8313 S WESTLAWN AVE 90045

Certificate Information: 8313 S WESTLAWN AVE 90045

Application / Permit
19014-10000-03723
Plan Check / Job No.
B19LA14274
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED ADDITION AND ALTERATION TO SFD TO EXTEND KITCHEN, DINING AND LIVING ROOM AT REAR AND CONVERT LIVING ROOM TO BEDROOM AT FRONT
Permit Issued
Issued on 1/10/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2019 APPLICANT
Assigned to Plan Check Engineer 7/11/2019 SINA KHOSRAVI
Corrections Issued 7/11/2019 SINA KHOSRAVI
Plan Check Approved 7/18/2019 HELEN NGUYEN
Issued 1/10/2020 LADBS
CofO in Progress 5/6/2026 JESUS PINEDA
Permit Finaled 5/11/2026 RICHARD STEINBACH
CofO Issued 5/11/2026 RICHARD STEINBACH
Permit Finaled 5/11/2026 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/11/2019 JEANIE LAM
Roof/Waste drainage to street Cleared 7/11/2019 JEANIE LAM
Sewer availability Cleared 7/11/2019 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Wong,, Jim Chu Man; Lic. No.: C69393 PO BOX 373      GLENDORA, CA 91740

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/27/2020 Not Ready for Inspection JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 4/1/2020 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 4/1/2020 Partial Approval JUAN VALENZUELA
ELECTRICAL-Rough 5/13/2020 Not Ready for Inspection JOHNNY MIRANDA
Gas Test 5/13/2020 Approved JOHNNY MIRANDA
PLUMBING-Rough 5/13/2020 Corrections Issued JOHNNY MIRANDA
Sewer 5/13/2020 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 5/18/2020 Partial Approval DAVID FEILER
Footing/Foundation/Slab 5/21/2020 Approved CRAIG DAVIS
ELECTRICAL-Rough 8/14/2020 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 9/8/2020 Partial Approval JUAN VALENZUELA
Insulation 9/8/2020 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 9/8/2020 Corrections Issued JUAN VALENZUELA
Drywall Nailing 10/8/2020 Partial Approval JUAN VALENZUELA
Green Building Rough 10/8/2020 Partial Approval JUAN VALENZUELA
Interior/Exterior Lathing 10/8/2020 Partial Approval JUAN VALENZUELA
Insulation 11/6/2020 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 11/6/2020 Approved JUAN VALENZUELA
Shower Pan 11/13/2020 Approved KENNETH NAGLE
PLUMBING-Rough 2/9/2021 Partial Approval DAVID HEINE
Deputy Steel/Welding 3/9/2021 Partial Approval PIERRE VEGA
Deputy Steel/Welding 3/10/2021 Approved DAVID HEINE
Deputy Steel/Welding 3/11/2021 Partial Approval DAVID HEINE
Deputy Steel/Welding 3/12/2021 No Access for Inspection DAVID HEINE
Excavation/Setback/Form/Re-Bar 3/12/2021 Approved DAVID HEINE
Deputy Steel/Welding 3/15/2021 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 4/16/2021 Corrections Issued BRENDAN LOONEY
Green Building Rough 4/16/2021 Not Ready for Inspection BRENDAN LOONEY
BUILDING-Rough-Frame 5/4/2021 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Rough 5/4/2021 Corrections Issued BRENDAN LOONEY
Green Building Rough 5/4/2021 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 5/4/2021 Corrections Issued BRENDAN LOONEY
BUILDING-Rough-Frame 5/18/2021 Approved BRENDAN LOONEY
ELECTRICAL-Rough 5/18/2021 Approved BRENDAN LOONEY
Gas Test 5/18/2021 Partial Approval BRENDAN LOONEY
Green Building Rough 5/18/2021 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 5/18/2021 Approved BRENDAN LOONEY
Insulation 5/26/2021 Not Ready for Inspection ADAM ESCOTO
Interior/Exterior Lathing 5/26/2021 Approved ADAM ESCOTO
Insulation 5/27/2021 Approved ADAM ESCOTO
Drywall Nailing 7/2/2021 Approved BRENDAN LOONEY
Green Building Rough 7/2/2021 Approved BRENDAN LOONEY
ELECTRICAL-Final 4/28/2026 Approved JESUS PINEDA
Final 4/28/2026 Corrections Issued JESUS PINEDA
Green Building Final 4/28/2026 Approved JESUS PINEDA
HVAC-Final 4/28/2026 Approved JESUS PINEDA
PLUMBING-Final 4/28/2026 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 4/28/2026 SGSOV Approved JESUS PINEDA
Service/Power Release 4/28/2026 Approved JESUS PINEDA
Smoke Detectors 4/28/2026 Approved JESUS PINEDA
Final 5/6/2026 OK to Issue CofO JESUS PINEDA