2011 W HILL DR 90041

Certificate Information: 2011 W HILL DR 90041

Application / Permit
19014-10000-03702
Plan Check / Job No.
B19LA14162
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Two Story Addition to existing two story Single Family Dwelling
Permit Issued
Issued on 5/8/2020
Issuing Office
Metro
Current Status
Issued on 5/8/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/10/2019 APPLICANT
Assigned to Plan Check Engineer 8/8/2019 DINA ELKINAWY
Corrections Issued 8/19/2019 DINA ELKINAWY
Quality Review Completed 8/23/2019 QUAN NGHIEM
Building Plans Picked Up 8/30/2019 APPLICANT
Green Plans Picked Up 8/30/2019 APPLICANT
Applicant returned to address corrections 1/14/2020 DINA ELKINAWY
Plan Check Approved 1/16/2020 DINA ELKINAWY
Issued 5/8/2020 LADBS

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 10/17/2019 EMIL KYUPELYAN
BHO/Hillside ordinance Cleared 10/17/2019 EMIL KYUPELYAN
BHO/Hillside ordinance Cleared 10/17/2019 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 10/17/2019 EMIL KYUPELYAN
Hydrant and Access approval Cleared 10/17/2019 JOHN CONNEALLY
Roof/Waste drainage to street Cleared 10/17/2019 EMIL KYUPELYAN
Sewer availability Cleared 10/17/2019 EMIL KYUPELYAN
Green Code Cleared 12/2/2019 VIVIAN LAO
Grading Pre-Inspection Cleared 1/13/2020 DINA ELKINAWY

Contact Information

Contractor Owner-Builder       ,
Engineer Hazrati,, Kayvan Naghib; Lic. No.: C60556 465 PUERTO DEL MAR      PACIFIC PALISADES, CA 90272

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/19/2020 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 5/28/2020 Approved CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 5/29/2020 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 6/9/2020 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 7/21/2020 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 7/21/2020 Corrections Issued CRAIG VAUGHAN
Green Building Rough 7/21/2020 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Rough 7/21/2020 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 7/21/2020 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 7/28/2020 Partial Approval CRAIG VAUGHAN
HVAC-Rough 7/28/2020 Approved CRAIG VAUGHAN
Wood Frame 7/28/2020 Approved CRAIG VAUGHAN
Insulation 7/31/2020 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 7/31/2020 Partial Approval CRAIG VAUGHAN
Drywall Nailing 8/10/2020 Approved COREY HUPP
Green Building Rough 8/10/2020 Approved COREY HUPP
Interior/Exterior Lathing 10/15/2020 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 11/12/2020 Approved CRAIG VAUGHAN
Final 11/12/2020 Corrections Issued CRAIG VAUGHAN
Green Building Final 11/12/2020 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 11/12/2020 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 11/12/2020 Corrections Issued CRAIG VAUGHAN
Final 1/14/2021 Conditional Approval CRAIG VAUGHAN
Smoke Detectors 1/14/2021 Approved CRAIG VAUGHAN
Final 4/6/2023 Corrections Issued CRAIG VAUGHAN