1739 S ORANGE GROVE AVE 90019

Certificate Information: 1739 S ORANGE GROVE AVE 90019

Application / Permit
19014-10000-03742
Plan Check / Job No.
B19LA14347
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF (E) GARAGE AT REAR TO ADU PER AB 494 AND SB 229. NEW ATTACHED STORAGE ROOM.
Permit Issued
Issued on 7/1/2021
Issuing Office
Current Status
CofO Issued on 4/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2019 APPLICANT
Assigned to Plan Check Engineer 7/12/2019 KEVIN MORALES
Corrections Issued 7/12/2019 KEVIN MORALES
Applicant returned to address corrections 5/21/2021 ZAW HAN
Plan Check Approved 5/25/2021 ZAW HAN
Issued 7/1/2021 APPLICANT
Building Plans Picked Up 7/6/2021 APPLICANT
CofO in Progress 4/13/2022 JOSE AVILA
Permit Finaled 4/19/2022 DEROLD HAUFF
CofO Issued 4/19/2022 DEROLD HAUFF
Permit Finaled 4/19/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/12/2019 ADRIAN SANCHEZ
Sewer availability Cleared 7/12/2019 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 7/30/2019 ERIK BEASLEY

Contact Information

Contractor Built To Perfection Inc; Lic. No.: 837987-B 22222 SHERMAN WAY #202      CANOGA PARK, CA 91303

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/13/2021 Conditional Approval CALEB MEISTER
Footing/Foundation/Slab 8/13/2021 Partial Approval KATHRYN BUTTERWORTH
METHANE-Barrier 8/13/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
METHANE-Subgrade 8/13/2021 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 8/26/2021 Corrections Issued KATHRYN BUTTERWORTH
PLUMBING-Rough 8/30/2021 Partial Approval STUART CHAPMAN
Deputy Drilled-In Anchors 9/8/2021 Approved ALAN MORELOS
Footing/Foundation/Slab 9/9/2021 Partial Approval JOAQUIN GREENOUGH
METHANE-Barrier 9/9/2021 Partial Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 9/23/2021 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 9/23/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Rough 9/23/2021 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Rough 9/23/2021 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 9/23/2021 Corrections Issued JOAQUIN GREENOUGH
Gas Test 10/22/2021 Approved JOSE AVILA
HVAC-Rough 10/22/2021 Not Ready for Inspection JOSE AVILA
PLUMBING-Rough 10/22/2021 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 10/26/2021 Partial Approval JOSE AVILA
ELECTRICAL-Rough 10/26/2021 Approved JOSE AVILA
Green Building Rough 10/26/2021 Approved JOSE AVILA
HVAC-Rough 10/26/2021 Not Ready for Inspection JOSE AVILA
METHANE-Rough 10/26/2021 Approved JOSE AVILA
Interior/Exterior Lathing 11/1/2021 Not Ready for Inspection JUSTIN HAWLEY
Interior/Exterior Lathing 11/4/2021 Partial Approval LILIANA PORTILLO
Insulation 11/9/2021 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 11/15/2021 Approved JOSE AVILA
Interior/Exterior Lathing 11/19/2021 Approved JOSE AVILA
Drywall Nailing 11/24/2021 Approved JOSE AVILA
BUILDING-Rough-Frame 2/18/2022 Approved JOSE AVILA
Footing/Foundation/Slab 2/18/2022 Approved JOSE AVILA
Green Building Final 2/18/2022 Approved JOSE AVILA
METHANE-Barrier 2/18/2022 Approved JOSE AVILA
PLUMBING-Final 2/18/2022 Partial Approval JOSE AVILA
SGSOV-Seismic Gas S/O Valve 2/18/2022 SGSOV Approved JOSE AVILA
Smoke Detectors 2/18/2022 Approved JOSE AVILA
Final 3/10/2022 Corrections Issued JOSE AVILA
Final 3/24/2022 Partial Approval JOSE AVILA
Final 4/13/2022 OK to Issue CofO JOSE AVILA