- CONVERSION OF (E) GARAGE AT REAR TO ADU PER AB 494 AND SB 229. NEW ATTACHED STORAGE ROOM.
- Permit Issued
- Issued on 7/1/2021
- Issuing Office
- Current Status
- CofO Issued on 4/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2019 | KEVIN MORALES |
| Corrections Issued | 7/12/2019 | KEVIN MORALES |
| Applicant returned to address corrections | 5/21/2021 | ZAW HAN |
| Plan Check Approved | 5/25/2021 | ZAW HAN |
| Issued | 7/1/2021 | APPLICANT |
| Building Plans Picked Up | 7/6/2021 | APPLICANT |
| CofO in Progress | 4/13/2022 | JOSE AVILA |
| Permit Finaled | 4/19/2022 | DEROLD HAUFF |
| CofO Issued | 4/19/2022 | DEROLD HAUFF |
| Permit Finaled | 4/19/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/12/2019 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 7/12/2019 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/30/2019 | ERIK BEASLEY |
Contact Information
| Contractor | Built To Perfection Inc; Lic. No.: 837987-B | 22222 SHERMAN WAY #202 CANOGA PARK, CA 91303 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/13/2021 | Conditional Approval | CALEB MEISTER |
| Footing/Foundation/Slab | 8/13/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| METHANE-Barrier | 8/13/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| METHANE-Subgrade | 8/13/2021 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 8/26/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 8/30/2021 | Partial Approval | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 9/8/2021 | Approved | ALAN MORELOS |
| Footing/Foundation/Slab | 9/9/2021 | Partial Approval | JOAQUIN GREENOUGH |
| METHANE-Barrier | 9/9/2021 | Partial Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 9/23/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 9/23/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 9/23/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Rough | 9/23/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 9/23/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Gas Test | 10/22/2021 | Approved | JOSE AVILA |
| HVAC-Rough | 10/22/2021 | Not Ready for Inspection | JOSE AVILA |
| PLUMBING-Rough | 10/22/2021 | Partial Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 10/26/2021 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 10/26/2021 | Approved | JOSE AVILA |
| Green Building Rough | 10/26/2021 | Approved | JOSE AVILA |
| HVAC-Rough | 10/26/2021 | Not Ready for Inspection | JOSE AVILA |
| METHANE-Rough | 10/26/2021 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 11/1/2021 | Not Ready for Inspection | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 11/4/2021 | Partial Approval | LILIANA PORTILLO |
| Insulation | 11/9/2021 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2021 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 11/19/2021 | Approved | JOSE AVILA |
| Drywall Nailing | 11/24/2021 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 2/18/2022 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 2/18/2022 | Approved | JOSE AVILA |
| Green Building Final | 2/18/2022 | Approved | JOSE AVILA |
| METHANE-Barrier | 2/18/2022 | Approved | JOSE AVILA |
| PLUMBING-Final | 2/18/2022 | Partial Approval | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 2/18/2022 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 2/18/2022 | Approved | JOSE AVILA |
| Final | 3/10/2022 | Corrections Issued | JOSE AVILA |
| Final | 3/24/2022 | Partial Approval | JOSE AVILA |
| Final | 4/13/2022 | OK to Issue CofO | JOSE AVILA |