2706 W 75TH ST 90043

Certificate Information: 2706 W 75TH ST 90043

Application / Permit
19014-10000-03670
Plan Check / Job No.
B19LA14081
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New ACCESSORY DWELLING UNIT (ADU) PER AB 494 AND SB 229; SCOPE WILL ALSO CONSIST OF A 660 SQ-FT ADDITION (22' X 30').
Permit Issued
Issued on 10/8/2020
Issuing Office
Current Status
CofO Issued on 10/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2019 APPLICANT
Assigned to Plan Check Engineer 7/11/2019 SINA KHOSRAVI
Corrections Issued 7/11/2019 SINA KHOSRAVI
Plan Check Approved 7/15/2019 MICHAEL LOPEZ
Issued 10/8/2020 APPLICANT
Building Plans Picked Up 4/19/2021 APPLICANT
CofO in Progress 9/30/2024 AMIR NAZARIAN
Permit Finaled 10/1/2024 RUBEN SALAS
CofO Issued 10/1/2024 RUBEN SALAS
Permit Finaled 10/1/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/11/2019 ELENA LOPEZ
Construction near power lines Cleared 7/11/2019 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 7/11/2019 ELENA LOPEZ
Roof/Waste drainage to street Cleared 7/11/2019 ELENA LOPEZ
Sewer availability Cleared 7/11/2019 ELENA LOPEZ
Low Impact Development Cleared 7/27/2020 JORGE MEJIA LEMUS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/29/2021 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 7/29/2021 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Rough 6/3/2024 Not Ready for Inspection JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 9/23/2024 SGSOV Not Ready AMIR NAZARIAN
BUILDING-Rough-Frame 9/27/2024 Approved AMIR NAZARIAN
Drywall Nailing 9/27/2024 Approved AMIR NAZARIAN
ELECTRICAL-Final 9/27/2024 Approved AMIR NAZARIAN
Enclosure/Fence 9/27/2024 Not Ready for Inspection AMIR NAZARIAN
Excavation/Setback/Form/Re-Bar 9/27/2024 Approved AMIR NAZARIAN
FLOOD-Elevation Certificate 9/27/2024 Not Ready for Inspection AMIR NAZARIAN
Final 9/27/2024 OK to Issue CofO AMIR NAZARIAN
Footing/Foundation/Slab 9/27/2024 Approved AMIR NAZARIAN
Green Building Final 9/27/2024 Approved AMIR NAZARIAN
Green Building Rough 9/27/2024 Approved AMIR NAZARIAN
Light Gage Steel Frame 9/27/2024 Not Ready for Inspection AMIR NAZARIAN
Piling/Pier/Caisson 9/27/2024 Not Ready for Inspection AMIR NAZARIAN
Pre-Gunite 9/27/2024 Not Ready for Inspection AMIR NAZARIAN
Pre-Inspection 9/27/2024 Not Ready for Inspection AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 9/27/2024 SGSOV Approved AMIR NAZARIAN
SWPPP-Const. Storm Water 9/27/2024 Not Required AMIR NAZARIAN
Service/Power Release 9/27/2024 Approved AMIR NAZARIAN
Shower Pan 9/27/2024 Approved AMIR NAZARIAN
Smoke Detectors 9/27/2024 Approved AMIR NAZARIAN
Verify Rec and Parks Fee Memo 9/27/2024 Approved AMIR NAZARIAN
Verify Sprinkler Sign Off 9/27/2024 Approved AMIR NAZARIAN