 BERCLAIR LANE      TARZANA, CA 91356

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/8/2020 Approved LUIS BARRALES
Deputy Drilled-In Anchors 1/22/2020 Approved COREY HUPP
Excavation/Setback/Form/Re-Bar 1/22/2020 Conditional Approval COREY HUPP
BUILDING-Rough-Frame 1/31/2020 Partial Approval LUIS BARRALES
PLUMBING-Rough 2/4/2020 Partial Approval BRAD BESCOS
BUILDING-Rough-Frame 2/14/2020 Partial Inspection BRAD BESCOS
Green Building Rough 2/14/2020 Not Ready for Inspection BRAD BESCOS
Floor/Roof Diaphrgm/Shear Wall 2/20/2020 Partial Approval RAUL BARAJAS
Deputy Wood Construction 3/3/2020 No Access for Inspection BRAD BESCOS
Wood Frame 3/4/2020 No Access for Inspection BRAD BESCOS
BUILDING-Rough-Frame 3/10/2020 Partial Approval KATHRYN BUTTERWORTH
Green Building Rough 3/10/2020 Partial Approval KATHRYN BUTTERWORTH
Gas Test 4/2/2020 Approved JOSEPH MCGARRY
HVAC-Rough 4/2/2020 Approved JOSEPH MCGARRY
PLUMBING-Rough 4/2/2020 Partial Approval JOSEPH MCGARRY
Underground Mechanical 4/2/2020 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 4/14/2020 Approved ARTHUR SARGSYAN
Shower Pan 4/14/2020 Approved ARTHUR SARGSYAN
Deputy Wood Construction 4/17/2020 Approved ARTHUR SARGSYAN
Wood Frame 4/20/2020 Approved CHRIS CHRISTENSEN
Insulation 5/11/2020 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 5/13/2020 Approved ARTHUR SARGSYAN
Drywall Nailing 5/15/2020 Approved ELMER BLAND
Green Building Rough 5/15/2020 Approved ELMER BLAND
Interior/Exterior Lathing 5/15/2020 Approved ELMER BLAND
Interior/Exterior Lathing 6/4/2020 Approved ARTHUR SARGSYAN
Service/Power Release 10/7/2020 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 11/12/2020 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 11/12/2020 Approved CHRIS CHRISTENSEN
Final 11/12/2020 OK to Issue CofO CHRIS CHRISTENSEN
Footing/Foundation/Slab 11/12/2020 Approved CHRIS CHRISTENSEN
Green Building Final 11/12/2020 Approved CHRIS CHRISTENSEN
HVAC-Final 11/12/2020 Approved CHRIS CHRISTENSEN
PLUMBING-Final 11/12/2020 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 11/12/2020 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 11/12/2020 Approved CHRIS CHRISTENSEN