874 S WELLESLEY AVE 90049
Certificate Information: 874 S WELLESLEY AVE 90049
- Application / Permit
- 19014-10000-03681
- Plan Check / Job No.
- B19LA14108
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. NEW ADU ATTACHED TO (E) 2-CAR GARAGE & EXTEND (E) GARAGE
- Permit Issued
- Issued on 11/4/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/24/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2019 | DANIEL SANJUAN |
| Green Plans Picked Up | 8/13/2019 | APPLICANT |
| Corrections Issued | 8/14/2019 | DANIEL SANJUAN |
| Quality Review Completed | 8/15/2019 | HERNAN ARREOLA |
| Building Plans Picked Up | 8/22/2019 | APPLICANT |
| Plan Check Approved | 9/27/2019 | DANIEL SANJUAN |
| Issued | 11/4/2019 | LADBS |
| CofO in Progress | 6/19/2020 | KENNETH NAGLE |
| Permit Finaled | 6/24/2020 | VINCENT COTTON |
| CofO Issued | 6/24/2020 | VINCENT COTTON |
| Permit Finaled | 6/24/2020 | VINCENT COTTON |
Permit Application Clearance Information
| Address approval | Cleared | 9/13/2019 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2019 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 9/13/2019 | JOHN CONNEALLY |
| Miscellaneous | Cleared | 9/13/2019 | HERNAN ARREOLA |
| Roof/Waste drainage to street | Cleared | 9/13/2019 | THOMAS LANG |
| Sewer availability | Cleared | 9/13/2019 | THOMAS LANG |
| Green Code | Cleared | 9/24/2019 | COLIN LOREDO |
Contact Information
| Contractor | Hallmark Construction Inc; Lic. No.: 843062-B | 8424 COLIMA ROAD WHITTIER, CA 90605 |
| Engineer | Adefeso,, Wole Dayo; Lic. No.: C63361 | 1608 CENTINELA AVE #13 INGLEWOOD, CA 90302 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/16/2019 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 12/19/2019 | Approved | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 12/19/2019 | Approved | OGANES TARAKHCHYAN |
| Underground Mechanical | 12/19/2019 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 2/5/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Drywall Nailing | 2/5/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 2/5/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 2/5/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 2/5/2020 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 2/5/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 2/6/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 3/2/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 3/2/2020 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 3/9/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Rough | 3/9/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 3/16/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 3/16/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 3/16/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 3/16/2020 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 3/16/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 3/23/2020 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 3/23/2020 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 3/23/2020 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 3/23/2020 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 3/23/2020 | Approved | OGANES TARAKHCHYAN |
| Insulation | 3/27/2020 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 3/27/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Drywall Nailing | 4/3/2020 | Approved | OGANES TARAKHCHYAN |
| Underground Mechanical | 4/3/2020 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 5/11/2020 | Approved | OGANES TARAKHCHYAN |
| Final | 5/11/2020 | Conditional Approval | OGANES TARAKHCHYAN |
| Green Building Final | 5/11/2020 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 5/11/2020 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 5/11/2020 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 5/11/2020 | SGSOV Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 5/11/2020 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 5/11/2020 | Approved | OGANES TARAKHCHYAN |