3441 S HILLCREST DR 90016
Certificate Information: 3441 S HILLCREST DR 90016
- Application / Permit
- 19014-10000-03970
- Plan Check / Job No.
- B19LA15176
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) ACCESSORY DWELLING UNIT PER AB 494 & SB 229
- Permit Issued
- Issued on 11/4/2021
- Issuing Office
- Current Status
- CofO Issued on 12/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2019 | LAMAR DAVIS |
| Corrections Issued | 8/12/2019 | LAMAR DAVIS |
| Quality Review Completed | 8/22/2019 | HERNAN ARREOLA |
| Green Plans Picked Up | 8/29/2019 | APPLICANT |
| Plan Check Approved | 2/24/2020 | LAMAR DAVIS |
| Issued | 11/4/2021 | APPLICANT |
| Building Plans Picked Up | 11/4/2021 | APPLICANT |
| CofO in Progress | 12/27/2023 | STUART CHAPMAN |
| CofO in Progress | 12/28/2023 | LILIANA PORTILLO |
| Permit Finaled | 12/29/2023 | DEROLD HAUFF |
| CofO Issued | 12/29/2023 | DEROLD HAUFF |
| Permit Finaled | 12/29/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/10/2019 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/10/2019 | EMIL KYUPELYAN |
| Flood clearance | Cleared | 10/2/2019 | TUYEN LE |
| Sewer availability | Cleared | 10/3/2019 | EMIL KYUPELYAN |
| Low Impact Development | Cleared | 10/21/2019 | MARTIN FRAGOSO |
| Green Code | Cleared | 1/21/2020 | VIVIAN LAO |
| Green Code | Cleared | 1/23/2020 | VIVIAN LAO |
| Hydrant and Access approval | Cleared | 2/13/2020 | JEREMY CARTER |
| Roof/Waste drainage to street | Cleared | 2/13/2020 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| FLOOD-Elevation Certificate | 6/23/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Footing/Foundation/Slab | 6/23/2022 | Corrections Issued | STUART CHAPMAN |
| FLOOD-Elevation Certificate | 6/30/2022 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 6/30/2022 | Approved | STUART CHAPMAN |
| Insulation | 7/19/2022 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 10/13/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 10/13/2022 | Approved | STUART CHAPMAN |
| FLOOD-Proofing Certificate | 10/13/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 10/13/2022 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 10/13/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 10/13/2022 | Approved | STUART CHAPMAN |
| Sewer | 10/13/2022 | Approved | STUART CHAPMAN |
| Underground Mechanical | 10/13/2022 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 10/13/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 12/6/2022 | Partial Approval | STUART CHAPMAN |
| Insulation | 12/29/2022 | Approved | DONALD CRICHLOW |
| Drywall Nailing | 1/23/2023 | Partial Approval | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 10/5/2023 | Approved | CALEB MEISTER |
| Drywall Nailing | 10/5/2023 | Approved | CALEB MEISTER |
| Final | 10/5/2023 | Corrections Issued | CALEB MEISTER |
| Green Building Final | 10/5/2023 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Rough | 10/5/2023 | Approved | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 10/5/2023 | SGSOV Approved | CALEB MEISTER |
| Service/Power Release | 10/5/2023 | Not Ready for Inspection | CALEB MEISTER |
| Smoke Detectors | 10/5/2023 | Approved | CALEB MEISTER |
| Final | 11/15/2023 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Final | 11/15/2023 | Not Ready for Inspection | CALEB MEISTER |
| Service/Power Release | 11/15/2023 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Final | 12/22/2023 | Approved | STUART CHAPMAN |
| Final | 12/22/2023 | OK to Issue CofO | STUART CHAPMAN |
| Green Building Final | 12/22/2023 | Approved | STUART CHAPMAN |
| HVAC-Final | 12/22/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 12/22/2023 | Approved | STUART CHAPMAN |
| Service/Power Release | 12/22/2023 | Approved | STUART CHAPMAN |
| Final | 12/27/2023 | OK to Issue CofO | LILIANA PORTILLO |