2061 N MCPHERSON AVE 90032

Certificate Information: 2061 N MCPHERSON AVE 90032

Application / Permit
19014-10000-03856
Plan Check / Job No.
B19LA14742
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition to an (E) 1-story Single Family Dwelling.
Permit Issued
Issued on 1/16/2020
Issuing Office
Metro
Current Status
CofO Issued on 10/8/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2019 APPLICANT
Assigned to Plan Check Engineer 8/8/2019 HELEN NGUYEN
Corrections Issued 8/21/2019 HELEN NGUYEN
Quality Review Completed 9/8/2019 YOUNG KIM
Building Plans Picked Up 9/16/2019 APPLICANT
Green Plans Picked Up 9/16/2019 APPLICANT
Plan Check Approved 12/11/2019 HELEN NGUYEN
Issued 1/16/2020 LADBS
CofO in Progress 10/8/2020 ELMER BLAND
Permit Finaled 10/8/2020 DEROLD HAUFF
CofO Issued 10/8/2020 DEROLD HAUFF
Permit Finaled 10/8/2020 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/16/2019 PATRICK MISCHLICH
Eng Process Fee Ord 176,300 Cleared 10/17/2019 JEANIE LAM
Green Code Cleared 10/17/2019 NEGAR NEJAD
Roof/Waste drainage to street Cleared 10/17/2019 JEANIE LAM
Sewer availability Cleared 10/17/2019 JEANIE LAM
GPI Written Notices Cleared 12/11/2019 HELEN NGUYEN

Contact Information

Contractor Owner-Builder       ,
Engineer Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 2160 PARNELL WY      ALTADENA, CA 91001

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/4/2020 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 3/4/2020 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 4/1/2020 Partial Approval ENRIQUE MIRELES
Green Building Rough 4/1/2020 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 4/1/2020 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 5/13/2020 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 5/13/2020 Partial Approval OSVALDO PARAMO
HVAC-Rough 5/13/2020 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 5/13/2020 Corrections Issued OSVALDO PARAMO
BUILDING-Rough-Frame 5/22/2020 Approved MATTHEW NUCKOLLS
ELECTRICAL-Rough 5/22/2020 Conditional Approval MATTHEW NUCKOLLS
Green Building Rough 5/22/2020 Approved MATTHEW NUCKOLLS
PLUMBING-Rough 5/22/2020 Approved MATTHEW NUCKOLLS
Service/Power Release 5/22/2020 Approved MATTHEW NUCKOLLS
Insulation 6/10/2020 Corrections Issued CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 6/10/2020 Partial Approval CHRISTOPHER DELLEFIELD
Insulation 6/11/2020 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 6/17/2020 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 6/17/2020 Partial Approval CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 8/26/2020 Approved ENRIQUE MIRELES
Green Building Final 8/26/2020 Approved ENRIQUE MIRELES
HVAC-Final 8/26/2020 Approved ENRIQUE MIRELES
PLUMBING-Final 8/26/2020 Corrections Issued ENRIQUE MIRELES
Final 10/2/2020 Partial Approval RUBEN SALAS
SGSOV-Seismic Gas S/O Valve 10/2/2020 SGSOV Approved RUBEN SALAS
Smoke Detectors 10/2/2020 Approved RUBEN SALAS
Final 10/8/2020 OK to Issue CofO ELMER BLAND
PLUMBING-Final 10/8/2020 Approved ELMER BLAND