5429 N ALCOVE AVE 91607
Certificate Information: 5429 N ALCOVE AVE 91607
- Application / Permit
- 19014-10000-03896
- Plan Check / Job No.
- B19LA14863
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 69' -1" X ____ Addition to existing single family dwelling.
- Permit Issued
- Issued on 10/21/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/31/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2019 | SHANGQIN XIE |
| Corrections Issued | 8/7/2019 | SHANGQIN XIE |
| Green Plans Picked Up | 8/15/2019 | APPLICANT |
| Quality Review Completed | 8/17/2019 | STANLEY RAAP |
| Building Plans Picked Up | 8/20/2019 | APPLICANT |
| Plan Check Approved | 10/18/2019 | ZAW HAN |
| Issued | 10/21/2019 | LADBS |
| CofO in Progress | 7/7/2021 | DANIEL ORRANTE |
| CofO in Progress | 7/12/2021 | RICHARD DOCKUS |
| CofO Issued | 7/31/2021 | MICHAEL SMITH |
| Permit Finaled | 7/31/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/12/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 9/12/2019 | ERIK BEASLEY |
| Specific Plan | Cleared | 9/24/2019 | MARIANNE KING |
| Low Impact Development | Cleared | 9/26/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 9/27/2019 | ERIK BEASLEY |
| Green Code | Cleared | 9/30/2019 | VIVIAN LAO |
| Miscellaneous | Cleared | 10/1/2019 | GABRIEL ROBLES |
Contact Information
| Engineer | Aronianpour,, Eilan; Lic. No.: C88101 | 7242 JELLICO AVE LAKE BALBOA, CA 91406 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/9/2020 | Approved | BRENDAN LOONEY |
| Wood Frame | 7/6/2020 | Partial Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 4/8/2021 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 4/8/2021 | Approved | RICHARD DOCKUS |
| Green Building Final | 4/8/2021 | Approved | RICHARD DOCKUS |
| Green Building Rough | 4/8/2021 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 4/8/2021 | SGSOV Not Ready | RICHARD DOCKUS |
| ELECTRICAL-Final | 5/26/2021 | Conditional Approval | RICHARD DOCKUS |
| Final | 5/26/2021 | Conditional Approval | RICHARD DOCKUS |
| HVAC-Final | 5/26/2021 | Approved | RICHARD DOCKUS |
| MERV13>=Final | 5/26/2021 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 5/26/2021 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 5/26/2021 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 5/26/2021 | Approved | RICHARD DOCKUS |
| Final | 5/27/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Final | 7/9/2021 | OK to Issue CofO | RICHARD DOCKUS |