7548 N TROOST AVE 91605
Certificate Information: 7548 N TROOST AVE 91605
- Application / Permit
- 19014-10000-03626
- Plan Check / Job No.
- B19LA13895
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to rear of (E) SFD to create a new bathroom. All works per Wood Frame Prescriptive Provisions.
- Permit Issued
- Issued on 3/19/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2019 | HELEN NGUYEN |
| Corrections Issued | 7/30/2019 | HELEN NGUYEN |
| Quality Review Completed | 8/19/2019 | YOUNG KIM |
| Building Plans Picked Up | 9/17/2019 | APPLICANT |
| Green Plans Picked Up | 9/17/2019 | APPLICANT |
| Applicant returned to address corrections | 1/7/2020 | HELEN NGUYEN |
| Plan Check Approved | 1/13/2020 | HELEN NGUYEN |
| Issued | 3/19/2020 | LADBS |
| CofO in Progress | 1/17/2025 | JOSE AVILA |
| Permit Finaled | 1/22/2025 | RUBEN SALAS |
| CofO Issued | 1/22/2025 | RUBEN SALAS |
| Permit Finaled | 1/22/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Green Code | Cleared | 11/14/2019 | NEGAR NEJAD |
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2019 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 11/22/2019 | THOMAS LANG |
| Sewer availability | Cleared | 12/16/2019 | EMIL KYUPELYAN |
Contact Information
| Contractor | L A Builders And Design Group Inc; Lic. No.: 1020905-B | 15500 ERWIN ST STE 146 VAN NUYS, CA 91411 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/1/2020 | Approved | BEAU COLLINS |
| Underground Mechanical | 4/9/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Underground Mechanical | 4/27/2020 | Approved | RAYMOND KEHOE |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2020 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2020 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 9/14/2020 | Approved | DANIEL DREW |
| PLUMBING-Rough | 9/14/2020 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 9/18/2020 | Approved | DANIEL DREW |
| Green Building Rough | 9/18/2020 | Approved | DANIEL DREW |
| Insulation | 9/18/2020 | Approved | DANIEL DREW |
| Drywall Nailing | 8/11/2021 | Approved | AMY COLIN |
| Final | 1/27/2022 | Not Ready for Inspection | DAVID MATSON |
| Green Building Final | 1/27/2022 | Approved | DAVID MATSON |
| Smoke Detectors | 1/27/2022 | Corrections Issued | DAVID MATSON |
| Final | 2/3/2022 | Partial Approval | THOMAS FINNILA |
| Smoke Detectors | 2/3/2022 | Approved | THOMAS FINNILA |
| Final | 1/17/2025 | OK to Issue CofO | JOSE AVILA |