3191 N TOPPINGTON DR 90210
Certificate Information: 3191 N TOPPINGTON DR 90210
- Application / Permit
- 19014-10000-03844
- Plan Check / Job No.
- B19LA14706
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND REMODELING OF 2-STORY SINGLE FAMILY RESIDENCE
- Permit Issued
- Issued on 11/4/2021
- Issuing Office
- Current Status
- CofO Issued on 7/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2019 | VU NGUYEN |
| Corrections Issued | 8/27/2019 | VU NGUYEN |
| Green Plans Picked Up | 9/6/2019 | APPLICANT |
| Quality Review Completed | 9/16/2019 | JOSE RODRIGUEZ |
| Building Plans Picked Up | 10/1/2019 | APPLICANT |
| Applicant returned to address corrections | 1/14/2020 | VU NGUYEN |
| Applicant returned to address corrections | 1/30/2020 | VU NGUYEN |
| Applicant returned to address corrections | 3/2/2020 | VU NGUYEN |
| Applicant returned to address corrections | 3/10/2020 | VU NGUYEN |
| Plan Check Approved | 3/17/2020 | VU NGUYEN |
| Issued | 11/4/2021 | APPLICANT |
| CofO in Progress | 6/27/2025 | SEAN HAUPT |
| Permit Finaled | 7/7/2025 | RICHARD STEINBACH |
| CofO Issued | 7/7/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/7/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/9/2019 | WALTER RAMIREZ |
| Disturb/Remove Protected Trees | Cleared | 10/9/2019 | JOHN KIM |
| BHO/Hillside ordinance | Cleared | 12/12/2019 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 12/12/2019 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 12/12/2019 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 12/12/2019 | DINAH GARIN |
| Miscellaneous | Cleared | 12/12/2019 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 12/12/2019 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 12/12/2019 | SARAH GOLDMAN |
| Sewer availability | Cleared | 12/12/2019 | DINAH GARIN |
| Specific Plan | Cleared | 12/12/2019 | SARAH GOLDMAN |
| ZA Case | Cleared | 12/12/2019 | SARAH GOLDMAN |
| Hydrant and Access approval | Cleared | 1/6/2020 | JEREMY CARTER |
| Low Impact Development | Cleared | 1/30/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 1/30/2020 | EMIL KYUPELYAN |
| Green Code | Cleared | 2/27/2020 | VIVIAN LAO |
| Excavation more than 5-ft deep | Cleared | 3/10/2020 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 3/10/2020 | VU NGUYEN |
| Grading Pre-Inspection | Cleared | 3/10/2020 | VU NGUYEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Pirbadian,, Amir; Lic. No.: C72413 | 5435 BALBOA BLVD 214 ENCINO, CA 91342 |
| Geologist | Haney,, Harry Drew; Lic. No.: EG2091 | 9003 DE SOTO AVENUE CANOGA PARK, CA 91304 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/27/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Drilled-In Anchors | 6/14/2022 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 6/29/2022 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 7/6/2022 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 7/6/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 7/6/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 7/11/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 7/11/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 7/11/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Reinf. Concrete | 7/12/2022 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 7/25/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Steel/Welding | 8/12/2022 | No Access for Inspection | KENNETH NAGLE |
| Deputy Steel/Welding | 8/15/2022 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Drilled-In Anchors | 9/16/2022 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 4/21/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 4/21/2023 | Corrections Issued | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 4/27/2023 | Corrections Issued | MICHAEL PELHAM |
| HVAC-Rough | 4/27/2023 | Corrections Issued | MICHAEL PELHAM |
| PLUMBING-Rough | 5/2/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 5/2/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 5/15/2023 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 5/15/2023 | Approved | JESUS RODRIGUEZ |
| Deputy Wood Construction | 5/17/2023 | Conditional Approval | MICHAEL PELHAM |
| HVAC-Rough | 5/25/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 6/9/2023 | Corrections Issued | BRENDAN LOONEY |
| Interior/Exterior Lathing | 6/9/2023 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Rough | 6/12/2023 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 6/14/2023 | Partial Approval | BRENDAN LOONEY |
| Interior/Exterior Lathing | 6/14/2023 | Partial Approval | BRENDAN LOONEY |
| ELECTRICAL-Rough | 6/21/2023 | Conditional Approval | BRENDAN LOONEY |
| HVAC-Rough | 6/26/2023 | Corrections Issued | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 6/30/2023 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 6/30/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Verify Sprinkler Sign Off | 6/30/2023 | Approved | BRENDAN LOONEY |
| Deputy Steel/Welding | 7/11/2023 | Conditional Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2023 | Partial Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 9/27/2023 | Approved | BRENDAN LOONEY |
| Green Building Rough | 9/27/2023 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 9/27/2023 | Partial Approval | BRENDAN LOONEY |
| Underground Mechanical | 9/27/2023 | Corrections Issued | BRENDAN LOONEY |
| Insulation | 10/5/2023 | Conditional Approval | BRENDAN LOONEY |
| Drywall Nailing | 10/17/2023 | Approved | BRENDAN LOONEY |
| Underground Mechanical | 12/18/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Underground Mechanical | 12/26/2023 | Partial Approval | BRENDAN LOONEY |
| Sewer | 3/12/2024 | Approved | SEAN HAUPT |
| Underground Mechanical | 3/12/2024 | Approved | SEAN HAUPT |
| Service/Power Release | 12/31/2024 | Not Ready for Inspection | SEAN HAUPT |
| ELECTRICAL-Final | 1/9/2025 | Approved | SEAN HAUPT |
| Service/Power Release | 1/9/2025 | Approved | SEAN HAUPT |
| HVAC-Final | 4/14/2025 | Approved | SEAN HAUPT |
| PLUMBING-Final | 4/14/2025 | Corrections Issued | SEAN HAUPT |
| PLUMBING-Final | 5/12/2025 | Approved | SEAN HAUPT |
| Final | 6/26/2025 | OK to Issue CofO | SEAN HAUPT |
| Footing/Foundation/Slab | 6/26/2025 | Approved | SEAN HAUPT |
| Green Building Final | 6/26/2025 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 6/26/2025 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 6/26/2025 | Approved | SEAN HAUPT |
| Structural Steel Frame | 6/26/2025 | Approved | SEAN HAUPT |