2706 W 75TH ST 90043
Certificate Information: 2706 W 75TH ST 90043
- Application / Permit
- 19014-10000-03670
- Plan Check / Job No.
- B19LA14081
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New ACCESSORY DWELLING UNIT (ADU) PER AB 494 AND SB 229; SCOPE WILL ALSO CONSIST OF A 660 SQ-FT ADDITION (22' X 30').
- Permit Issued
- Issued on 10/8/2020
- Issuing Office
- Current Status
- CofO Issued on 10/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2019 | SINA KHOSRAVI |
| Corrections Issued | 7/11/2019 | SINA KHOSRAVI |
| Plan Check Approved | 7/15/2019 | MICHAEL LOPEZ |
| Issued | 10/8/2020 | APPLICANT |
| Building Plans Picked Up | 4/19/2021 | APPLICANT |
| CofO in Progress | 9/30/2024 | AMIR NAZARIAN |
| Permit Finaled | 10/1/2024 | RUBEN SALAS |
| CofO Issued | 10/1/2024 | RUBEN SALAS |
| Permit Finaled | 10/1/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/11/2019 | ELENA LOPEZ |
| Construction near power lines | Cleared | 7/11/2019 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/11/2019 | ELENA LOPEZ |
| Roof/Waste drainage to street | Cleared | 7/11/2019 | ELENA LOPEZ |
| Sewer availability | Cleared | 7/11/2019 | ELENA LOPEZ |
| Low Impact Development | Cleared | 7/27/2020 | JORGE MEJIA LEMUS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/29/2021 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 7/29/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 6/3/2024 | Not Ready for Inspection | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 9/23/2024 | SGSOV Not Ready | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 9/27/2024 | Approved | AMIR NAZARIAN |
| Drywall Nailing | 9/27/2024 | Approved | AMIR NAZARIAN |
| ELECTRICAL-Final | 9/27/2024 | Approved | AMIR NAZARIAN |
| Enclosure/Fence | 9/27/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Excavation/Setback/Form/Re-Bar | 9/27/2024 | Approved | AMIR NAZARIAN |
| FLOOD-Elevation Certificate | 9/27/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Final | 9/27/2024 | OK to Issue CofO | AMIR NAZARIAN |
| Footing/Foundation/Slab | 9/27/2024 | Approved | AMIR NAZARIAN |
| Green Building Final | 9/27/2024 | Approved | AMIR NAZARIAN |
| Green Building Rough | 9/27/2024 | Approved | AMIR NAZARIAN |
| Light Gage Steel Frame | 9/27/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Piling/Pier/Caisson | 9/27/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Pre-Gunite | 9/27/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Pre-Inspection | 9/27/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 9/27/2024 | SGSOV Approved | AMIR NAZARIAN |
| SWPPP-Const. Storm Water | 9/27/2024 | Not Required | AMIR NAZARIAN |
| Service/Power Release | 9/27/2024 | Approved | AMIR NAZARIAN |
| Shower Pan | 9/27/2024 | Approved | AMIR NAZARIAN |
| Smoke Detectors | 9/27/2024 | Approved | AMIR NAZARIAN |
| Verify Rec and Parks Fee Memo | 9/27/2024 | Approved | AMIR NAZARIAN |
| Verify Sprinkler Sign Off | 9/27/2024 | Approved | AMIR NAZARIAN |