9528 S COMPTON AVE 90002

Certificate Information: 9528 S COMPTON AVE 90002

Application / Permit
19014-10000-03692
Plan Check / Job No.
B19LA14120
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2-STORY ADDITION TO EXISTING DETACHED GARAGE, CONVERTING TO 2-STORY A.D.U.
Permit Issued
Issued on 11/10/2020
Issuing Office
Current Status
CofO Issued on 3/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/10/2019 APPLICANT
Assigned to Plan Check Engineer 8/8/2019 DINA ELKINAWY
Green Plans Picked Up 8/14/2019 APPLICANT
Corrections Issued 8/19/2019 DINA ELKINAWY
Quality Review Completed 8/23/2019 QUAN NGHIEM
Building Plans Picked Up 9/24/2019 APPLICANT
Applicant returned to address corrections 11/13/2019 DINA ELKINAWY
Plan Check Approved 9/4/2020 DINA ELKINAWY
Issued 11/10/2020 APPLICANT
CofO in Progress 3/2/2022 JOHN KLARIN
Permit Finaled 3/14/2022 DEROLD HAUFF
CofO Issued 3/14/2022 DEROLD HAUFF
Permit Finaled 3/14/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/25/2019 ELAINE LEI
Permit Cleared 10/25/2019 ELAINE LEI
Green Code Cleared 10/31/2019 KHEDER ALRAZAA
ZI Cleared 2/13/2020 TERRI OSBORNE
Eng Process Fee Ord 176,300 Cleared 2/25/2020 THOMAS LANG
Low Impact Development Cleared 2/25/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 2/25/2020 ERIK BEASLEY
Sewer availability Cleared 2/25/2020 THOMAS LANG

Contact Information

Contractor Cervantes Construction; Lic. No.: 554143-B 10335 GORMAN AVENUE      LOS ANGELES, CA 90002
Engineer Chen,, Yeshen Jason; Lic. No.: C40169 20601 ALDA CT      WALNUT, CA 91789
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/25/2021 Conditional Approval WILLIAM ROSE
Footing/Foundation/Slab 5/27/2021 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 6/9/2021 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 6/9/2021 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 6/11/2021 Approved EUGENE CASSIDY
Pre-Inspection 6/11/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 8/17/2021 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 8/17/2021 Corrections Issued EUGENE CASSIDY
Green Building Rough 8/17/2021 Not Ready for Inspection EUGENE CASSIDY
HVAC-Rough 8/17/2021 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 8/17/2021 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 8/19/2021 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 8/19/2021 Approved EUGENE CASSIDY
Green Building Rough 8/19/2021 Not Ready for Inspection EUGENE CASSIDY
HVAC-Rough 8/19/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 8/19/2021 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 9/3/2021 Approved EUGENE CASSIDY
Insulation 9/3/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 9/3/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 9/14/2021 Approved EUGENE CASSIDY
Drywall Nailing 9/14/2021 Approved EUGENE CASSIDY
Green Building Rough 9/14/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 9/14/2021 Approved EUGENE CASSIDY
Final 11/23/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 11/23/2021 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 11/23/2021 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 11/23/2021 Corrections Issued EUGENE CASSIDY
Final 1/5/2022 Corrections Issued EUGENE CASSIDY
Green Building Final 1/5/2022 Approved EUGENE CASSIDY
Smoke Detectors 1/5/2022 Not Ready for Inspection EUGENE CASSIDY
Final 2/14/2022 Corrections Issued JOHN KLARIN
Smoke Detectors 2/14/2022 Partial Approval JOHN KLARIN
Pre-Inspection 2/17/2022 Corrections Issued ALIZAH MAYAGOITIA
Final 2/23/2022 No Access for Inspection JOHN KLARIN
Smoke Detectors 2/23/2022 No Access for Inspection JOHN KLARIN
ELECTRICAL-Final 3/1/2022 Approved JOHN KLARIN
Final 3/1/2022 OK to Issue CofO JOHN KLARIN
HVAC-Final 3/1/2022 Approved JOHN KLARIN
PLUMBING-Final 3/1/2022 Approved JOHN KLARIN
Smoke Detectors 3/1/2022 Approved JOHN KLARIN