4231 W VIRGINIA AVE 90029
Certificate Information: 4231 W VIRGINIA AVE 90029
- Application / Permit
- 19014-10000-03637
- Plan Check / Job No.
- B19LA13942
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL BATHROOM AND KITCHEN IN (E) SINGLE FAMILY DWELLING, ADD 2-STORY ADDITION TO THE BACK TO CREATE A POWDER ROOM, 2 BEDROOMS, 2 BATHROOMS AND A ROOF DECK.
- Permit Issued
- Issued on 2/5/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2019 | JOHNNY WU |
| Corrections Issued | 8/6/2019 | JOHNNY WU |
| Quality Review Completed | 8/19/2019 | JOSE RODRIGUEZ |
| Building Plans Picked Up | 8/21/2019 | APPLICANT |
| Green Plans Picked Up | 9/23/2019 | APPLICANT |
| Applicant returned to address corrections | 11/5/2019 | JOHNNY WU |
| Applicant returned to address corrections | 1/28/2020 | JOHNNY WU |
| Plan Check Approved | 1/30/2020 | JOHNNY WU |
| Issued | 2/5/2020 | LADBS |
| CofO in Progress | 9/3/2022 | FREDDIE RIVERA |
| Permit Finaled | 9/19/2022 | RONALD MYRICK |
| CofO Issued | 9/19/2022 | RONALD MYRICK |
| Permit Finaled | 9/19/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/23/2019 | KIRK LINKLATER |
| Green Code | Cleared | 12/16/2019 | VIVIAN LAO |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2020 | THOMAS LANG |
| Low Impact Development | Cleared | 1/6/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 1/6/2020 | THOMAS LANG |
| Sewer availability | Cleared | 1/6/2020 | THOMAS LANG |
Contact Information
| Contractor | Centrepoint Construction; Lic. No.: 1032400-B | 19100 VENTURA BLVD STE 20 TARZANA, CA 91356 |
| Engineer | Andrada,, Aprile Larracas; Lic. No.: C81097 | 27356 DEARBORN DRIVE VALENCIA, CA 91354 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/11/2020 | Approved | ROBERT CORNELL |
| Deputy Drilled-In Anchors | 3/18/2020 | Conditional Approval | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 3/27/2020 | Partial Inspection | ROBERT VORHIS |
| PLUMBING-Rough | 3/27/2020 | Approved | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 4/14/2020 | Partial Approval | ROBERT VORHIS |
| Deputy Reinf. Concrete | 5/1/2020 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 5/18/2020 | Approved | ROBERT VORHIS |
| Footing/Foundation/Slab | 6/3/2020 | Partial Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2020 | Partial Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2020 | Partial Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2020 | Partial Approval | ROBERT VORHIS |
| Interior/Exterior Lathing | 8/6/2020 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 8/28/2020 | Approved | DAVID CHAN |
| HVAC-Rough | 8/28/2020 | Approved | DAVID CHAN |
| PLUMBING-Rough | 8/28/2020 | Corrections Issued | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2020 | Partial Approval | ROBERT VORHIS |
| PLUMBING-Rough | 9/9/2020 | Approved | ROBERT VORHIS |
| BUILDING-Rough-Frame | 9/29/2020 | Approved | ROBERT VORHIS |
| Green Building Rough | 9/29/2020 | Approved | ROBERT VORHIS |
| Insulation | 10/5/2020 | Corrections Issued | DONALD CRICHLOW |
| Interior/Exterior Lathing | 10/5/2020 | Partial Approval | DONALD CRICHLOW |
| Insulation | 10/8/2020 | Approved | DONALD CRICHLOW |
| Drywall Nailing | 10/15/2020 | Approved | ROBERT VORHIS |
| Shower Pan | 10/27/2020 | Approved | ROBERT VORHIS |
| Interior/Exterior Lathing | 11/5/2020 | Approved | RUBEN SALAS |
| Footing/Foundation/Slab | 2/11/2021 | Approved | ROBERT VORHIS |
| Green Building Final | 2/11/2021 | Not Ready for Inspection | ROBERT VORHIS |
| PLUMBING-Final | 2/11/2021 | Approved | ROBERT VORHIS |
| SGSOV-Seismic Gas S/O Valve | 2/11/2021 | SGSOV Not Ready | ROBERT VORHIS |
| Smoke Detectors | 2/11/2021 | Approved | ROBERT VORHIS |
| ELECTRICAL-Final | 2/23/2021 | Approved | ROBERT VORHIS |
| Green Building Final | 2/23/2021 | Approved | ROBERT VORHIS |
| HVAC-Final | 2/23/2021 | Approved | ROBERT VORHIS |
| Service/Power Release | 2/23/2021 | Approved | ROBERT VORHIS |
| SGSOV-Seismic Gas S/O Valve | 3/9/2021 | SGSOV Approved | SCOTT FINNILA |
| Gas Test | 3/25/2021 | Approved | RUBEN SALAS |
| Final | 7/1/2021 | Conditional Approval | ROBERT VORHIS |